IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ledges State Park | Date: 1/22/2026 | Project No. |
| Oak Woods Shelter Repairs | County: | BOONE | Time: 3:00 p.m. | 24-02-08-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $260,000.00 | Contractor: | Holman Construction, LLC | Eick & Day Construction LLC | R.H. Grabau Construction, Inc | |||||||||
| Funding Source: 100% Infrastructure, | 7006 R57 Hwy | 4705 NW 59th Ave | 871 P Ave PO Box 99 | ||||||||||
| Indianola IA 50125 | Johnston IA 50131 | Boone IA 50036 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 515-250-8072 | 515-644-3100 | 515-432-6935 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $26,865.00 | $26,865.00 | $29,554.00 | $29,554.00 | $20,000.00 | $20,000.00 | ||||
| 2 | DEMOLITION | 1 | L.S. | $23,250.00 | $23,250.00 | $5,310.00 | $5,310.00 | $31,700.00 | $31,700.00 | ||||
| 3 | CONCRETE FOOTINGS AND PAD | 1 | L.S. | $9,800.00 | $9,800.00 | $14,750.00 | $14,750.00 | $10,000.00 | $10,000.00 | ||||
| 4 | CHIMNEY STONE REPLACEMENT AND REPOINTING | 1 | L.S. | $12,400.00 | $12,400.00 | $15,340.00 | $15,340.00 | $21,500.00 | $21,500.00 | ||||
| 5 | CHIMNEY CROWN AND FLUE REPAIRS | 1 | L.S. | $2,870.00 | $2,870.00 | $3,540.00 | $3,540.00 | $5,000.00 | $5,000.00 | ||||
| 6 | FIREPLACE BRICK REPAIR AND REPOINTING | 1 | L.S. | $3,500.00 | $3,500.00 | $1,770.00 | $1,770.00 | $4,000.00 | $4,000.00 | ||||
| 7 | LOG COLUMN CONSTRUCTION AND ACCESSORIES | 1 | L.S. | $17,454.00 | $17,454.00 | $25,657.00 | $25,657.00 | $14,000.00 | $14,000.00 | ||||
| 8 | LOG BEAMS AND RAFTERS CONSTRUCTION | 1 | L.S. | $23,036.00 | $23,036.00 | $27,436.00 | $27,436.00 | $42,000.00 | $42,000.00 | ||||
| 9 | LOG PURLIN CONSTRUCTION | 1 | L.S. | $32,000.00 | $32,000.00 | $53,356.00 | $53,356.00 | $10,700.00 | $10,700.00 | ||||
| 10 | LOG RAILING AND COLUMN BRACES REINSTALLATION CONSTRUCTION | 1 | L.S. | $5,600.00 | $5,600.00 | $5,900.00 | $5,900.00 | $39,100.00 | $39,100.00 | ||||
| 11 | ROOF SHEATHING, UNDERLAYMENT, SHINGLES AND ACCESSORIES | 1 | L.S. | $8,250.00 | $8,250.00 | $24,843.00 | $24,843.00 | $9,500.00 | $9,500.00 | ||||
| 12 | LOG STAINING, PROTECTANTS, CONSOLIDANTS, AND COATINGS | 1 | L.S. | $4,300.00 | $4,300.00 | $5,660.00 | $5,660.00 | $5,500.00 | $5,500.00 | ||||
| 13 | CHIMNEY FLASHING REPLACEMENT AND SEALANT | 1 | L.S. | $1,785.00 | $1,785.00 | $1,416.00 | $1,416.00 | $1,000.00 | $1,000.00 | ||||
| 14 | ELECTRICAL PANEL, CONDUIT AND OUTDOOR RECEPTACLES | 1 | L.S. | $8,800.00 | $8,800.00 | $2,950.00 | $2,950.00 | $6,000.00 | $6,000.00 | ||||
