IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake of Three Fires  Date: 2/27/2025  Project No.  
  Spillway Rehabilitation  County:   TAYLOR  Time: 3:00 p.m.  25-04-87-01

 

 
1
2
3
Estimated Cost: $20,000.00
Contractor: 
JC Midwest Services LLCVicker Drilling LLCDovel Construction LLC
Funding Source: 100% Marine Fuel Tax, 2233 Upland Ave
2151 Cherry St Road
1507 Argyle St
St Charles IA  50240Creston IA  50801Hamburg IA  51640
Plan Sets Requested: 0
Quantities
515-478-4272641-202-2728712-382-0024
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Class 1080C.Y.$25.00$2,000.00 $28.00$2,240.00 $25.00$2,000.00 
2Site Restoration1L.S.$2,000.00$2,000.00 $2,500.00$2,500.00 $2,500.00$2,500.00 
3Flowable Mortar13C.Y.$230.77$3,000.01 $360.00$4,680.00 $250.00$3,250.00 
4Patches, Full-Depth Finish, By Area0.67S.Y.$750.00$502.50 $500.00$335.00 $100.00$67.00 
5Patches, Full-Depth Finish, By Count3Each$500.00$1,500.00 $600.00$1,800.00 $1,000.00$3,000.00 
6Mobilization1L.S.$3,497.49$3,497.49 $4,500.00$4,500.00 $6,000.00$6,000.00 
76" Drain Pipe Connection Repair1L.S.$1,000.00$1,000.00 $1,500.00$1,500.00 $1,500.00$1,500.00 
8Flowable Mortar Equipment1L.S.$1,500.00$1,500.00 $4,500.00$4,500.00 $4,000.00$4,000.00 
      $15,000.00  $22,055.00  $22,317.00 
 



 

12/5/2025