Bids For: | Location: | Yellow River State Forest | Date: 5/23/2024 | Project No. |
Paint Creek Streambank Improvements | County: | ALLAMAKEE | Time: 11:00 a.m. | 24-03-03-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $180,000.00 | Contractor: | Tschiggfrie Excavating Co | Cornwell Construction | Szabo Construction Co Inc | |||||||||
Funding Source: 66% Federal-EPA, 34% Cash Donation, | 425 Julien Dubuque Dr | 1678 Rabbit Run Ln | 152 S West St | ||||||||||
Dubuque IA 52003 | Hapers Ferry IA 52146 | Postville IA 52162 | |||||||||||
Plan Sets Requested: 5 | Quantities | 563-557-7450 | 563-880-2071 | 563-864-7515 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $3,250.00 | $3,250.00 | $500.00 | $500.00 | $5,000.00 | $5,000.00 | ||||
2 | Clearing and Grubbing | 0.86 | Acres | $2,100.00 | $1,806.00 | $3,500.00 | $3,010.00 | $5,000.00 | $4,300.00 | ||||
3 | Bank Shaping | 1502 | L.F. | $2.90 | $4,355.80 | $6.00 | $9,012.00 | $9.50 | $14,269.00 | ||||
4 | Wattles, 9" | 1550 | L.F. | $2.25 | $3,487.50 | $3.00 | $4,650.00 | $3.75 | $5,812.50 | ||||
5 | Revetment, Class E | 2800 | Tons | $26.00 | $72,800.00 | $26.00 | $72,800.00 | $25.00 | $70,000.00 | ||||
6 | Revetment, Class B | 640 | Tons | $26.00 | $16,640.00 | $35.00 | $22,400.00 | $30.00 | $19,200.00 | ||||
7 | Slope Protection Matting | 800 | S.Y. | $4.25 | $3,400.00 | $5.00 | $4,000.00 | $4.75 | $3,800.00 | ||||
8 | Seeding and Mulching | 0.86 | Acres | $1,395.00 | $1,199.70 | $1,000.00 | $860.00 | $800.00 | $688.00 | ||||
$106,939.00 | $117,232.00 | $123,069.50 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $180,000.00 | Contractor: | Riehm Construction Co | Bacon Concrete LLC | Nick Jones Earthmoving | |||||||||
Funding Source: 66% Federal-EPA, 34% Cash Donation, | 2340 9th St SW | 370 N Bancroft St | 1223 Peterson Hollow Dr | ||||||||||
Waukon IA 52172 | Postville IA 52162 | Waukon IA 52172 | |||||||||||
Plan Sets Requested: 5 | Quantities | 563-568-3314 | 563-864-7602 | 563-535-7156 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $2,000.00 | $2,000.00 | $10,000.00 | $10,000.00 | ||||
2 | Clearing and Grubbing | 0.86 | Acres | $3,500.00 | $3,010.00 | $4,000.00 | $3,440.00 | $6,000.00 | $5,160.00 | ||||
3 | Bank Shaping | 1502 | L.F. | $3.25 | $4,881.50 | $3.50 | $5,257.00 | $5.00 | $7,510.00 | ||||
4 | Wattles, 9" | 1550 | L.F. | $4.60 | $7,130.00 | $3.50 | $5,425.00 | $3.00 | $4,650.00 | ||||
5 | Revetment, Class E | 2800 | Tons | $31.60 | $88,480.00 | $35.00 | $98,000.00 | $30.00 | $84,000.00 | ||||
6 | Revetment, Class B | 640 | Tons | $31.00 | $19,840.00 | $40.00 | $25,600.00 | $50.00 | $32,000.00 | ||||
7 | Slope Protection Matting | 800 | S.Y. | $4.50 | $3,600.00 | $7.25 | $5,800.00 | $12.00 | $9,600.00 | ||||
8 | Seeding and Mulching | 0.86 | Acres | $3,000.00 | $2,580.00 | $1,500.00 | $1,290.00 | $3,000.00 | $2,580.00 | ||||
$132,521.50 | $146,812.00 | $155,500.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $180,000.00 | Contractor: | Connolly Construction Inc | Shift Companies | ||||||||||
Funding Source: 66% Federal-EPA, 34% Cash Donation, | 18409 N Cascade Rd | 4812 Harvest Ct SW | |||||||||||
Peosta IA 52068 | Cedar Rapids IA 52404 | ||||||||||||
Plan Sets Requested: 5 | Quantities | 563-876-3225 | 319-440-9676 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $9,200.00 | $9,200.00 | $20,000.00 | $20,000.00 | $0.00 | |||||
2 | Clearing and Grubbing | 0.86 | Acres | $13,400.00 | $11,524.00 | $8,000.00 | $6,880.00 | $0.00 | |||||
3 | Bank Shaping | 1502 | L.F. | $13.90 | $20,877.80 | $22.00 | $33,044.00 | $0.00 | |||||
4 | Wattles, 9" | 1550 | L.F. | $3.25 | $5,037.50 | $3.75 | $5,812.50 | $0.00 | |||||
5 | Revetment, Class E | 2800 | Tons | $28.00 | $78,400.00 | $29.00 | $81,200.00 | $0.00 | |||||
6 | Revetment, Class B | 640 | Tons | $37.50 | $24,000.00 | $36.00 | $23,040.00 | $0.00 | |||||
7 | Slope Protection Matting | 800 | S.Y. | $7.70 | $6,160.00 | $4.75 | $3,800.00 | $0.00 | |||||
8 | Seeding and Mulching | 0.86 | Acres | $1,770.00 | $1,522.20 | $1,000.00 | $860.00 | $0.00 | |||||
$156,721.50 | $174,636.50 | $0.00 | |||||||||||