| 15 | NEW ADA GRILL UNIT | 1 | L.S. | $3,790.00 | $3,790.00 | $1,180.00 | $1,180.00 | $600.00 | $600.00 | ||||
| 16 | CLEAN AND SEAL EXISTING CONCRETE | 1 | L.S. | $1,560.00 | $1,560.00 | $3,534.00 | $3,534.00 | $4,000.00 | $4,000.00 | ||||
| 17 | CLEAN, SEAL, RESTRIPE ADA PARKING CONCRETE PAD | 1 | L.S. | $3,500.00 | $3,500.00 | $2,069.00 | $2,069.00 | $1,000.00 | $1,000.00 | ||||
| 18 | SEEDING AND EROSION CONTROL | 1 | L.S. | $4,950.00 | $4,950.00 | $5,310.00 | $5,310.00 | $500.00 | $500.00 | ||||
| 19 | HENNING SHELTER - TIMBER BEAMS REPAIR | 1 | L.S. | $4,800.00 | $4,800.00 | $590.00 | $590.00 | $8,800.00 | $8,800.00 | ||||
| 20 | HENNING SHELTER - CHIMNEY FLASHING REPAIR | 1 | L.S. | $1,785.00 | $1,785.00 | $944.00 | $944.00 | $1,000.00 | $1,000.00 | ||||
| 21 | HENNING SHELTER - REPOINTING AT TIMBER HEADER | 1 | L.S. | $850.00 | $850.00 | $1,180.00 | $1,180.00 | $1,000.00 | $1,000.00 | ||||
| 22 | HENNING SHELTER - REALIGN AND SECURE GABLE END LOG RAFTERS | 1 | L.S. | $1,420.00 | $1,420.00 | $2,360.00 | $2,360.00 | $1,500.00 | $1,500.00 | ||||
| 23 | HENNING SHELTER - REPOINT MORTAR AT CHIMNEY(25% OF AREA EST.) | 1 | L.S. | $3,400.00 | $3,400.00 | $4,720.00 | $4,720.00 | $20,000.00 | $20,000.00 | ||||
| $205,965.00 | $239,369.00 | $258,400.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $260,000.00 | Contractor: | Shyft Collective | Woodruff Construction, Inc | Home Boy Enterprises, LTD | |||||||||
| Funding Source: 100% Infrastructure, | 740 18th St | 1890 Kountry Lane | 7575 NE 56th St | ||||||||||
| Des Moines IA 50319 | Fort Dodge IA 50501 | Bondurant IA 50035 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 515-556-8903 | 515-576-1118 | 515-669-3138 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $17,000.00 | $17,000.00 | $15,535.00 | $15,535.00 | $103,886.00 | $103,886.00 | ||||
| 2 | DEMOLITION | 1 | L.S. | $19,800.00 | $19,800.00 | $28,717.00 | $28,717.00 | $15,600.00 | $15,600.00 | ||||
| 3 | CONCRETE FOOTINGS AND PAD | 1 | L.S. | $9,300.00 | $9,300.00 | $8,499.00 | $8,499.00 | $4,800.00 | $4,800.00 | ||||
| 4 | CHIMNEY STONE REPLACEMENT AND REPOINTING | 1 | L.S. | $25,530.00 | $25,530.00 | $27,024.00 | $27,024.00 | $20,786.37 | $20,786.37 | ||||
| 5 | CHIMNEY CROWN AND FLUE REPAIRS | 1 | L.S. | $4,550.00 | $4,550.00 | $4,525.00 | $4,525.00 | $16,907.76 | $16,907.76 | ||||
| 6 | FIREPLACE BRICK REPAIR AND REPOINTING | 1 | L.S. | $7,750.00 | $7,750.00 | $6,465.00 | $6,465.00 | $11,830.89 | $11,830.89 | ||||
