IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Clear Lake State Park  Date: 11/20/2025  Project No.  
  East Restroom and Shower Building  County:   CERRO GORDO  Time: 11:00 a.m.  23-03-17-10

 

 
1
2
3
Estimated Cost: $250,000.00
Contractor: 
Sadler Construction IncMatt Construction IncLarson Contracting Central, LLC
Funding Source: 50% Infrastructure, 50% Federal-Land and Water Conservation Fund, 1905 N Iowa Ave
203 Y Ave
508 W Main St
Eagle Grove IA  50533Sumner IA  50674Lake Mills IA  50450
Plan Sets Requested: 2
Quantities
515-448-3856563-578-8418641-592-5800
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$35,000.00$35,000.00 $8,800.00$8,800.00 $15,597.00$15,597.00 
2SITE GRADING AND SEEDING1L.S.$1,500.00$1,500.00 $3,300.00$3,300.00 $1,204.00$1,204.00 
3INTERIOR DEMOLITION AND PREP WORK1L.S.$7,900.00$7,900.00 $8,250.00$8,250.00 $3,506.00$3,506.00 
4CONCRETE/ASPHALT DEMOLITION AND REMOVAL1L.S.$2,950.00$2,950.00 $3,850.00$3,850.00 $3,181.00$3,181.00 
5CONCRETE SLAB AND SLAB POLYFOAM JACKING1L.S.$9,590.00$9,590.00 $6,600.00$6,600.00 $7,077.00$7,077.00 
6CONCRETE CLEANING AND SEALING1L.S.$2,470.00$2,470.00 $7,700.00$7,700.00 $2,944.00$2,944.00 
7CLEAN EXTERIOR SPLIT-FACED BLOCK AND SEAL1L.S.$3,010.00$3,010.00 $7,370.00$7,370.00 $2,634.00$2,634.00 
8NEW SHOWER AND TOILET PARTITIONS1L.S.$22,400.00$22,400.00 $29,861.70$29,861.70 $18,256.00$18,256.00 
9INTERIOR WOOD CEILING INFILL AT SKYLIGHTS1L.S.$5,350.00$5,350.00 $9,152.00$9,152.00 $6,315.00$6,315.00 
10STANDING SEAM METAL ROOF, UNDERLAYMENT AND ACCESSORIES1L.S.$24,900.00$24,900.00 $43,964.80$43,964.80 $42,393.00$42,393.00 
11GUTTERS AND DOWNSPOUTS1L.S.$900.00$900.00 $1,375.00$1,375.00 $3,108.00$3,108.00 
12NEW ALUMINUM SOFFIT220S.F.$27.73$6,100.60 $48.46$10,661.20 $38.65$8,503.00 
13PAINTING - EXTERIOR FASCIA1L.S.$2,000.00$2,000.00 $1,469.60$1,469.60 $3,455.00$3,455.00 
14PAINTING - INTERIOR CMU WALLS1L.S.$6,500.00$6,500.00 $5,412.00$5,412.00 $11,512.00$11,512.00 
15FRP LINING AT SHOWER STALLS AND HAND DRYERS LOCATIONS1L.S.$2,100.00$2,100.00 $8,252.42$8,252.42 $5,454.00$5,454.00 
16PAINTING - INTERIOR CEILING STAINING AND SEALING1L.S.$4,500.00$4,500.00 $6,820.00$6,820.00 $15,571.00$15,571.00 
17INTERIOR RESINOUS FLOORING AND BASE1L.S.$28,300.00$28,300.00 $6,490.00$6,490.00 $6,614.00$6,614.00 
18NEW WALL VENTS AND LOUVERS1L.S.$1,600.00$1,600.00 $1,980.00$1,980.00 $10,070.00$10,070.00 
19NEW COUNTERTOPS AND SIDE SPLASHES1L.S.$5,010.00$5,010.00 $2,860.00$2,860.00 $7,534.00$7,534.00 
20NEW HAND DRYERS, DISPENSERS, AND MIRRORS1L.S.$5,925.00$5,925.00 $4,774.00$4,774.00 $4,752.00$4,752.00 
21PLUMBING - ROUGH-IN1L.S.$3,200.00$3,200.00 $4,455.00$4,455.00 $5,035.00$5,035.00 
22PLUMBING FIXTURES - TOILETS AND URINAL1L.S.$14,530.00$14,530.00 $8,195.00$8,195.00 $9,262.00$9,262.00 
23LAVATORIES AND PLUMBING1L.S.$6,250.00$6,250.00 $6,556.00$6,556.00 $7,409.00$7,409.00 
24ADA SHOWER STALLS1L.S.$5,600.00$5,600.00 $11,935.00$11,935.00 $17,744.00$17,744.00 
25NEW SHOWER HEADS, CONTROLS, VALVES AND ACCESSORIES1L.S.$10,340.00$10,340.00 $10,065.00$10,065.00 $11,856.00$11,856.00 
26ELECTRICAL - ROUGH-IN1L.S.$2,860.00$2,860.00 $2,200.00$2,200.00 $1,832.00$1,832.00 
27LIGHTING FIXTURES AND SENSORS1L.S.$8,420.00$8,420.00 $7,700.00$7,700.00 $4,889.00$4,889.00 
28NEW EXHAUST VENTILATION FANS AND SENSOR/TIMER1L.S.$4,500.00$4,500.00 $7,700.00$7,700.00 $9,759.00$9,759.00 
      $233,705.60  $237,748.72  $247,466.00 
 
