IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Nishnabotna Wildlife Unit | Date: 5/22/2025 | Project No. |
| 2019 Flood Damage Repairs - Phase 5 Riverton WMA - Thompson Levee | County: | FREMONT | Time: 11:00 am | 22-04-36-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $160,000.00 | Contractor: | Levis Thies dba Empire Excavation | Three Oaks Construction Inc | Legacy Grading LLC | |||||||||
| Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | 219 Lawndale St | 515 South Flynn St | 10744 Wildflower Ridge Rd | ||||||||||
| Odebolt IA 51458 | North Sioux City SD 57049 | Unionville MO 63565 | |||||||||||
| Plan Sets Requested: 3 | Quantities | 712-660-8137 | 712-251-1767 | 660-292-3843 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization (309084, Site 2) | 1 | L.S. | $17,300.00 | $17,300.00 | $15,000.00 | $15,000.00 | $10,500.00 | $10,500.00 | ||||
| 2 | Clearing and Grubbing (309084, Site 2) | 5 | Acres | $5,000.00 | $25,000.00 | $2,000.00 | $10,000.00 | $500.00 | $2,500.00 | ||||
| 3 | Excavation Class 10 - Available Onsite (309084, Site 2) | 6935 | C.Y. | $3.80 | $26,353.00 | $5.00 | $34,675.00 | $4.95 | $34,328.25 | ||||
| 4 | Excavation Class 10 - Borrow Offsite (309084, Site 2) | 3005 | C.Y. | $10.00 | $30,050.00 | $13.00 | $39,065.00 | $25.12 | $75,485.60 | ||||
| 5 | Erosion Matting (309084, Site 2) | 1075 | S.Y. | $3.50 | $3,762.50 | $5.00 | $5,375.00 | $4.50 | $4,837.50 | ||||
| 6 | Seeding, Fertilizing and Mulching - Dikes (309084 Site 2) | 1.4 | Acres | $1,400.00 | $1,960.00 | $3,500.00 | $4,900.00 | $1,800.00 | $2,520.00 | ||||
| 7 | Seeding and Mulching - Borrow (309084 Site 2) | 3.4 | Acres | $1,400.00 | $4,760.00 | $3,500.00 | $11,900.00 | $1,800.00 | $6,120.00 | ||||
| 8 | Silt Fence | 770 | L.F. | $3.50 | $2,695.00 | $4.00 | $3,080.00 | $3.85 | $2,964.50 | ||||
| 9 | NPDES Permit No. 2 and SWPPP (309084, Site 2) | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | ||||
| 10 | Construction Staking (309084, Site 2) | 1 | L.S. | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | ||||
| $116,380.50 | $132,495.00 | $147,755.85 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $160,000.00 | Contractor: | Hendrickson Transportation LLC | MDX LLC | ||||||||||
| Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | 2762 310th St | 1761 305th Ave | |||||||||||
| Hamburg IA 51640 | Sidney IA 51652 | ||||||||||||
| Plan Sets Requested: 3 | Quantities | 712-382-1505 | 712-308-3993 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization (309084, Site 2) | 1 | L.S. | $11,753.12 | $11,753.12 | $10,000.00 | $10,000.00 | $0.00 | |||||
| 2 | Clearing and Grubbing (309084, Site 2) | 5 | Acres | $540.82 | $2,704.10 | $1,600.00 | $8,000.00 | $0.00 | |||||
| 3 | Excavation Class 10 - Available Onsite (309084, Site 2) | 6935 | C.Y. | $5.08 | $35,229.80 | $4.10 | $28,433.50 | $0.00 | |||||
| 4 | Excavation Class 10 - Borrow Offsite (309084, Site 2) | 3005 | C.Y. | $18.96 | $56,974.80 | $32.00 | $96,160.00 | $0.00 | |||||
| 5 | Erosion Matting (309084, Site 2) | 1075 | S.Y. | $2.94 | $3,160.50 | $4.00 | $4,300.00 | $0.00 | |||||
| 6 | Seeding, Fertilizing and Mulching - Dikes (309084 Site 2) | 1.4 | Acres | $4,407.42 | $6,170.388 | $1,800.00 | $2,520.00 | $0.00 | |||||
| 7 | Seeding and Mulching - Borrow (309084 Site 2) | 3.4 | Acres | $4,407.42 | $14,985.228 | $1,800.00 | $6,120.00 | $0.00 | |||||
| 8 | Silt Fence | 770 | L.F. | $4.41 | $3,395.70 | $3.75 | $2,887.50 | $0.00 | |||||
| 9 | NPDES Permit No. 2 and SWPPP (309084, Site 2) | 1 | L.S. | $11,018.55 | $11,018.55 | $10,500.00 | $10,500.00 | $0.00 | |||||
| 10 | Construction Staking (309084, Site 2) | 1 | L.S. | $5,072.36 | $5,072.36 | $4,400.00 | $4,400.00 | $0.00 | |||||
| $150,464.546 | $173,321.00 | $0.00 | |||||||||||
12/5/2025