IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Iowa River  Date: 7/24/2025  Project No.  
  Steamboat Rock Dam Mitigation - Phase 1  County:   HARDIN  Time: 11:00 a.m.  23-02-42-01

 

 
1
2
3
Estimated Cost: $1,391,000.00
Contractor: 
Shift General ContractingThree Oaks Contruction IncGehrke, Inc
Funding Source: 19% Marine Fuel Tax, 19% Water Trails/Low Head Dams, 62% Federal-Other, 4812 Harvest CT SW
515 S Flynn St
1405 21st
ced IA  52404North Sioux City SD  57049Eldora IA  50627
Plan Sets Requested: 9
Quantities
319-536-0111712-251-1767641-858-3821
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$223,000.00$223,000.00 $100,000.00$100,000.00 $134,200.00$134,200.00 
2NPDES GENERAL PERMIT #2 & SWPPP1L.S.$20,000.00$20,000.00 $3,500.00$3,500.00 $27,000.00$27,000.00 
3TRAFFIC CONTROL1L.S.$6,000.00$6,000.00 $5,000.00$5,000.00 $6,854.00$6,854.00 
4CONSTRUCTION STAKING1L.S.$20,000.00$20,000.00 $5,000.00$5,000.00 $20,000.00$20,000.00 
5CLEARING AND GRUBBING3.11Acres$10,000.00$31,100.00 $4,500.00$13,995.00 $13,320.00$41,425.20 
6TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"2790C.Y.$8.00$22,320.00 $6.00$16,740.00 $13.50$37,665.00 
7EXCAVATION, CLASS 1012480C.Y.$9.00$112,320.00 $10.00$124,800.00 $10.00$124,800.00 
8SUBGRADE PREPARATION, 12-INCH2323S.Y.$2.00$4,646.00 $4.34$10,081.82 $2.50$5,807.50 
9GRAVEL ROAD SURFACING, CLASS 'A' CRUSHED STONE73Tons$26.00$1,898.00 $46.00$3,358.00 $27.30$1,992.90 
10GRAVEL ROAD SURFACING (SALVAGED)415Tons$9.00$3,735.00 $20.00$8,300.00 $13.50$5,602.50 
11STABILIZED CONSTRUCTION ENTRANCE, MACADAM STONE40Tons$27.00$1,080.00 $50.00$2,000.00 $27.30$1,092.00 
12ROAD MAINTENANCE1L.S.$15,075.35$15,075.35 $3,000.00$3,000.00 $16,650.00$16,650.00 
13STORM SEWER, TRENCHED, RCP, 15 IN.54L.F.$125.00$6,750.00 $300.00$16,200.00 $89.25$4,819.50 
1415" CONCRETE APRON2Each$3,000.00$6,000.00 $1,400.00$2,800.00 $2,872.00$5,744.00 
15CLASS 'E' REVETMENT784Tons$54.00$42,336.00 $63.00$49,392.00 $50.75$39,788.00 
16EROSION STONE156Tons$45.00$7,020.00 $57.00$8,892.00 $47.50$7,410.00 
17MACADAM STONE798Tons$32.00$25,536.00 $50.00$39,900.00 $32.00$25,536.00 
18WEIR STONE (4'x5'x1.2' MIN.)400Tons$120.00$48,000.00 $150.00$60,000.00 $120.00$48,000.00 
19DAM REMOVAL1L.S.$195,000.00$195,000.00 $200,000.00$200,000.00 $253,000.00$253,000.00 
20REMOVAL OF SIDEWALK, PCC13S.Y.$20.00$260.00 $10.00$130.00 $24.00$312.00 
21GRAVEL ROAD REMOVAL3045S.Y.$2.00$6,090.00 $1.00$3,045.00 $6.50$19,792.50 
22BOAT RAMP REMOVAL AND SALVAGE1L.S.$1,200.00$1,200.00 $3,000.00$3,000.00 $4,000.00$4,000.00 
23EXCAVATION, CLASS 10736C.Y.$9.00$6,624.00 $10.00$7,360.00 $10.00$7,360.00 
24CLASS 'E' REVETMENT12Tons$54.00$648.00 $63.00$756.00 $50.75$609.00 
25EROSION STONE106Tons$45.00$4,770.00 $57.00$6,042.00 $47.50$5,035.00 
