IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Clear Lake State Park  Date: 7/24/2025  Project No.  
  Restroom and Shower Building (duplicate)  County:   CERRO GORDO  Time: 3:00 p.m.  23-03-17-09

 

 
1
2
3
Estimated Cost: $150,000.00
Contractor: 
Steege Construction, Inc
Funding Source: 50% Infrastructure, 50% Federal-Land and Water Conservation Fund, 2601 Easton Ave


Waverly IA  50677    
Plan Sets Requested: 0
Quantities
319-240-3492
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$13,986.00$13,986.00 $0.00 $0.00 
2Demolition1L.S.$4,863.00$4,863.00 $0.00 $0.00 
3Electrical and Lighting1L.S.$7,722.00$7,722.00 $0.00 $0.00 
4Plumbing and Piping1L.S.$7,215.00$7,215.00 $0.00 $0.00 
5Concrete Construction and Repair1L.S.$3,480.00$3,480.00 $0.00 $0.00 
6Flooring Preparation and Coating1L.S.$10,788.00$10,788.00 $0.00 $0.00 
7Precast Concrete Cleaning, Repair, Painting1L.S.$36,565.00$36,565.00 $0.00 $0.00 
8Shower Tower and Sediment Trap1L.S.$17,980.00$17,980.00 $0.00 $0.00 
9Exhaust Fans Replacement1L.S.$24,300.00$24,300.00 $0.00 $0.00 
10New Precast Concrete Joint Treatments1L.S.$12,163.00$12,163.00 $0.00 $0.00 
11Bottle Filler Station1L.S.$3,422.00$3,422.00 $0.00 $0.00 
12Shower Valve Replacement1L.S.$6,705.00$6,705.00 $0.00 $0.00 
13Standing Seam Roof Covering, Furring, and Flashing1L.S.$35,666.00$35,666.00 $0.00 $0.00 
14Site Fill and Seeding1L.S.$4,930.00$4,930.00 $0.00 $0.00 
      $189,785.00  $0.00  $0.00 
 



 

12/5/2025