IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Manchester Fisheries Management Unit | Date: 11/13/2025 | Project No. |
| Spring Branch 319 Project | County: | DELAWARE | Time: 3:00 p.m. | 24-03-28-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $73,000.00 | Contractor: | Sommer Excavating LLC | Offset Construction | Connolly Construction Inc | |||||||||
| Funding Source: 75% Other, 21% REAP Land Management, 4% Cash Donation, | 750 16th Ave NW | 9126 North Pleasant Grove Rd | 18409 N Cascade Rd | ||||||||||
| Waukon IA | Farley IA 52046 | Peosta IA 52068 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-568-1677 | 563-542-9464 | 563-876-3225 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $4,200.00 | $4,200.00 | $1,000.00 | $1,000.00 | $3,500.00 | $3,500.00 | ||||
| 2 | Safety Fence | 250 | L.F. | $1.70 | $425.00 | $2.00 | $500.00 | $2.35 | $587.50 | ||||
| 3 | Ag Fence Demolition | 1200 | L.F. | $1.25 | $1,500.00 | $1.00 | $1,200.00 | $1.50 | $1,800.00 | ||||
| 4 | Ag Fence Installation | 1200 | L.F. | $4.00 | $4,800.00 | $8.25 | $9,900.00 | $9.75 | $11,700.00 | ||||
| 5 | Clearing and Grubbing | 0.7 | Acres | $11,500.00 | $8,050.00 | $7,000.00 | $4,900.00 | $7,500.00 | $5,250.00 | ||||
| 6 | Bank Reshaping-Class 10 Excavation | 575 | C.Y. | $1.73 | $994.75 | $6.35 | $3,651.25 | $5.85 | $3,363.75 | ||||
| 7 | Class E Revetment | 375 | Tons | $31.15 | $11,681.25 | $34.00 | $12,750.00 | $32.00 | $12,000.00 | ||||
| 8 | Top Soil Remove and Place | 150 | C.Y. | $4.67 | $700.50 | $26.00 | $3,900.00 | $8.15 | $1,222.50 | ||||
| 9 | Remove and Dispose 12 inch CMP | 1 | L.S. | $500.00 | $500.00 | $300.00 | $300.00 | $200.00 | $200.00 | ||||
| 10 | Install 24 " CMP | 15 | L.F. | $50.00 | $750.00 | $87.00 | $1,305.00 | $65.50 | $982.50 | ||||
| 11 | SWPPP Preparation and Management | 1 | L.S. | $1,200.00 | $1,200.00 | $1,000.00 | $1,000.00 | $750.00 | $750.00 | ||||
| 12 | 9 Inch Filter Sock Installation | 2500 | L.F. | $2.36 | $5,900.00 | $2.25 | $5,625.00 | $2.50 | $6,250.00 | ||||
| 13 | 9 inch Filter Sock Removal | 2500 | L.F. | $0.80 | $2,000.00 | $0.25 | $625.00 | $0.50 | $1,250.00 | ||||
| 14 | Seeding, Fertilizer and Mulch | 0.95 | Acres | $3,500.00 | $3,325.00 | $2,300.00 | $2,185.00 | $1,875.00 | $1,781.25 | ||||
| $46,026.50 | $48,841.25 | $50,637.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $73,000.00 | Contractor: | Connolly Excavating, Inc | Adam Laubenthal DBA Laubenthal Excavation | Ludovissy Enterprises | |||||||||
| Funding Source: 75% Other, 21% REAP Land Management, 4% Cash Donation, | 23709 N Cascade Rd | 1245 180th St | 702 S 2nd St | ||||||||||
| Cascade IA 52033 | Bradgate IA 50520 | Guttenberg IA 52052 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-590-9770 | 515-368-1112 | 563-880-4866 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,802.41 | $3,802.41 | $4,500.00 | $4,500.00 | $4,000.00 | $4,000.00 | ||||
| 2 | Safety Fence | 250 | L.F. | $1.75 | $437.50 | $4.00 | $1,000.00 | $3.00 | $750.00 | ||||
| 3 | Ag Fence Demolition | 1200 | L.F. | $1.00 | $1,200.00 | $1.25 | $1,500.00 | $2.00 | $2,400.00 | ||||
| 4 | Ag Fence Installation | 1200 | L.F. | $4.85 | $5,820.00 | $11.66 | $13,992.00 | $10.00 | $12,000.00 | ||||
| 5 | Clearing and Grubbing | 0.7 | Acres | $10,750.00 | $7,525.00 | $15,000.00 | $10,500.00 | $6,000.00 | $4,200.00 | ||||