26MACADAM STONE66Tons$32.00$2,112.00 $50.00$3,300.00 $32.00$2,112.00 
27WEIR STONE (3'x2'x1' MIN.)64Tons$120.00$7,680.00 $150.00$9,600.00 $120.00$7,680.00 
28WEIR STONE (3.5'x3'x2' MIN.)32Tons$120.00$3,840.00 $150.00$4,800.00 $120.00$3,840.00 
29EXCAVATION, CLASS 1040C.Y.$9.00$360.00 $10.00$400.00 $10.00$400.00 
306" MINUS CHOKE STONE55Tons$34.00$1,870.00 $46.00$2,530.00 $46.25$2,543.75 
31WEIR STONE (3.5'x3'x2' MIN.)184Tons$120.00$22,080.00 $150.00$27,600.00 $120.00$22,080.00 
32EXCAVATION, CLASS 1020C.Y.$9.00$180.00 $10.00$200.00 $10.00$200.00 
336" MINUS CHOKE STONE42Tons$34.00$1,428.00 $46.00$1,932.00 $46.25$1,942.50 
34WEIR STONE (3.5'x3'x2' MIN.)140Tons$120.00$16,800.00 $150.00$21,000.00 $120.00$16,800.00 
35WEIR STONE (3.5'x3'x2' MIN.)42Tons$120.00$5,040.00 $150.00$6,300.00 $120.00$5,040.00 
36TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"164C.Y.$8.00$1,312.00 $6.00$984.00 $13.50$2,214.00 
37EXCAVATION, CLASS 10171C.Y.$9.00$1,539.00 $10.00$1,710.00 $10.00$1,710.00 
38SUBGRADE PREPARATION, 12-INCH282S.Y.$2.00$564.00 $4.34$1,223.88 $2.50$705.00 
39CLASS 'A' CRUSHED STONE60Tons$25.00$1,500.00 $46.00$2,760.00 $25.25$1,515.00 
40MACADAM STONE55Tons$32.00$1,760.00 $50.00$2,750.00 $32.00$1,760.00 
41TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$8.00$5,040.00 $6.00$3,780.00 $13.50$8,505.00 
42EXCAVATION, CLASS 101507C.Y.$9.00$13,563.00 $10.00$15,070.00 $10.00$15,070.00 
43SUBGRADE PREPARATION, 12-INCH600S.Y.$2.00$1,200.00 $4.34$2,604.00 $2.50$1,500.00 
44CLASS 'A' CRUSHED STONE126Tons$26.00$3,276.00 $46.00$5,796.00 $25.25$3,181.50 
45MACADAM STONE392Tons$32.00$12,544.00 $50.00$19,600.00 $32.00$12,544.00 
46CLASS 'E' REVETMENT582Tons$54.00$31,428.00 $63.00$36,666.00 $50.75$29,536.50 
47EXCAVATION, CLASS 101757C.Y.$9.00$15,813.00 $10.00$17,570.00 $10.00$17,570.00 
48SUBGRADE PREPARATION, 12-INCH446S.Y.$2.00$892.00 $4.34$1,935.64 $2.50$1,115.00 
49CLASS 'A' CRUSHED STONE98Tons$27.00$2,646.00 $46.00$4,508.00 $25.25$2,474.50 
50MACADAM STONE356Tons$32.00$11,392.00 $50.00$17,800.00 $32.00$11,392.00 
51CLASS 'E' REVETMENT433Tons$54.00$23,382.00 $63.00$27,279.00 $50.75$21,974.75 
52SEEDING/FERTILIZING/MULCHING3.9Acres$2,750.00$10,725.00 $5,000.00$19,500.00 $4,150.00$16,185.00 
53WATERS EDGE SEEDING2.15Acres$825.00$1,773.75 $5,000.00$10,750.00 $2,125.00$4,568.75 
54TEMPORARY SEEDING AND HYDROMULCHING6.05Acres$1,500.00$9,075.00 $3,000.00$18,150.00 $2,400.00$14,520.00 
55WATTLE3846L.F.$1.80$6,922.80 $3.00$11,538.00 $2.50$9,615.00 
56EROSION MATTING9756S.Y.$3.55$34,633.80 $4.50$43,902.00 $4.50$43,902.00 
57ROLLED EROSION CONTROL PRODUCT, TYPE 1.C8686S.Y.$1.05$9,120.30 $5.00$43,430.00 $1.20$10,423.20 
      $1,072,900.00  $1,080,260.34  $1,139,114.55 