| 7 | LOG COLUMN CONSTRUCTION AND ACCESSORIES | 1 | L.S. | $21,345.00 | $21,345.00 | $30,274.00 | $30,274.00 | $25,973.17 | $25,973.17 | ||||
| 8 | LOG BEAMS AND RAFTERS CONSTRUCTION | 1 | L.S. | $37,700.00 | $37,700.00 | $30,381.00 | $30,381.00 | $21,813.17 | $21,813.17 | ||||
| 9 | LOG PURLIN CONSTRUCTION | 1 | L.S. | $36,325.00 | $36,325.00 | $27,789.00 | $27,789.00 | $21,813.17 | $21,813.17 | ||||
| 10 | LOG RAILING AND COLUMN BRACES REINSTALLATION CONSTRUCTION | 1 | L.S. | $7,980.00 | $7,980.00 | $25,721.00 | $25,721.00 | $12,973.14 | $12,973.14 | ||||
| 11 | ROOF SHEATHING, UNDERLAYMENT, SHINGLES AND ACCESSORIES | 1 | L.S. | $14,533.00 | $14,533.00 | $45,274.00 | $45,274.00 | $4,680.00 | $4,680.00 | ||||
| 12 | LOG STAINING, PROTECTANTS, CONSOLIDANTS, AND COATINGS | 1 | L.S. | $15,410.00 | $15,410.00 | $6,593.00 | $6,593.00 | $12,000.00 | $12,000.00 | ||||
| 13 | CHIMNEY FLASHING REPLACEMENT AND SEALANT | 1 | L.S. | $6,050.00 | $6,050.00 | $7,217.00 | $7,217.00 | $1,600.00 | $1,600.00 | ||||
| 14 | ELECTRICAL PANEL, CONDUIT AND OUTDOOR RECEPTACLES | 1 | L.S. | $6,800.00 | $6,800.00 | $2,585.00 | $2,585.00 | $6,500.00 | $6,500.00 | ||||
| 15 | NEW ADA GRILL UNIT | 1 | L.S. | $2,100.00 | $2,100.00 | $961.00 | $961.00 | $1,244.00 | $1,244.00 | ||||
| 16 | CLEAN AND SEAL EXISTING CONCRETE | 1 | L.S. | $6,500.00 | $6,500.00 | $3,991.00 | $3,991.00 | $5,200.00 | $5,200.00 | ||||
| 17 | CLEAN, SEAL, RESTRIPE ADA PARKING CONCRETE PAD | 1 | L.S. | $2,195.00 | $2,195.00 | $1,745.00 | $1,745.00 | $2,000.00 | $2,000.00 | ||||
| 18 | SEEDING AND EROSION CONTROL | 1 | L.S. | $5,950.00 | $5,950.00 | $3,038.00 | $3,038.00 | $1,500.00 | $1,500.00 | ||||
| 19 | HENNING SHELTER - TIMBER BEAMS REPAIR | 1 | L.S. | $2,100.00 | $2,100.00 | $4,329.00 | $4,329.00 | $1,400.00 | $1,400.00 | ||||
| 20 | HENNING SHELTER - CHIMNEY FLASHING REPAIR | 1 | L.S. | $2,500.00 | $2,500.00 | $2,270.00 | $2,270.00 | $1,600.00 | $1,600.00 | ||||
| 21 | HENNING SHELTER - REPOINTING AT TIMBER HEADER | 1 | L.S. | $1,900.00 | $1,900.00 | $1,710.00 | $1,710.00 | $4,751.43 | $4,751.43 | ||||
| 22 | HENNING SHELTER - REALIGN AND SECURE GABLE END LOG RAFTERS | 1 | L.S. | $2,400.00 | $2,400.00 | $1,952.00 | $1,952.00 | $1,400.00 | $1,400.00 | ||||
| 23 | HENNING SHELTER - REPOINT MORTAR AT CHIMNEY(25% OF AREA EST.) | 1 | L.S. | $6,750.00 | $6,750.00 | $3,232.00 | $3,232.00 | $3,427.30 | $3,427.30 | ||||
| $262,468.00 | $289,827.00 | $303,686.40 | |||||||||||
2/19/2026