| 6 | Bank Reshaping-Class 10 Excavation | 575 | C.Y. | $5.56 | $3,197.00 | $3.50 | $2,012.50 | $5.00 | $2,875.00 | ||||
| 7 | Class E Revetment | 375 | Tons | $25.50 | $9,562.50 | $26.66 | $9,997.50 | $40.00 | $15,000.00 | ||||
| 8 | Top Soil Remove and Place | 150 | C.Y. | $13.00 | $1,950.00 | $4.33 | $649.50 | $5.00 | $750.00 | ||||
| 9 | Remove and Dispose 12 inch CMP | 1 | L.S. | $300.00 | $300.00 | $250.00 | $250.00 | $2,000.00 | $2,000.00 | ||||
| 10 | Install 24 " CMP | 15 | L.F. | $66.70 | $1,000.50 | $86.66 | $1,299.90 | $125.00 | $1,875.00 | ||||
| 11 | SWPPP Preparation and Management | 1 | L.S. | $2,500.00 | $2,500.00 | $1,200.00 | $1,200.00 | $3,000.00 | $3,000.00 | ||||
| 12 | 9 Inch Filter Sock Installation | 2500 | L.F. | $4.00 | $10,000.00 | $2.40 | $6,000.00 | $2.00 | $5,000.00 | ||||
| 13 | 9 inch Filter Sock Removal | 2500 | L.F. | $0.50 | $1,250.00 | $0.50 | $1,250.00 | $2.00 | $5,000.00 | ||||
| 14 | Seeding, Fertilizer and Mulch | 0.95 | Acres | $4,300.00 | $4,085.00 | $2,000.00 | $1,900.00 | $4,500.00 | $4,275.00 | ||||
| $52,629.91 | $56,051.40 | $63,125.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $73,000.00 | Contractor: | Jones Contractors & Associates LLC | Steger Const., Inc | Precisions Corporation | |||||||||
| Funding Source: 75% Other, 21% REAP Land Management, 4% Cash Donation, | 13635 Route 52 | 3297 Vine Rd | 505 Cherry St Ct | ||||||||||
| Dyersville IA 52040 | dyer IA 52040 | Port Byron IL 61275 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-880-7885 | 563-542-2944 | 309-236-9072 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $10,500.00 | $10,500.00 | $3,500.00 | $3,500.00 | ||||
| 2 | Safety Fence | 250 | L.F. | $2.00 | $500.00 | $5.50 | $1,375.00 | $9.60 | $2,400.00 | ||||
| 3 | Ag Fence Demolition | 1200 | L.F. | $2.09 | $2,508.00 | $2.45 | $2,940.00 | $2.26 | $2,712.00 | ||||
| 4 | Ag Fence Installation | 1200 | L.F. | $20.42 | $24,504.00 | $5.95 | $7,140.00 | $11.10 | $13,320.00 | ||||
| 5 | Clearing and Grubbing | 0.7 | Acres | $2,857.15 | $2,000.005 | $30,000.00 | $21,000.00 | $26,890.00 | $18,823.00 | ||||
| 6 | Bank Reshaping-Class 10 Excavation | 575 | C.Y. | $10.44 | $6,003.00 | $7.20 | $4,140.00 | $33.65 | $19,348.75 | ||||
| 7 | Class E Revetment | 375 | Tons | $41.74 | $15,652.50 | $40.00 | $15,000.00 | $99.50 | $37,312.50 | ||||
| 8 | Top Soil Remove and Place | 150 | C.Y. | $6.00 | $900.00 | $6.00 | $900.00 | $61.10 | $9,165.00 | ||||
| 9 | Remove and Dispose 12 inch CMP | 1 | L.S. | $1,000.00 | $1,000.00 | $190.00 | $190.00 | $750.00 | $750.00 | ||||
| 10 | Install 24 " CMP | 15 | L.F. | $166.67 | $2,500.05 | $65.00 | $975.00 | $322.67 | $4,840.05 | ||||
| 11 | SWPPP Preparation and Management | 1 | L.S. | $2,100.00 | $2,100.00 | $3,300.00 | $3,300.00 | $8,160.00 | $8,160.00 | ||||
| 12 | 9 Inch Filter Sock Installation | 2500 | L.F. | $2.80 | $7,000.00 | $2.45 | $6,125.00 | $5.30 | $13,250.00 | ||||
| 13 | 9 inch Filter Sock Removal | 2500 | L.F. | $0.60 | $1,500.00 | $0.20 | $500.00 | $3.44 | $8,600.00 | ||||
| 14 | Seeding, Fertilizer and Mulch | 0.95 | Acres | $3,578.95 | $3,400.003 | $3,000.00 | $2,850.00 | $7,393.68 | $7,023.996 | ||||
| $74,567.558 | $76,935.00 | $149,205.296 | |||||||||||
12/5/2025