Alternate        
58TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$8.00$5,040.00 $6.00$3,780.00 $13.50$8,505.00 
Alternate        
59EXCAVATION, CLASS 101524C.Y.$9.00$13,716.00 $10.00$15,240.00 $10.00$15,240.00 
Alternate        
60SUBGRADE PREPARATION, 12-INCH600S.Y.$2.00$1,200.00 $4.34$2,604.00 $2.50$1,500.00 
Alternate        
61REINFORCED PCC 6-INCH33S.Y.$172.00$5,676.00 $70.00$2,310.00 $212.00$6,996.00 
Alternate        
62REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$172.00$3,096.00 $100.00$1,800.00 $212.00$3,816.00 
Alternate        
63CLASS 'A' CRUSHED STONE131Tons$27.00$3,537.00 $46.00$6,026.00 $25.25$3,307.75 
Alternate        
64MACADAM STONE388Tons$31.00$12,028.00 $50.00$19,400.00 $32.00$12,416.00 
Alternate        
65CLASS 'E' REVETMENT582Tons$54.00$31,428.00 $63.00$36,666.00 $50.75$29,536.50 
Alternate        
66EXCAVATION, CLASS 101802C.Y.$9.00$16,218.00 $10.00$18,020.00 $10.00$18,020.00 
Alternate        
67SUBGRADE PREPARATION, 12-INCH446S.Y.$2.00$892.00 $4.34$1,935.64 $2.50$1,115.00 
Alternate        
68REINFORCED PCC 6-INCH45S.Y.$172.00$7,740.00 $70.00$3,150.00 $212.00$9,540.00 
Alternate        
69REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$172.00$3,096.00 $100.00$1,800.00 $212.00$3,816.00 
Alternate        
70CLASS 'A' CRUSHED STONE104Tons$27.00$2,808.00 $46.00$4,784.00 $25.25$2,626.00 
Alternate        
71MACADAM STONE344Tons$32.00$11,008.00 $50.00$17,200.00 $32.00$11,008.00 
Alternate        
72CLASS 'E' REVETMENT433Tons$54.00$23,382.00 $63.00$27,279.00 $50.75$21,974.75 
      $1,213,765.00  $1,242,254.98  $1,288,531.55 
 
4
5
6
Estimated Cost: $1,391,000.00
Contractor: 
Boomerang Corp of IowaPeterson Contractors, IncH & H Construction & Development LLC
Funding Source: 19% Marine Fuel Tax, 19% Water Trails/Low Head Dams, 62% Federal-Other, 13225 Circle Drive Suite A
104 Blackhawk St
12475 Hwy 52
Anamosa IA  52205Reinbeck IA  50669Miles IA  52064
Plan Sets Requested: 9
Quantities
319-462-4435319-345-2713563-357-1849
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$180,000.00$180,000.00 $135,000.00$135,000.00 $275,000.00$275,000.00 
2NPDES GENERAL PERMIT #2 & SWPPP1L.S.$5,000.00$5,000.00 $25,000.00$25,000.00 $10,000.00$10,000.00 
3TRAFFIC CONTROL1L.S.$1,200.00$1,200.00 $17,500.00$17,500.00 $5,000.00$5,000.00 
4CONSTRUCTION STAKING1L.S.$4,200.00$4,200.00 $14,000.00$14,000.00 $10,000.00$10,000.00 
5CLEARING AND GRUBBING3.11Acres$8,500.00$26,435.00 $18,000.00$55,980.00 $3,000.00$9,330.00 
6TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"2790C.Y.$10.00$27,900.00 $9.25$25,807.50 $6.00$16,740.00 
7EXCAVATION, CLASS 1012480C.Y.$10.00$124,800.00 $11.75$146,640.00 $4.50$56,160.00 
