IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Clear Lake Wildlife Unit  Date: 3/13/2025  Project No.  
  Langesen WPA 2 - NAWCA  County:   WINNEBAGO  Time: 3:00 P.M.  24-02-95-01

 

 
1
2
3
Estimated Cost: $18,370.00
Contractor: 
A1 Excavating & Drainage IncLarson Contracting Central LLC
Funding Source: 100% Federal-NAWCA, 505 410th St
508 W Main St

Joice IA  50446Lake Mills IA  50450  
Plan Sets Requested: 0
Quantities
641-588-3576641-592-5800
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,000.00$1,000.00 $679.00$679.00 $0.00 
2Earthfill500C.Y.$10.00$5,000.00 $10.94$5,470.00 $0.00 
3Water Control Structure, Complete1Each$10,000.00$10,000.00 $13,241.00$13,241.00 $0.00 
418" CMP, 14 GA25L.F.$80.00$2,000.00 $59.76$1,494.00 $0.00 
5Site Prep and Mowing1L.S.$2,000.00$2,000.00 $270.00$270.00 $0.00 
68" - 12" Field Stone2Tons$200.00$400.00 $282.50$565.00 $0.00 
7Macadam Stone1.5Tons$300.00$450.00 $176.67$265.005 $0.00 
8Filter Sock, 9 Inch Dia.90L.F.$10.00$900.00 $7.00$630.00 $0.00 
9Seed and Mulch (Furnish Only)1L.S.$1,000.00$1,000.00 $899.00$899.00 $0.00 
      $22,750.00  $23,513.005  $0.00 
 



 

3/30/2025