IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Crystal Hills WMA | Date: 9/18/2025 | Project No. |
| Dike Repair | County: | HANCOCK | Time: 3:00 PM | 23-02-41-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $16,120.00 | Contractor: | Adam Laubenthal DBA Laubenthal Excavation | Ground Line Company LLC | ||||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 1245 180th St | 4782 County Rd E17 | |||||||||||
| Bradgate IA 50520 | Onslow IA 52321 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 515-368-1112 | 319-251-0425 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $0.00 | |||||
| 2 | 12" CMP, 14 Ga. | 1 | L.S. | $2,500.00 | $2,500.00 | $2,330.00 | $2,330.00 | $0.00 | |||||
| 3 | On-Site Topsoil | 214 | C.Y. | $9.34 | $1,998.76 | $15.00 | $3,210.00 | $0.00 | |||||
| 4 | Class 10 Excavation, On-Site Borrow | 150 | C.Y. | $6.66 | $999.00 | $9.00 | $1,350.00 | $0.00 | |||||
| 5 | Class 10 Excavation, Contractor Furnished | 265 | C.Y. | $10.95 | $2,901.75 | $18.00 | $4,770.00 | $0.00 | |||||
| 6 | 1" Clean Stone | 15 | Tons | $40.00 | $600.00 | $47.00 | $705.00 | $0.00 | |||||
| 7 | Erosion Stone | 8 | Tons | $62.50 | $500.00 | $55.00 | $440.00 | $0.00 | |||||
| 8 | Fire Proof Cover | 1 | Each | $2,500.00 | $2,500.00 | $1,600.00 | $1,600.00 | $0.00 | |||||
| 9 | Clearing and Grubbing | 1 | L.S. | $2,000.00 | $2,000.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| $16,499.51 | $20,405.00 | $0.00 | |||||||||||
12/5/2025