IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Red Haw State Park | Date: 10/26/2023 | Project No. |
Culvert Replacement | County: | LUCAS | Time: 3:00 p.m. | 24-05-59-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | Haworth Land Construction | IA Builders Dirt Work LLC | Sterk Excavating Inc | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 12981 Quaker St | 219 N 10th St | 1087 200th St | ||||||||||
Indianola IA 50125 | Albia IA 52531 | Pella IA 50219 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-249-4747 | 641-895-5447 | 641-416-0110 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2416 Culv, Conc Rdwy Pipe, 24" RCP Class 3 | 56 | L.F. | $160.72 | $9,000.32 | $85.00 | $4,760.00 | $102.00 | $5,712.00 | ||||
2 | 2416 Apron, Conc, 24" RCP Class 3 | 2 | Each | $1,500.00 | $3,000.00 | $1,000.00 | $2,000.00 | $1,350.00 | $2,700.00 | ||||
3 | 2312 Class A Crushed Stone | 30 | Tons | $30.00 | $900.00 | $40.00 | $1,200.00 | $39.67 | $1,190.10 | ||||
4 | 2510 Removal of Pavement | 45 | S.Y. | $22.23 | $1,000.35 | $60.00 | $2,700.00 | $33.33 | $1,499.85 | ||||
5 | 2301 PCC Pavement, Class C4, 6" | 45 | S.Y. | $80.00 | $3,600.00 | $90.00 | $4,050.00 | $111.11 | $4,999.95 | ||||
6 | 2507 Revetment, Class E | 16 | Tons | $50.00 | $800.00 | $45.00 | $720.00 | $78.25 | $1,252.00 | ||||
7 | 2528 Traffic Control | 1 | L.S. | $500.00 | $500.00 | $1,600.00 | $1,600.00 | $1,000.00 | $1,000.00 | ||||
8 | 2533 Mobilization | 1 | L.S. | $400.00 | $400.00 | $3,000.00 | $3,000.00 | $3,200.00 | $3,200.00 | ||||
9 | 2599 Removal & Disposal of Existing CMP | 1 | L.S. | $500.00 | $500.00 | $500.00 | $500.00 | $400.00 | $400.00 | ||||
10 | 2601 Stabilize Crop - Seed & Fertilize | 1 | L.S. | $500.00 | $500.00 | $750.00 | $750.00 | $1,000.00 | $1,000.00 | ||||
$20,200.67 | $21,280.00 | $22,953.90 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | TK Concrete, Inc | J & K Contracting LLC | DCLI LLC | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 1608 Fifield Rd | 10703 Justin Dr | 21297 State Hwy 2 | ||||||||||
Pella IA 50219 | Urbandale IA 50322 | Leon IA 50144 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-628-4590 | 515-233-5500 | 641-442-5347 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2416 Culv, Conc Rdwy Pipe, 24" RCP Class 3 | 56 | L.F. | $90.00 | $5,040.00 | $92.00 | $5,152.00 | $175.90 | $9,850.40 | ||||
2 | 2416 Apron, Conc, 24" RCP Class 3 | 2 | Each | $2,750.00 | $5,500.00 | $3,200.00 | $6,400.00 | $1,700.00 | $3,400.00 | ||||
3 | 2312 Class A Crushed Stone | 30 | Tons | $40.00 | $1,200.00 | $36.00 | $1,080.00 | $39.34 | $1,180.20 | ||||
4 | 2510 Removal of Pavement | 45 | S.Y. | $25.00 | $1,125.00 | $16.00 | $720.00 | $17.50 | $787.50 | ||||
5 | 2301 PCC Pavement, Class C4, 6" | 45 | S.Y. | $80.00 | $3,600.00 | $92.00 | $4,140.00 | $115.56 | $5,200.20 | ||||
6 | 2507 Revetment, Class E | 16 | Tons | $80.00 | $1,280.00 | $110.00 | $1,760.00 | $59.00 | $944.00 | ||||
7 | 2528 Traffic Control | 1 | L.S. | $1,500.00 | $1,500.00 | $600.00 | $600.00 | $200.00 | $200.00 | ||||
8 | 2533 Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,200.00 | $2,200.00 | ||||
9 | 2599 Removal & Disposal of Existing CMP | 1 | L.S. | $1,000.00 | $1,000.00 | $700.00 | $700.00 | $450.00 | $450.00 | ||||
10 | 2601 Stabilize Crop - Seed & Fertilize | 1 | L.S. | $750.00 | $750.00 | $1,200.00 | $1,200.00 | $475.00 | $475.00 | ||||
$23,495.00 | $24,252.00 | $24,687.30 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | Jasper Construction Services Inc | |||||||||||
Funding Source: 100% Park & Institutional Road Fund, | 928 N 19th Ave E | ||||||||||||
Newton IA 50208 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 641-792-8650 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2416 Culv, Conc Rdwy Pipe, 24" RCP Class 3 | 56 | L.F. | $135.00 | $7,560.00 | $0.00 | $0.00 | ||||||
2 | 2416 Apron, Conc, 24" RCP Class 3 | 2 | Each | $2,300.00 | $4,600.00 | $0.00 | $0.00 | ||||||
3 | 2312 Class A Crushed Stone | 30 | Tons | $40.00 | $1,200.00 | $0.00 | $0.00 | ||||||
4 | 2510 Removal of Pavement | 45 | S.Y. | $40.00 | $1,800.00 | $0.00 | $0.00 | ||||||
5 | 2301 PCC Pavement, Class C4, 6" | 45 | S.Y. | $110.00 | $4,950.00 | $0.00 | $0.00 | ||||||
6 | 2507 Revetment, Class E | 16 | Tons | $95.00 | $1,520.00 | $0.00 | $0.00 | ||||||
7 | 2528 Traffic Control | 1 | L.S. | $750.00 | $750.00 | $0.00 | $0.00 | ||||||
8 | 2533 Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
9 | 2599 Removal & Disposal of Existing CMP | 1 | L.S. | $1,960.00 | $1,960.00 | $0.00 | $0.00 | ||||||
10 | 2601 Stabilize Crop - Seed & Fertilize | 1 | L.S. | $1,000.00 | $1,000.00 | $0.00 | $0.00 | ||||||
$27,840.00 | $0.00 | $0.00 | |||||||||||
12/21/2024