4
5
6
Estimated Cost: $250,000.00
Contractor: 
Lejas CorporationKing Knutson Construction, IncDean Snyder Construction Co
Funding Source: 50% Infrastructure, 50% Federal-Land and Water Conservation Fund, 6202 S Maple Avenue, Suite 127
1205 N Oak St
913 North 14th St
Tempe AZ  85283Iowa Falls IA  50126Clear Lake IA  50428
Plan Sets Requested: 2
Quantities
480-775-1152641-648-5464641-357-2283
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$12,483.00$12,483.00 $50,225.00$50,225.00 $56,741.00$56,741.00 
2SITE GRADING AND SEEDING1L.S.$3,780.00$3,780.00 $3,675.00$3,675.00 $3,889.00$3,889.00 
3INTERIOR DEMOLITION AND PREP WORK1L.S.$20,500.00$20,500.00 $7,839.00$7,839.00 $5,964.00$5,964.00 
4CONCRETE/ASPHALT DEMOLITION AND REMOVAL1L.S.$6,425.00$6,425.00 $7,560.00$7,560.00 $4,541.00$4,541.00 
5CONCRETE SLAB AND SLAB POLYFOAM JACKING1L.S.$9,450.00$9,450.00 $3,360.00$3,360.00 $11,967.00$11,967.00 
6CONCRETE CLEANING AND SEALING1L.S.$7,155.00$7,155.00 $7,035.00$7,035.00 $4,957.00$4,957.00 
7CLEAN EXTERIOR SPLIT-FACED BLOCK AND SEAL1L.S.$4,800.00$4,800.00 $41,269.00$41,269.00 $9,492.00$9,492.00 
8NEW SHOWER AND TOILET PARTITIONS1L.S.$15,555.00$15,555.00 $17,611.00$17,611.00 $22,451.00$22,451.00 
9INTERIOR WOOD CEILING INFILL AT SKYLIGHTS1L.S.$650.00$650.00 $5,633.00$5,633.00 $8,959.00$8,959.00 
10STANDING SEAM METAL ROOF, UNDERLAYMENT AND ACCESSORIES1L.S.$41,555.00$41,555.00 $39,698.00$39,698.00 $41,905.00$41,905.00 
11GUTTERS AND DOWNSPOUTS1L.S.$11,250.00$11,250.00 $2,268.00$2,268.00 $2,809.00$2,809.00 
12NEW ALUMINUM SOFFIT220S.F.$22.50$4,950.00 $89.145$19,611.90 $92.00$20,240.00 
13PAINTING - EXTERIOR FASCIA1L.S.$2,950.00$2,950.00 $1,935.00$1,935.00 $2,192.00$2,192.00 
14PAINTING - INTERIOR CMU WALLS1L.S.$19,000.00$19,000.00 $7,560.00$7,560.00 $9,503.00$9,503.00 
15FRP LINING AT SHOWER STALLS AND HAND DRYERS LOCATIONS1L.S.$8,725.00$8,725.00 $8,451.00$8,451.00 $9,297.00$9,297.00 
16PAINTING - INTERIOR CEILING STAINING AND SEALING1L.S.$8,650.00$8,650.00 $5,384.00$5,384.00 $5,368.00$5,368.00 
17INTERIOR RESINOUS FLOORING AND BASE1L.S.$14,444.00$14,444.00 $5,145.00$5,145.00 $17,147.00$17,147.00 
18NEW WALL VENTS AND LOUVERS1L.S.$2,880.00$2,880.00 $2,915.00$2,915.00 $11,702.00$11,702.00 
19NEW COUNTERTOPS AND SIDE SPLASHES1L.S.$5,580.00$5,580.00 $1,929.00$1,929.00 $7,685.00$7,685.00 
20NEW HAND DRYERS, DISPENSERS, AND MIRRORS1L.S.$5,500.00$5,500.00 $3,255.00$3,255.00 $2,825.00$2,825.00 
21PLUMBING - ROUGH-IN1L.S.$3,330.00$3,330.00 $3,818.00$3,818.00 $4,334.00$4,334.00 
22PLUMBING FIXTURES - TOILETS AND URINAL1L.S.$16,525.00$16,525.00 $6,909.00$6,909.00 $7,973.00$7,973.00 
23LAVATORIES AND PLUMBING1L.S.$6,000.00$6,000.00 $5,882.00$5,882.00 $6,378.00$6,378.00 
24ADA SHOWER STALLS1L.S.$4,950.00$4,950.00 $12,911.00$12,911.00 $11,611.00$11,611.00 
25NEW SHOWER HEADS, CONTROLS, VALVES AND ACCESSORIES1L.S.$5,555.00$5,555.00 $9,590.00$9,590.00 $9,792.00$9,792.00 
26ELECTRICAL - ROUGH-IN1L.S.$3,785.00$3,785.00 $12,600.00$12,600.00 $5,351.00$5,351.00 
27LIGHTING FIXTURES AND SENSORS1L.S.$7,125.00$7,125.00 $1,575.00$1,575.00 $5,351.00$5,351.00 
28NEW EXHAUST VENTILATION FANS AND SENSOR/TIMER1L.S.$8,580.00$8,580.00 $1,050.00$1,050.00 $10,687.00$10,687.00 
      $262,132.00  $296,693.90  $321,111.00 
 



 

12/5/2025