8SUBGRADE PREPARATION, 12-INCH2323S.Y.$1.00$2,323.00 $3.00$6,969.00 $1.50$3,484.50 
9GRAVEL ROAD SURFACING, CLASS 'A' CRUSHED STONE73Tons$40.00$2,920.00 $25.75$1,879.75 $35.00$2,555.00 
10GRAVEL ROAD SURFACING (SALVAGED)415Tons$20.00$8,300.00 $14.50$6,017.50 $21.42$8,889.30 
11STABILIZED CONSTRUCTION ENTRANCE, MACADAM STONE40Tons$50.00$2,000.00 $40.00$1,600.00 $50.00$2,000.00 
12ROAD MAINTENANCE1L.S.$2,200.00$2,200.00 $10,000.00$10,000.00 $10,000.00$10,000.00 
13STORM SEWER, TRENCHED, RCP, 15 IN.54L.F.$100.00$5,400.00 $160.00$8,640.00 $140.00$7,560.00 
1415" CONCRETE APRON2Each$4,000.00$8,000.00 $4,500.00$9,000.00 $3,500.00$7,000.00 
15CLASS 'E' REVETMENT784Tons$80.00$62,720.00 $55.00$43,120.00 $65.00$50,960.00 
16EROSION STONE156Tons$60.00$9,360.00 $58.00$9,048.00 $50.00$7,800.00 
17MACADAM STONE798Tons$50.00$39,900.00 $35.00$27,930.00 $50.00$39,900.00 
18WEIR STONE (4'x5'x1.2' MIN.)400Tons$200.00$80,000.00 $350.00$140,000.00 $125.00$50,000.00 
19DAM REMOVAL1L.S.$270,000.00$270,000.00 $430,000.00$430,000.00 $800,000.00$800,000.00 
20REMOVAL OF SIDEWALK, PCC13S.Y.$20.00$260.00 $20.00$260.00 $100.00$1,300.00 
21GRAVEL ROAD REMOVAL3045S.Y.$5.00$15,225.00 $3.50$10,657.50 $6.89$20,980.05 
22BOAT RAMP REMOVAL AND SALVAGE1L.S.$3,200.00$3,200.00 $7,250.00$7,250.00 $10,000.00$10,000.00 
23EXCAVATION, CLASS 10736C.Y.$20.00$14,720.00 $11.75$8,648.00 $15.00$11,040.00 
24CLASS 'E' REVETMENT12Tons$80.00$960.00 $65.00$780.00 $70.00$840.00 
25EROSION STONE106Tons$80.00$8,480.00 $60.00$6,360.00 $50.00$5,300.00 
26MACADAM STONE66Tons$50.00$3,300.00 $45.00$2,970.00 $50.00$3,300.00 
27WEIR STONE (3'x2'x1' MIN.)64Tons$200.00$12,800.00 $350.00$22,400.00 $125.00$8,000.00 
28WEIR STONE (3.5'x3'x2' MIN.)32Tons$200.00$6,400.00 $350.00$11,200.00 $125.00$4,000.00 
29EXCAVATION, CLASS 1040C.Y.$20.00$800.00 $25.00$1,000.00 $100.00$4,000.00 
306" MINUS CHOKE STONE55Tons$60.00$3,300.00 $50.00$2,750.00 $50.00$2,750.00 
31WEIR STONE (3.5'x3'x2' MIN.)184Tons$200.00$36,800.00 $350.00$64,400.00 $125.00$23,000.00 
32EXCAVATION, CLASS 1020C.Y.$20.00$400.00 $25.00$500.00 $100.00$2,000.00 
336" MINUS CHOKE STONE42Tons$60.00$2,520.00 $50.00$2,100.00 $50.00$2,100.00 
34WEIR STONE (3.5'x3'x2' MIN.)140Tons$200.00$28,000.00 $350.00$49,000.00 $125.00$17,500.00 
35WEIR STONE (3.5'x3'x2' MIN.)42Tons$200.00$8,400.00 $350.00$14,700.00 $125.00$5,250.00 
36TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"164C.Y.$20.00$3,280.00 $9.25$1,517.00 $5.00$820.00 
37EXCAVATION, CLASS 10171C.Y.$40.00$6,840.00 $25.00$4,275.00 $4.50$769.50 
38SUBGRADE PREPARATION, 12-INCH282S.Y.$1.00$282.00 $3.00$846.00 $1.75$493.50 
39CLASS 'A' CRUSHED STONE60Tons$40.00$2,400.00 $30.00$1,800.00 $35.00$2,100.00 
40MACADAM STONE55Tons$50.00$2,750.00 $50.00$2,750.00 $50.00$2,750.00 
41TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$20.00$12,600.00 $9.25$5,827.50 $6.00$3,780.00 
42EXCAVATION, CLASS 101507C.Y.$20.00$30,140.00 $11.75$17,707.25 $4.50$6,781.50 
43SUBGRADE PREPARATION, 12-INCH600S.Y.$1.00$600.00 $3.00$1,800.00 $1.50$900.00 
44CLASS 'A' CRUSHED STONE126Tons$40.00$5,040.00 $25.50$3,213.00 $45.00$5,670.00 
45MACADAM STONE392Tons$50.00$19,600.00 $35.00$13,720.00 $50.00$19,600.00 
46CLASS 'E' REVETMENT582Tons$80.00$46,560.00 $55.00$32,010.00 $75.00$43,650.00 
47EXCAVATION, CLASS 101757C.Y.$20.00$35,140.00 $11.75$20,644.75 $4.50$7,906.50 
48SUBGRADE PREPARATION, 12-INCH446S.Y.$1.00$446.00 $3.00$1,338.00 $2.00$892.00 
49CLASS 'A' CRUSHED STONE98Tons$40.00$3,920.00 $25.50$2,499.00 $35.00$3,430.00 
50MACADAM STONE356Tons$50.00$17,800.00 $35.00$12,460.00 $50.00$17,800.00 
51CLASS 'E' REVETMENT433Tons$80.00$34,640.00 $55.00$23,815.00 $75.00$32,475.00 
52SEEDING/FERTILIZING/MULCHING3.9Acres$4,000.00$15,600.00 $4,000.00$15,600.00 $5,000.00$19,500.00 
53WATERS EDGE SEEDING2.15Acres$2,000.00$4,300.00 $3,500.00$7,525.00 $3,000.00$6,450.00 
54TEMPORARY SEEDING AND HYDROMULCHING6.05Acres$2,000.00$12,100.00 $2,500.00$15,125.00 $5,000.00$30,250.00 
55WATTLE3846L.F.$3.00$11,538.00 $2.00$7,692.00 $6.50$24,999.00 
56EROSION MATTING9756S.Y.$4.50$43,902.00 $3.50$34,146.00 $4.00$39,024.00 
57ROLLED EROSION CONTROL PRODUCT, TYPE 1.C8686S.Y.$2.00$17,372.00 $1.20$10,423.20 $5.00$43,430.00 
Alternate        
58TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$20.00$12,600.00 $9.25$5,827.50 $5.00$3,150.00 
Alternate        
59EXCAVATION, CLASS 101524C.Y.$20.00$30,480.00 $11.75$17,907.00 $4.50$6,858.00 
Alternate        
60SUBGRADE PREPARATION, 12-INCH600S.Y.$1.00$600.00 $3.00$1,800.00 $1.50$900.00 
Alternate        
61REINFORCED PCC 6-INCH33S.Y.$80.00$2,640.00 $500.00$16,500.00 $700.00$23,100.00 
Alternate        
62REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$90.00$1,620.00 $370.00$6,660.00 $700.00$12,600.00 
Alternate        
63CLASS 'A' CRUSHED STONE131Tons$40.00$5,240.00 $25.50$3,340.50 $35.00$4,585.00 
Alternate        
64MACADAM STONE388Tons$50.00$19,400.00 $35.00$13,580.00 $50.00$19,400.00 
Alternate        
65CLASS 'E' REVETMENT582Tons$80.00$46,560.00 $55.00$32,010.00 $75.00$43,650.00 
Alternate        
66EXCAVATION, CLASS 101802C.Y.$20.00$36,040.00 $11.75$21,173.50 $4.00$7,208.00 
Alternate        
67SUBGRADE PREPARATION, 12-INCH446S.Y.$1.00$446.00 $3.00$1,338.00 $2.00$892.00 
Alternate        
68REINFORCED PCC 6-INCH45S.Y.$80.00$3,600.00 $500.00$22,500.00 $600.00$27,000.00 
Alternate        
69REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$90.00$1,620.00 $370.00$6,660.00 $6.00$108.00 
Alternate        
70CLASS 'A' CRUSHED STONE104Tons$40.00$4,160.00 $25.50$2,652.00 $40.00$4,160.00 
