IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pikes Peak State Park  Date: 2/19/2026  Project No.  
  Lagoon Liner Replacement  County:   CLAYTON  Time: 11:00 a.m.  26-03-22-01

 

 
1
2
3
Estimated Cost: $180,000.00
Contractor: 
MidAmerica LinerConnolly Construction IncGround Line Company LLC
Funding Source: 100% Infrastructure, 272 Midwest Lane
18409 N Cascade Rd
4782 County Rd E17
Strafford MO  65757Cascade IA  52068Onslow IA  52321
Plan Sets Requested: 8
Quantities
417-501-4155563-876-3225319-251-0425
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$6,100.00$6,100.00 $16,000.00$16,000.00 $19,200.00$19,200.00 
2Biosolids Removal55535GAL.$0.816$45,299.90 $1.60$88,856.00 $1.39$77,193.65 
3Removal & Disposal of Old Liner1L.S.$53,000.00$53,000.00 $7,950.00$7,950.00 $14,800.00$14,800.00 
4New Liner & Installation1852S.Y.$22.30$41,299.60 $21.35$39,540.20 $38.00$70,376.00 
5Site Restoration1L.S.$14,900.00$14,900.00 $9,250.00$9,250.00 $9,000.00$9,000.00 
      $160,599.50  $161,596.20  $190,569.65 
 
 
4
5
6
Estimated Cost: $180,000.00
Contractor: 
JB Holland Construction IncMinturn, Inc
Funding Source: 100% Infrastructure, 2191 US Hwy 52
144 W Front St

Decorah IA  52101Brooklyn IA  52211  
Plan Sets Requested: 8
Quantities
563-382-2901641-455-0331
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,458.85$5,458.85 $106,000.00$106,000.00 $0.00 
2Biosolids Removal55535GAL.$1.69$93,854.15 $0.50$27,767.50 $0.00 
3Removal & Disposal of Old Liner1L.S.$9,450.00$9,450.00 $65,000.00$65,000.00 $0.00 
4New Liner & Installation1852S.Y.$43.00$79,636.00 $30.00$55,560.00 $0.00 
5Site Restoration1L.S.$11,600.00$11,600.00 $40,000.00$40,000.00 $0.00 
      $199,999.00  $294,327.50  $0.00 
 



 

4/7/2026