IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Yellow River State Forest | Date: 6/18/2026 | Project No. |
| Paint Creek Streambank Improvements - Phase 2 | County: | ALLAMAKEE | Time: 11:00 a.m. | 25-03-03-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $115,000.00 | Contractor: | Bacon Concrete, LLC | DKW Tree Service LLC | Matt Construction Inc | |||||||||
| Funding Source: 75% Federal-Other, 25% Cash Donation, | 370 N Bancroft St | 455 Main Street West | 203 Y Ave | ||||||||||
| Postville IA 52162 | Maynard IA 50655 | Sumner IA 50674 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 563-864-7602 | 319-505-7439 | 563-578-8418 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $10,000.00 | $10,000.00 | $8,000.00 | $8,000.00 | ||||
| 2 | Clearing and Grubbing | 1 | L.S. | $3,000.00 | $3,000.00 | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | ||||
| 3 | Class 10 Excavation | 2540 | C.Y. | $4.00 | $10,160.00 | $3.50 | $8,890.00 | $10.00 | $25,400.00 | ||||
| 4 | Wattles, 9" | 550 | L.F. | $3.50 | $1,925.00 | $3.00 | $1,650.00 | $2.58 | $1,419.00 | ||||
| 5 | Revetment, Class E | 330 | Tons | $35.00 | $11,550.00 | $50.00 | $16,500.00 | $27.95 | $9,223.50 | ||||
| 6 | Revetment, Class B | 480 | Tons | $38.00 | $18,240.00 | $50.00 | $24,000.00 | $28.50 | $13,680.00 | ||||
| 7 | Large Boulders | 100 | Each | $280.00 | $28,000.00 | $250.00 | $25,000.00 | $260.00 | $26,000.00 | ||||
| 8 | Erosion Matting | 2048 | S.Y. | $7.00 | $14,336.00 | $1.50 | $3,072.00 | $5.00 | $10,240.00 | ||||
| 9 | Temporary Seeding | 0.5 | Acres | $2,000.00 | $1,000.00 | $3,000.00 | $1,500.00 | $3,000.00 | $1,500.00 | ||||
| 10 | Permanent Seeding | 0.5 | Acres | $2,000.00 | $1,000.00 | $3,000.00 | $1,500.00 | $3,000.00 | $1,500.00 | ||||
| 11 | Mobilizations, Emergency Erosion Control | 1 | Each | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | ||||
| $94,211.00 | $95,112.00 | $101,462.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $115,000.00 | Contractor: | Sommer Excavating LLC | Top Grade Excavating Inc | Ground Line Company LLC | |||||||||
| Funding Source: 75% Federal-Other, 25% Cash Donation, | 750 16th Ave NW | 971 9th Ave NW | 4782 County Rd E17 | ||||||||||
| Waukon IA 52172 | Farley IA 52046 | Onslow IA 52321 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 563-568-1677 | 563-744-3416 | 319-251-0425 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,750.00 | $3,750.00 | $4,120.00 | $4,120.00 | $8,900.00 | $8,900.00 | ||||
| 2 | Clearing and Grubbing | 1 | L.S. | $3,800.00 | $3,800.00 | $2,475.00 | $2,475.00 | $6,750.00 | $6,750.00 | ||||
| 3 | Class 10 Excavation | 2540 | C.Y. | $3.89 | $9,880.60 | $5.90 | $14,986.00 | $8.00 | $20,320.00 | ||||
| 4 | Wattles, 9" | 550 | L.F. | $2.49 | $1,369.50 | $7.00 | $3,850.00 | $3.00 | $1,650.00 | ||||
| 5 | Revetment, Class E | 330 | Tons | $32.45 | $10,708.50 | $62.00 | $20,460.00 | $37.00 | $12,210.00 | ||||
| 6 | Revetment, Class B | 480 | Tons | $39.89 | $19,147.20 | $54.50 | $26,160.00 | $41.00 | $19,680.00 | ||||
| 7 | Large Boulders | 100 | Each | $436.25 | $43,625.00 | $224.00 | $22,400.00 | $370.00 | $37,000.00 | ||||
| 8 | Erosion Matting | 2048 | S.Y. | $4.89 | $10,014.72 | $4.20 | $8,601.60 | $1.30 | $2,662.40 | ||||
| 9 | Temporary Seeding | 0.5 | Acres | $1,300.00 | $650.00 | $3,125.00 | $1,562.50 | $1,000.00 | $500.00 | ||||
| 10 | Permanent Seeding | 0.5 | Acres | $2,200.00 | $1,100.00 | $3,125.00 | $1,562.50 | $1,200.00 | $600.00 | ||||
| 11 | Mobilizations, Emergency Erosion Control | 1 | Each | $875.00 | $875.00 | $1,250.00 | $1,250.00 | $490.00 | $490.00 | ||||
| $104,920.52 | $107,427.60 | $110,762.40 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $115,000.00 | Contractor: | Szabo Construction Co Inc | Rausch Construction, Inc | ||||||||||
| Funding Source: 75% Federal-Other, 25% Cash Donation, | 152 S West St | 2725 State Hwy 24 | |||||||||||
| Postville IA 52162 | Fort Atkinson IA 52144 | ||||||||||||
| Plan Sets Requested: 9 | Quantities | 563-864-7515 | 563-534-7356 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $20,000.00 | $20,000.00 | $0.00 | |||||
| 2 | Clearing and Grubbing | 1 | L.S. | $8,000.00 | $8,000.00 | $7,500.00 | $7,500.00 | $0.00 | |||||
| 3 | Class 10 Excavation | 2540 | C.Y. | $10.00 | $25,400.00 | $12.00 | $30,480.00 | $0.00 | |||||
| 4 | Wattles, 9" | 550 | L.F. | $5.00 | $2,750.00 | $5.00 | $2,750.00 | $0.00 | |||||
| 5 | Revetment, Class E | 330 | Tons | $35.00 | $11,550.00 | $55.00 | $18,150.00 | $0.00 | |||||
| 6 | Revetment, Class B | 480 | Tons | $45.00 | $21,600.00 | $60.00 | $28,800.00 | $0.00 | |||||
| 7 | Large Boulders | 100 | Each | $350.00 | $35,000.00 | $550.00 | $55,000.00 | $0.00 | |||||
| 8 | Erosion Matting | 2048 | S.Y. | $8.50 | $17,408.00 | $5.00 | $10,240.00 | $0.00 | |||||
| 9 | Temporary Seeding | 0.5 | Acres | $2,000.00 | $1,000.00 | $5,000.00 | $2,500.00 | $0.00 | |||||
| 10 | Permanent Seeding | 0.5 | Acres | $2,000.00 | $1,000.00 | $5,000.00 | $2,500.00 | $0.00 | |||||
| 11 | Mobilizations, Emergency Erosion Control | 1 | Each | $1,500.00 | $1,500.00 | $20,000.00 | $20,000.00 | $0.00 | |||||
| $128,208.00 | $197,920.00 | $0.00 | |||||||||||
6/26/2026