Alternate        
71MACADAM STONE344Tons$50.00$17,200.00 $35.00$12,040.00 $50.00$17,200.00 
Alternate        
72CLASS 'E' REVETMENT433Tons$80.00$34,640.00 $55.00$23,815.00 $75.00$32,475.00 
      $1,551,919.00  $1,743,644.45  $2,010,495.85 
 
7
8
9
Estimated Cost: $1,391,000.00
Contractor: 
HGS, LLC
Funding Source: 19% Marine Fuel Tax, 19% Water Trails/Low Head Dams, 62% Federal-Other, 3700 SE Beisser Drive Suites D & E


Grimes IA  50111    
Plan Sets Requested: 9
Quantities
262-895-9005
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$184,400.00$184,400.00 $0.00 $0.00 
2NPDES GENERAL PERMIT #2 & SWPPP1L.S.$22,300.00$22,300.00 $0.00 $0.00 
3TRAFFIC CONTROL1L.S.$4,800.00$4,800.00 $0.00 $0.00 
4CONSTRUCTION STAKING1L.S.$6,400.00$6,400.00 $0.00 $0.00 
5CLEARING AND GRUBBING3.11Acres$21,600.00$67,176.00 $0.00 $0.00 
6TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"2790C.Y.$17.86$49,829.40 $0.00 $0.00 
7EXCAVATION, CLASS 1012480C.Y.$9.43$117,686.40 $0.00 $0.00 
8SUBGRADE PREPARATION, 12-INCH2323S.Y.$2.25$5,226.75 $0.00 $0.00 
9GRAVEL ROAD SURFACING, CLASS 'A' CRUSHED STONE73Tons$84.00$6,132.00 $0.00 $0.00 
10GRAVEL ROAD SURFACING (SALVAGED)415Tons$54.00$22,410.00 $0.00 $0.00 
11STABILIZED CONSTRUCTION ENTRANCE, MACADAM STONE40Tons$231.00$9,240.00 $0.00 $0.00 
12ROAD MAINTENANCE1L.S.$23,300.00$23,300.00 $0.00 $0.00 
13STORM SEWER, TRENCHED, RCP, 15 IN.54L.F.$250.00$13,500.00 $0.00 $0.00 
1415" CONCRETE APRON2Each$4,480.00$8,960.00 $0.00 $0.00 
15CLASS 'E' REVETMENT784Tons$78.00$61,152.00 $0.00 $0.00 
16EROSION STONE156Tons$85.00$13,260.00 $0.00 $0.00 
17MACADAM STONE798Tons$74.00$59,052.00 $0.00 $0.00 
18WEIR STONE (4'x5'x1.2' MIN.)400Tons$552.00$220,800.00 $0.00 $0.00 
19DAM REMOVAL1L.S.$543,400.00$543,400.00 $0.00 $0.00 
20REMOVAL OF SIDEWALK, PCC13S.Y.$64.10$833.30 $0.00 $0.00 
21GRAVEL ROAD REMOVAL3045S.Y.$3.55$10,809.75 $0.00 $0.00 
22BOAT RAMP REMOVAL AND SALVAGE1L.S.$1,800.00$1,800.00 $0.00 $0.00 
23EXCAVATION, CLASS 10736C.Y.$21.44$15,779.84 $0.00 $0.00 
24CLASS 'E' REVETMENT12Tons$225.00$2,700.00 $0.00 $0.00 
25EROSION STONE106Tons$110.00$11,660.00 $0.00 $0.00 
26MACADAM STONE66Tons$101.00$6,666.00 $0.00 $0.00 
27WEIR STONE (3'x2'x1' MIN.)64Tons$603.00$38,592.00 $0.00 $0.00 
28WEIR STONE (3.5'x3'x2' MIN.)32Tons$739.00$23,648.00 $0.00 $0.00 
29EXCAVATION, CLASS 1040C.Y.$127.00$5,080.00 $0.00 $0.00 
306" MINUS CHOKE STONE55Tons$125.00$6,875.00 $0.00 $0.00 
31WEIR STONE (3.5'x3'x2' MIN.)184Tons$573.00$105,432.00 $0.00 $0.00 
32EXCAVATION, CLASS 1020C.Y.$142.00$2,840.00 $0.00 $0.00 
336" MINUS CHOKE STONE42Tons$126.00$5,292.00 $0.00 $0.00 
34WEIR STONE (3.5'x3'x2' MIN.)140Tons$584.00$81,760.00 $0.00 $0.00 
