IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Nishnabotna Wildlife Unit | Date: 2/20/2025 | Project No. |
2019 Flood Damage Repairs - Phase 3 Riverton WMA | County: | FREMONT | Time: 3:00 p.m. | 22-04-36-03 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $140,000.00 | Contractor: | ![]() | MDX LLC | Dynamic Grading LLC dba Eckard Construction LLC | Three Oaks Construction Inc | ![]() | |||||||
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | ![]() | 1761 305th Ave | ![]() | 2766 280th St | ![]() | 515 South Flynn St PO Box 757 | ![]() | ||||||
![]() | Sidney IA 51652 | ![]() | Mount Ayr IA 50854 | ![]() | North Sioux City SD 57049 | ![]() | |||||||
Plan Sets Requested: 4 | Quantities | ![]() | 712-308-3993 | ![]() | 515-865-5081 | ![]() | 712-251-1767 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization (309087, Site 3) | 1 | L.S. | ![]() | $21,500.00 | $21,500.00 | ![]() | $16,500.02 | $16,500.02 | ![]() | $2,500.00 | $2,500.00 | ![]() |
2 | Excavation, Class 10 (309087, Site 3) | 1778 | C.Y. | ![]() | $8.50 | $15,113.00 | ![]() | $8.00 | $14,224.00 | ![]() | $13.61 | $24,198.58 | ![]() |
3 | Seeding, Fertilizing and Mulching (309087, Site 3) | 1.1 | Acres | ![]() | $1,600.00 | $1,760.00 | ![]() | $1,750.00 | $1,925.00 | ![]() | $1,592.36 | $1,751.596 | ![]() |
4 | Mobilization (309087, Site 4) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $8,200.00 | $8,200.00 | ![]() | $500.00 | $500.00 | ![]() |
5 | Embankment-In-Place (309087, Site 4) | 5181 | C.Y. | ![]() | $8.50 | $44,038.50 | ![]() | $12.75 | $66,057.75 | ![]() | $13.61 | $70,513.41 | ![]() |
6 | Seeding and Fertilizing (309087, Site 4) | 1.28 | Acres | ![]() | $1,600.00 | $2,048.00 | ![]() | $1,500.00 | $1,920.00 | ![]() | $1,592.36 | $2,038.221 | ![]() |
7 | Mobilization (309087, Site 4A) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $833.33 | $833.33 | ![]() | $500.00 | $500.00 | ![]() |
8 | Erosion Matting (309087, Site 4A) | 6218 | S.Y. | ![]() | $2.20 | $13,679.60 | ![]() | $1.50 | $9,327.00 | ![]() | $3.50 | $21,763.00 | ![]() |
9 | Mobilization (309087, Site 5) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
10 | Embankment-In-Place (309087, Site 5) | 118 | C.Y. | ![]() | $8.50 | $1,003.00 | ![]() | $8.00 | $944.00 | ![]() | $13.61 | $1,605.98 | ![]() |
11 | Seeding and Fertilizing (309087, Site 5) | 0.02 | Acres | ![]() | $1,600.00 | $32.00 | ![]() | $1,500.00 | $30.00 | ![]() | $1,592.36 | $31.847 | ![]() |
12 | Mobilization (309087, Site 5A) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $833.33 | $833.33 | ![]() | $500.00 | $500.00 | ![]() |
13 | Erosion Matting (309087, Site 5A) | 44 | S.Y. | ![]() | $2.20 | $96.80 | ![]() | $1.50 | $66.00 | ![]() | $3.50 | $154.00 | ![]() |
14 | Mobilization (309087, Site 6) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
15 | Embankment-In-Place (309087, Site 6) | 266 | C.Y. | ![]() | $8.50 | $2,261.00 | ![]() | $8.00 | $2,128.00 | ![]() | $13.61 | $3,620.26 | ![]() |
16 | Seeding and Fertilizing (309087, Site 6) | 0.11 | Acres | ![]() | $1,600.00 | $176.00 | ![]() | $1,500.00 | $165.00 | ![]() | $1,592.36 | $175.16 | ![]() |
17 | Mobilization (309087, Site 6A) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $833.33 | $833.33 | ![]() | $500.00 | $500.00 | ![]() |
