| Bids For: | Location: | Lake Keomah State Park | Date: 7/24/2025 | Project No. |
| Spillway Floor Concrete | County: | MAHASKA | Time: 11:00 a.m. | 20-05-62-07 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Modern Concrete MODCON INC | Caliber Concrete LLC | TK Concrete, Inc | |||||||||
| Funding Source: 100% Lake Restoration, | 2768 NW 152nd St | 309 Audubon St | 1608 Fifield Road | ||||||||||
| Clive IA 50325 | Adair IA 50002 | Pella IA 50219 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 515-732-5855 | 515-979-2004 | 641-628-4590 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $19,000.00 | $19,000.00 | $10,000.00 | $10,000.00 | ||||
| 2 | Surface Cleaning | 1088 | S.Y. | $5.00 | $5,440.00 | $3.00 | $3,264.00 | $10.00 | $10,880.00 | ||||
| 3 | 6" PCC Overlay | 1088 | S.Y. | $60.00 | $65,280.00 | $61.51 | $66,922.88 | $75.00 | $81,600.00 | ||||
| 4 | Concrete Testing | 1 | L.S. | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | $3,500.00 | $3,500.00 | ||||
| $76,720.00 | $91,186.88 | $105,980.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Jasper Construction Services, Inc | Portland Construction Company | McGee Concrete, LLC | |||||||||
| Funding Source: 100% Lake Restoration, | 928 N 19th Ave E | 1615 SE Cortina Dr Ste 106 | 219 N Fryer St | ||||||||||
| Newton IA 50208 | Ankeny IA 50021 | Russell IA 50238 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 641-792-8650 | 515-456-4010 | 641-203-0721 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,000.00 | $9,000.00 | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Surface Cleaning | 1088 | S.Y. | $7.00 | $7,616.00 | $18.00 | $19,584.00 | $18.00 | $19,584.00 | ||||
| 3 | 6" PCC Overlay | 1088 | S.Y. | $82.00 | $89,216.00 | $73.50 | $79,968.00 | $87.45 | $95,145.60 | ||||
| 4 | Concrete Testing | 1 | L.S. | $3,150.00 | $3,150.00 | $2,500.00 | $2,500.00 | $4,500.00 | $4,500.00 | ||||
| $108,982.00 | $112,052.00 | $124,229.60 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Iowa Bridge & Culvert, LC | Construction Leaders Co LLC | Cramer and Associates Inc | |||||||||
| Funding Source: 100% Lake Restoration, | 409 N Avenue B PO Box 13 | 8401 Douglas Ave Ste 5 | 3100 SW Brookside Dr | ||||||||||
| Washington IA 52353 | Urbandale IA 50322 | Grimes IA 50111 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 319-653-5436 | 515-505-3299 | 515-265-1447 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $20,000.00 | $20,000.00 | $5,000.00 | $5,000.00 | $20,000.00 | $20,000.00 | ||||
| 2 | Surface Cleaning | 1088 | S.Y. | $5.00 | $5,440.00 | $4.00 | $4,352.00 | $12.00 | $13,056.00 | ||||
| 3 | 6" PCC Overlay | 1088 | S.Y. | $100.00 | $108,800.00 | $122.00 | $132,736.00 | $150.00 | $163,200.00 | ||||
| 4 | Concrete Testing | 1 | L.S. | $3,000.00 | $3,000.00 | $4,500.00 | $4,500.00 | $7,500.00 | $7,500.00 | ||||
| $137,240.00 | $146,588.00 | $203,756.00 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Godbersen-Smith Construction Co | |||||||||||
| Funding Source: 100% Lake Restoration, | 5784 Hwy 175 | ||||||||||||
| Ida Grove IA 51445 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 712-364-3388 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $26,000.00 | $26,000.00 | $0.00 | $0.00 | ||||||
| 2 | Surface Cleaning | 1088 | S.Y. | $15.00 | $16,320.00 | $0.00 | $0.00 | ||||||
| 3 | 6" PCC Overlay | 1088 | S.Y. | $158.00 | $171,904.00 | $0.00 | $0.00 | ||||||
| 4 | Concrete Testing | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| $217,724.00 | $0.00 | $0.00 | |||||||||||
12/5/2025