IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Nishnabotna Wildlife Unit  Date: 6/19/2025  Project No.  
  2019 FLOOD DAMAGE REPAIRS PHASE 8  County:   FREMONT  Time: 11:00 AM  22-04-36-06

 

 
1
2
3
Estimated Cost: $57,000.00
Contractor: 
Legacy Grading LLCThree Oaks Construction IncAshland Road Excavating LLC
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 10744 Wildflower Ridge Rd
515 South Flynn St
PO Box 757
4405 Ashland Rd
Unionville MO  63565North Sioux City SD  57049Plattsmouth NE  68048
Plan Sets Requested: 3
Quantities
660-292-2843712-251-1767402-297-0764
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clear and Grub, Dike (309105 Cooper Creek Dike)0.12Acres$4,550.00$546.00 $2,500.00$300.00 $2,250.00$270.00 
2Clear and Grub, Borrow (309105 Cooper Creek Dike)1.12Acres$2,000.00$2,240.00 $2,500.00$2,800.00 $2,250.00$2,520.00 
3Excavation, Class 10 (309105 Cooper Creek Dike)1C.Y.$100.00$100.00 $25.00$25.00 $6.75$6.75 
4Embankment-In-Place (309105 Cooper Creek Dike)10C.Y.$100.75$1,007.50 $25.00$250.00 $11.25$112.50 
5Seed and Mulch, Dike (309105 Cooper Creek Dike)0.12Acres$11,500.00$1,380.00 $1,500.00$180.00 $1,755.00$210.60 
6Construction Survey (309105 Cooper Creek Dike)1L.S.$750.00$750.00 $1,000.00$1,000.00 $675.00$675.00 
7Mobilization (309105 Cooper Creek Dike)1L.S.$1,800.00$1,800.00 $2,500.00$2,500.00 $3,150.00$3,150.00 
8Clear and Grub, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)0.91Acres$2,650.00$2,411.50 $2,500.00$2,275.00 $2,250.00$2,047.50 
9Excavation, Class 10 (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)18C.Y.$42.00$756.00 $25.00$450.00 $6.75$121.50 
10Embankment-In-Place (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)36C.Y.$46.00$1,656.00 $25.00$900.00 $13.05$469.80 
11Seed and Mulch, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)0.91Acres$2,875.00$2,616.25 $1,500.00$1,365.00 $1,755.00$1,597.05 
12Construction Survey (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)1L.S.$1,100.00$1,100.00 $1,000.00$1,000.00 $3,150.00$3,150.00 
13Mobilization (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)1L.S.$2,200.00$2,200.00 $2,500.00$2,500.00 $3,150.00$3,150.00 
14Clear and Grub, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 3)0.22Acres$4,400.00$968.00 $1,500.00$330.00 $1,575.00$346.50 
15Excavation, Class 10 (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1C.Y.$100.00$100.00 $25.00$25.00 $9.45$9.45 
16Embankment-In-Place (309107 Botna Bottom Kruse Dike Site 1 Loc 3)22C.Y.$85.75$1,886.50 $25.00$550.00 $12.60$277.20 