18 | Erosion Matting (309087, Site 6A) | 533 | S.Y. | ![]() | $2.20 | $1,172.60 | ![]() | $1.50 | $799.50 | ![]() | $3.50 | $1,865.50 | ![]() |
19 | Mobilization (309087, Site 8) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
20 | Embankment-In-Place (309087, Site 8) | 58 | C.Y. | ![]() | $8.50 | $493.00 | ![]() | $8.00 | $464.00 | ![]() | $13.61 | $789.38 | ![]() |
21 | Seeding and Fertilizing (309087, Site 8) | 0.02 | Acres | ![]() | $1,600.00 | $32.00 | ![]() | $1,500.00 | $30.00 | ![]() | $1,592.36 | $31.847 | ![]() |
22 | Mobilization (309087, Site 8A) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $833.33 | $833.33 | ![]() | $500.00 | $500.00 | ![]() |
23 | Erosion Matting (309087, Site 8A) | 117 | S.Y. | ![]() | $2.20 | $257.40 | ![]() | $1.50 | $175.50 | ![]() | $3.50 | $409.50 | ![]() |
24 | Mobilization (309087, Site 9) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
25 | Excavation, Class 10 (309087, Site 9) | 50 | C.Y. | ![]() | $8.50 | $425.00 | ![]() | $8.00 | $400.00 | ![]() | $13.61 | $680.50 | ![]() |
26 | Seeding, Fertilizing and Mulching (309087, Site 9) | 0.06 | Acres | ![]() | $1,600.00 | $96.00 | ![]() | $2,000.00 | $120.00 | ![]() | $1,592.36 | $95.542 | ![]() |
27 | Mobilization (309087, Site 13) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
28 | Excavation, Class 10 (309087, Site 13) | 28 | C.Y. | ![]() | $8.50 | $238.00 | ![]() | $8.00 | $224.00 | ![]() | $13.61 | $381.08 | ![]() |
29 | Seeding, Fertilizing and Mulching (309087, Site 13) | 0.06 | Acres | ![]() | $1,600.00 | $96.00 | ![]() | $2,000.00 | $120.00 | ![]() | $1,592.36 | $95.542 | ![]() |
30 | Mobilization (309087, Site 14) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $500.00 | $500.00 | ![]() |
31 | Embankment-In-Place (309087, Site 14) | 83 | C.Y. | ![]() | $8.50 | $705.50 | ![]() | $8.00 | $664.00 | ![]() | $13.61 | $1,129.63 | ![]() |
32 | Seeding and Fertilizing (309087, Site 14) | 0.03 | Acres | ![]() | $1,600.00 | $48.00 | ![]() | $1,750.00 | $52.50 | ![]() | $1,592.36 | $47.771 | ![]() |
33 | Mobilization (309087, Site 14A) | 1 | L.S. | ![]() | $1,000.00 | $1,000.00 | ![]() | $833.33 | $833.33 | ![]() | $500.00 | $500.00 | ![]() |
34 | Erosion Matting (309087, Site 14A) | 167 | S.Y. | ![]() | $2.20 | $367.40 | ![]() | $1.50 | $250.50 | ![]() | $3.50 | $584.50 | ![]() |
35 | Mobilization (309087, Site 16) | 1 | L.S. | ![]() | $7,000.00 | $7,000.00 | ![]() | $6,000.00 | $6,000.00 | ![]() | $225.00 | $225.00 | ![]() |
36 | Embankment-In-Place (309087, Site 16) | 3772 | C.Y. | ![]() | $8.50 | $32,062.00 | ![]() | $15.00 | $56,580.00 | ![]() | $13.61 | $51,336.92 | ![]() |
37 | Seeding and Fertilizing (309087, Site 16) | 1.56 | Acres | ![]() | $1,600.00 | $2,496.00 | ![]() | $2,000.00 | $3,120.00 | ![]() | $1,592.36 | $2,484.082 | ![]() |
38 | Mobilization (309087, Site 16A) | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $833.33 | $833.33 | ![]() | $225.00 | $225.00 | ![]() |
39 | Erosion Matting (309087, Site 16A) | 7544 | S.Y. | ![]() | $2.20 | $16,596.80 | ![]() | $1.50 | $11,316.00 | ![]() | $3.50 | $26,404.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$180,793.60 | ![]() | $212,802.75 | ![]() | $221,137.846 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
2/23/2025