35WEIR STONE (3.5'x3'x2' MIN.)42Tons$530.00$22,260.00 $0.00 $0.00 
36TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"164C.Y.$36.00$5,904.00 $0.00 $0.00 
37EXCAVATION, CLASS 10171C.Y.$28.00$4,788.00 $0.00 $0.00 
38SUBGRADE PREPARATION, 12-INCH282S.Y.$4.14$1,167.48 $0.00 $0.00 
39CLASS 'A' CRUSHED STONE60Tons$67.00$4,020.00 $0.00 $0.00 
40MACADAM STONE55Tons$73.00$4,015.00 $0.00 $0.00 
41TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$36.00$22,680.00 $0.00 $0.00 
42EXCAVATION, CLASS 101507C.Y.$15.90$23,961.30 $0.00 $0.00 
43SUBGRADE PREPARATION, 12-INCH600S.Y.$3.43$2,058.00 $0.00 $0.00 
44CLASS 'A' CRUSHED STONE126Tons$66.00$8,316.00 $0.00 $0.00 
45MACADAM STONE392Tons$73.00$28,616.00 $0.00 $0.00 
46CLASS 'E' REVETMENT582Tons$82.00$47,724.00 $0.00 $0.00 
47EXCAVATION, CLASS 101757C.Y.$13.22$23,227.54 $0.00 $0.00 
48SUBGRADE PREPARATION, 12-INCH446S.Y.$3.50$1,561.00 $0.00 $0.00 
49CLASS 'A' CRUSHED STONE98Tons$66.00$6,468.00 $0.00 $0.00 
50MACADAM STONE356Tons$73.00$25,988.00 $0.00 $0.00 
51CLASS 'E' REVETMENT433Tons$80.00$34,640.00 $0.00 $0.00 
52SEEDING/FERTILIZING/MULCHING3.9Acres$10,120.00$39,468.00 $0.00 $0.00 
53WATERS EDGE SEEDING2.15Acres$1,680.00$3,612.00 $0.00 $0.00 
54TEMPORARY SEEDING AND HYDROMULCHING6.05Acres$5,790.00$35,029.50 $0.00 $0.00 
55WATTLE3846L.F.$3.76$14,460.96 $0.00 $0.00 
56EROSION MATTING9756S.Y.$4.00$39,024.00 $0.00 $0.00 
57ROLLED EROSION CONTROL PRODUCT, TYPE 1.C8686S.Y.$2.18$18,935.48 $0.00 $0.00 
Alternate        
58TOPSOIL, STRIP, SALVAGE AND SPREAD, 6"630C.Y.$36.00$22,680.00 $0.00 $0.00 
Alternate        
59EXCAVATION, CLASS 101524C.Y.$15.88$24,201.12 $0.00 $0.00 
Alternate        
60SUBGRADE PREPARATION, 12-INCH600S.Y.$4.95$2,970.00 $0.00 $0.00 
Alternate        
61REINFORCED PCC 6-INCH33S.Y.$281.00$9,273.00 $0.00 $0.00 
Alternate        
62REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$299.00$5,382.00 $0.00 $0.00 
Alternate        
63CLASS 'A' CRUSHED STONE131Tons$69.00$9,039.00 $0.00 $0.00 
Alternate        
64MACADAM STONE388Tons$73.00$28,324.00 $0.00 $0.00 
Alternate        
65CLASS 'E' REVETMENT582Tons$81.00$47,142.00 $0.00 $0.00 
Alternate        
66EXCAVATION, CLASS 101802C.Y.$13.80$24,867.60 $0.00 $0.00 
Alternate        
67SUBGRADE PREPARATION, 12-INCH446S.Y.$3.50$1,561.00 $0.00 $0.00 
Alternate        
68REINFORCED PCC 6-INCH45S.Y.$275.00$12,375.00 $0.00 $0.00 
Alternate        
69REINFORCED PCC BOAT RAMP TRANSITION SECTION 6-INCH18S.Y.$296.00$5,328.00 $0.00 $0.00 
Alternate        
70CLASS 'A' CRUSHED STONE104Tons$66.00$6,864.00 $0.00 $0.00 
Alternate        
71MACADAM STONE344Tons$74.00$25,456.00 $0.00 $0.00 
Alternate        
72CLASS 'E' REVETMENT433Tons$80.00$34,640.00 $0.00 $0.00 
      $2,436,819.42  $0.00  $0.00 
 



 

12/5/2025