17Seed and Mulch, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 3)0.22Acres$5,200.00$1,144.00 $1,500.00$330.00 $1,755.00$386.10 
18Construction Survey (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1L.S.$1,150.00$1,150.00 $1,000.00$1,000.00 $3,150.00$3,150.00 
19Mobilization (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1L.S.$1,000.00$1,000.00 $2,500.00$2,500.00 $3,150.00$3,150.00 
20Clear and Grub, Borrow (309107 Botna Bottom Kruse)1.02Acres$2,500.00$2,550.00 $2,500.00$2,550.00 $2,250.00$2,295.00 
21Seed and Mulch, Borrow (309107 Botna Bottom Kruse)1.02Acres$1,400.00$1,428.00 $1,500.00$1,530.00 $1,755.00$1,790.10 
22Clear and Grub, Dike (309108 Botna Bottom Deng Dike Site 1 Loc 5)0.24Acres$4,500.00$1,080.00 $2,500.00$600.00 $2,250.00$540.00 
23Excavation, Class 10 (309108 Botna Bottom Deng Dike Site 1 Loc 5)1C.Y.$100.00$100.00 $25.00$25.00 $10.80$10.80 
24Embankment-In-Place (309108 Botna Bottom Deng Dike Site 1 Loc 5)52C.Y.$44.00$2,288.00 $25.00$1,300.00 $12.60$655.20 
25Seed and Mulch, Dike (309108 Botna Bottom Deng Dike Site 1 Loc 5)0.24Acres$4,500.00$1,080.00 $1,500.00$360.00 $2,250.00$540.00 
26Construction Survey (309108 Botna Bottom Deng Dike Site 1 Loc 5)1L.S.$800.00$800.00 $1,000.00$1,000.00 $3,150.00$3,150.00 
27Mobilization (309108 Botna Bottom Deng Dike Site 1 Loc 5)1L.S.$1,400.00$1,400.00 $2,500.00$2,500.00 $3,150.00$3,150.00 
28Clear and Grub, Dike (309108 Botna Bottom Deng Dike)0.17Acres$4,500.00$765.00 $2,500.00$425.00 $2,250.00$382.50 
29Excavation, Class 10 (309108 Botna Bottom Deng Dike)1C.Y.$100.00$100.00 $25.00$25.00 $10.80$10.80 
30Embankment-In-Place (309108 Botna Bottom Deng Dike)59C.Y.$44.00$2,596.00 $25.00$1,475.00 $12.60$743.40 
31Seed and Mulch, Dike (309108 Botna Bottom Deng Dike)0.17Acres$3,500.00$595.00 $1,500.00$255.00 $1,755.00$298.35 
32Construction Survey (309108 Botna Bottom Deng Dike)1L.S.$700.00$700.00 $1,000.00$1,000.00 $3,150.00$3,150.00 
33Mobilization (309108 Botna Bottom Deng Dike)1L.S.$1,100.00$1,100.00 $2,500.00$2,500.00 $3,150.00$3,150.00 
34Clear and Grub, Borrow (309108 Botna Bottom Deng Dike)2.63Acres$1,500.00$3,945.00 $2,500.00$6,575.00 $2,250.00$5,917.50 
35Seed and Mulch, Borrow (309108 Botna Bottom Deng Dike)2.63Acres$1,400.00$3,682.00 $1,500.00$3,945.00 $1,750.00$4,602.50 
36NPDES General Permit #2 & SWPPP (309105 Cooper Creek and 309107/309108 Botna Bottoms)1L.S.$800.00$800.00 $3,500.00$3,500.00 $4,050.00$4,050.00 
      $49,820.75  $49,845.00  $59,236.10 
 
