 Bids For:  Location:   Shimek State Forest  Date: 2/20/2025  Project No.  
  Pavement Maintenance  County:   LEE  Time: 3:00 p.m.  24-06-56-01

 

 
1
2
3
Estimated Cost: $54,000.00
Contractor: 
Mike Kilbride Construction Inc
Funding Source: 100% Park & Institutional Road Fund, 406 Crescent Dr


Middletown IA  52638    
Plan Sets Requested: 0
Quantities
913-572-9597
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Patches, Full-Depth Finish, 6-inch, By Area, PCC313S.Y.$111.50$34,899.50 $0.00 $0.00 
2Patches, Full-Depth Finish, 6-inch, By Count, PCC25Each$250.00$6,250.00 $0.00 $0.00 
3Subbase (Patches)51.9C.Y.$150.00$7,785.00 $0.00 $0.00 
4Crack and Joint Clean and Fill (PCC Pvmt)0.21MI.$50,000.00$10,500.00 $0.00 $0.00 
5Granular Shoulder, 1 1/2" Minus14Tons$50.00$700.00 $0.00 $0.00 
6Traffic Control1L.S.$1,500.00$1,500.00 $0.00 $0.00 
7Mobilization1L.S.$3,000.00$3,000.00 $0.00 $0.00 
      $64,634.50  $0.00  $0.00 
 



 

12/5/2025