IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Pikes Peak State Park | Date: 2/19/2026 | Project No. |
| Lagoon Liner Replacement | County: | CLAYTON | Time: 11:00 a.m. | 26-03-22-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $180,000.00 | Contractor: | MidAmerica Liner | Connolly Construction Inc | Ground Line Company LLC | |||||||||
| Funding Source: 100% Infrastructure, | 272 Midwest Lane | 18409 N Cascade Rd | 4782 County Rd E17 | ||||||||||
| Strafford MO 65757 | Cascade IA 52068 | Onslow IA 52321 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 417-501-4155 | 563-876-3225 | 319-251-0425 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $6,100.00 | $6,100.00 | $16,000.00 | $16,000.00 | $19,200.00 | $19,200.00 | ||||
| 2 | Biosolids Removal | 55535 | GAL. | $0.816 | $45,299.90 | $1.60 | $88,856.00 | $1.39 | $77,193.65 | ||||
| 3 | Removal & Disposal of Old Liner | 1 | L.S. | $53,000.00 | $53,000.00 | $7,950.00 | $7,950.00 | $14,800.00 | $14,800.00 | ||||
| 4 | New Liner & Installation | 1852 | S.Y. | $22.30 | $41,299.60 | $21.35 | $39,540.20 | $38.00 | $70,376.00 | ||||
| 5 | Site Restoration | 1 | L.S. | $14,900.00 | $14,900.00 | $9,250.00 | $9,250.00 | $9,000.00 | $9,000.00 | ||||
| $160,599.50 | $161,596.20 | $190,569.65 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $180,000.00 | Contractor: | JB Holland Construction Inc | Minturn, Inc | ||||||||||
| Funding Source: 100% Infrastructure, | 2191 US Hwy 52 | 144 W Front St | |||||||||||
| Decorah IA 52101 | Brooklyn IA 52211 | ||||||||||||
| Plan Sets Requested: 8 | Quantities | 563-382-2901 | 641-455-0331 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,458.85 | $5,458.85 | $106,000.00 | $106,000.00 | $0.00 | |||||
| 2 | Biosolids Removal | 55535 | GAL. | $1.69 | $93,854.15 | $0.50 | $27,767.50 | $0.00 | |||||
| 3 | Removal & Disposal of Old Liner | 1 | L.S. | $9,450.00 | $9,450.00 | $65,000.00 | $65,000.00 | $0.00 | |||||
| 4 | New Liner & Installation | 1852 | S.Y. | $43.00 | $79,636.00 | $30.00 | $55,560.00 | $0.00 | |||||
| 5 | Site Restoration | 1 | L.S. | $11,600.00 | $11,600.00 | $40,000.00 | $40,000.00 | $0.00 | |||||
| $199,999.00 | $294,327.50 | $0.00 | |||||||||||
4/7/2026