IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Rathbun Wildlife Unit  Date: 5/22/2025  Project No.  
  Sedan Bottoms Office Build-Out Phase II  County:   APPANOOSE  Time: 11:00 a.m.  24-05-04-02

 

 
1
2
3
Estimated Cost: $120,000.00
Contractor: 
Burkett Construction LLCHartland Bobcat Services LLCLejas Corporation
Funding Source: 100% F&W Trust-Wildlife Non-Habitat Stamp, 25 Ellefson Dr
19561 205th Ave
6202 S Maple Ave Suite 127
De Soto IA  50069Centerville IA  52544Tempe AZ  85283
Plan Sets Requested: 0
Quantities
515-783-8860641-895-2127480-775-1152
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$0.00$0.00 $14,882.00$14,882.00 $10,000.50$10,000.50 
2Concrete Slab/Stoop Footing/ADA Accessories325S.F.$26.77$8,700.25 $47.65$15,486.25 $83.50$27,137.50 
3Electrical and Lighting1L.S.$18,995.00$18,995.00 $15,300.00$15,300.00 $27,470.00$27,470.00 
4Plumbing and Piping1L.S.$25,500.00$25,500.00 $29,838.00$29,838.00 $14,648.00$14,648.00 
5Mechanical - Heating and Cooling1L.S.$7,825.00$7,825.00 $12,233.00$12,233.00 $13,672.00$13,672.00 
6Framing and Steel Liner Panel/Wall Coverings1750L.F.$37.15$65,012.50 $23.00$40,250.00 $45.00$78,750.00 
7Restroom Casework and Fixtures1L.S.$2,200.00$2,200.00 $10,670.00$10,670.00 $4,296.00$4,296.00 
      $128,232.75  $138,659.25  $175,974.00 
Alternate        
8ALTERNATE #1 - 5" Concrete Approach Apron500S.F.$10.00$5,000.00 $18.00$9,000.00 $25.00$12,500.00 
Alternate        
9ALTERNATE #2 - Epoxy Flooring400S.F.$27.50$11,000.00 $14.30$5,720.00 $20.00$8,000.00 
      $144,232.75  $153,379.25  $196,474.00 
 



 