4
5
6
Estimated Cost: $57,000.00
Contractor: 
Dovel Construction LLCDCLI LLCHendrickson Transportation LLC
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 1507 Argyle St
21297 State Hwy 2
2762 310th St
Hamburg IA  51640Leon IA  50144Hamburg IA  51640
Plan Sets Requested: 3
Quantities
712-382-0024641-442-5347712-382-1505
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clear and Grub, Dike (309105 Cooper Creek Dike)0.12Acres$3,500.00$420.00 $1,000.00$120.00 $20,730.67$2,487.68 
2Clear and Grub, Borrow (309105 Cooper Creek Dike)1.12Acres$500.00$560.00 $1,000.00$1,120.00 $2,221.14$2,487.677 
3Excavation, Class 10 (309105 Cooper Creek Dike)1C.Y.$20.00$20.00 $100.00$100.00 $15.00$15.00 
4Embankment-In-Place (309105 Cooper Creek Dike)10C.Y.$20.00$200.00 $50.00$500.00 $10.00$100.00 
5Seed and Mulch, Dike (309105 Cooper Creek Dike)0.12Acres$4,900.00$588.00 $3,500.00$420.00 $4,407.42$528.89 
6Construction Survey (309105 Cooper Creek Dike)1L.S.$2,000.00$2,000.00 $3,200.00$3,200.00 $1,001.34$1,001.34 
7Mobilization (309105 Cooper Creek Dike)1L.S.$2,000.00$2,000.00 $14,000.00$14,000.00 $2,938.28$2,938.28 
8Clear and Grub, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)0.91Acres$3,500.00$3,185.00 $1,000.00$910.00 $2,733.71$2,487.676 
9Excavation, Class 10 (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)18C.Y.$20.00$360.00 $50.00$900.00 $15.00$270.00 
10Embankment-In-Place (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)36C.Y.$20.00$720.00 $50.00$1,800.00 $10.00$360.00 
11Seed and Mulch, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)0.91Acres$4,900.00$4,459.00 $3,500.00$3,185.00 $4,407.42$4,010.752 
12Construction Survey (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)1L.S.$2,000.00$2,000.00 $1,600.00$1,600.00 $1,001.34$1,001.34 
13Mobilization (309107 Botna Bottom Kruse Dike Site 1 Loc 1 & 2)1L.S.$2,000.00$2,000.00 $2,500.00$2,500.00 $2,938.28$2,938.28 
14Clear and Grub, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 3)0.22Acres$3,500.00$770.00 $1,000.00$220.00 $11,307.64$2,487.681 
15Excavation, Class 10 (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1C.Y.$20.00$20.00 $50.00$50.00 $15.00$15.00 
16Embankment-In-Place (309107 Botna Bottom Kruse Dike Site 1 Loc 3)22C.Y.$20.00$440.00 $50.00$1,100.00 $10.00$220.00 
17Seed and Mulch, Dike (309107 Botna Bottom Kruse Dike Site 1 Loc 3)0.22Acres$4,900.00$1,078.00 $3,000.00$660.00 $4,407.41$969.63 
18Construction Survey (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1L.S.$2,000.00$2,000.00 $1,600.00$1,600.00 $1,001.34$1,001.34 
19Mobilization (309107 Botna Bottom Kruse Dike Site 1 Loc 3)1L.S.$2,000.00$2,000.00 $2,500.00$2,500.00 $2,938.28$2,938.28 
20Clear and Grub, Borrow (309107 Botna Bottom Kruse)1.02Acres$3,500.00$3,570.00 $1,000.00$1,020.00 $2,438.90$2,487.678 
21Seed and Mulch, Borrow (309107 Botna Bottom Kruse)1.02Acres$1,300.00$1,326.00 $3,000.00$3,060.00 $4,407.42$4,495.568 
22Clear and Grub, Dike (309108 Botna Bottom Deng Dike Site 1 Loc 5)0.24Acres$3,500.00$840.00 $1,000.00$240.00 $10,365.33$2,487.679 
23Excavation, Class 10 (309108 Botna Bottom Deng Dike Site 1 Loc 5)1C.Y.$20.00$20.00 $50.00$50.00 $15.00$15.00 
24Embankment-In-Place (309108 Botna Bottom Deng Dike Site 1 Loc 5)52C.Y.$20.00$1,040.00 $50.00$2,600.00 $10.00$520.00 
25Seed and Mulch, Dike (309108 Botna Bottom Deng Dike Site 1 Loc 5)0.24Acres$4,900.00$1,176.00 $3,000.00$720.00 $4,407.46$1,057.79 
26Construction Survey (309108 Botna Bottom Deng Dike Site 1 Loc 5)1L.S.$2,000.00$2,000.00 $1,600.00$1,600.00 $1,001.34$1,001.34 
27Mobilization (309108 Botna Bottom Deng Dike Site 1 Loc 5)1L.S.$2,000.00$2,000.00 $2,500.00$2,500.00 $2,938.28$2,938.28 
28Clear and Grub, Dike (309108 Botna Bottom Deng Dike)0.17Acres$3,500.00$595.00 $1,000.00$170.00 $14,633.41$2,487.68 
29Excavation, Class 10 (309108 Botna Bottom Deng Dike)1C.Y.$20.00$20.00 $50.00$50.00 $15.00$15.00 
30Embankment-In-Place (309108 Botna Bottom Deng Dike)59C.Y.$20.00$1,180.00 $50.00$2,950.00 $10.00$590.00 
31Seed and Mulch, Dike (309108 Botna Bottom Deng Dike)0.17Acres$4,900.00$833.00 $3,000.00$510.00 $4,407.47$749.27 
32Construction Survey (309108 Botna Bottom Deng Dike)1L.S.$2,000.00$2,000.00 $1,600.00$1,600.00 $1,001.34$1,001.34 
33Mobilization (309108 Botna Bottom Deng Dike)1L.S.$2,000.00$2,000.00 $2,500.00$2,500.00 $2,938.28$2,938.28 
34Clear and Grub, Borrow (309108 Botna Bottom Deng Dike)2.63Acres$3,500.00$9,205.00 $1,000.00$2,630.00 $1,891.77$4,975.355 
35Seed and Mulch, Borrow (309108 Botna Bottom Deng Dike)2.63Acres$1,400.00$3,682.00 $3,000.00$7,890.00 $4,407.42$11,591.515 
36NPDES General Permit #2 & SWPPP (309105 Cooper Creek and 309107/309108 Botna Bottoms)1L.S.$6,500.00$6,500.00 $1,000.00$1,000.00 $16,895.11$16,895.11 
      $62,807.00  $67,575.00  $84,505.732 
 



 

12/5/2025