IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   George Wyth State Park  Date: 4/23/2026  Project No.  
  Office and Shop Building  County:   BLACK HAWK  Time: 11:00 a.m.  24-03-07-01

 

 
1
2
3
Estimated Cost: $1,430,677.00
Contractor: 
Matt Construction IncSteege Construction, IncPeters Construction Corporation
Funding Source: 85% Infrastructure, 15% Federal-Boat Safety (Coast Guard), 203 Y Ave
2601 Easton Ave
901 Black Hawk Road
Sumner IA  50674Waverly IA  50677Waterloo IA  50701
Plan Sets Requested: 9
Quantities
563-578-8418319-249-3492319-236-2003
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$24,150.00$24,150.00 $6,761.00$6,761.00 $24,900.00$24,900.00 
2DIVISION 1 - GENERAL AND ADMINISTRATIVE1L.S.$33,951.00$33,951.00 $24,610.00$24,610.00 $43,951.00$43,951.00 
3DIVISION 2 - EXISTING CONDITIONS1L.S.$62,299.65$62,299.65 $40,553.00$40,553.00 $31,635.00$31,635.00 
4DIVISION 3 - CONCRETE1L.S.$196,623.26$196,623.26 $201,848.00$201,848.00 $80,537.00$80,537.00 
5DIVISION 5 - METALS1L.S.$6,300.00$6,300.00 $3,891.00$3,891.00 $3,084.00$3,084.00 
6DIVISION 6 - WOOD1L.S.$87,272.06$87,272.06 $88,801.00$88,801.00 $79,078.00$79,078.00 
7DIVISION 7 - THERMAL AND MOISTURE1L.S.$97,378.58$97,378.58 $132,895.00$132,895.00 $173,518.00$173,518.00 
8DIVISION 8 - OPENINGS1L.S.$51,516.15$51,516.15 $59,225.00$59,225.00 $62,018.00$62,018.00 
9DIVISION 9 - FINISHES1L.S.$22,607.55$22,607.55 $17,772.00$17,772.00 $20,463.00$20,463.00 
10DIVISION 10 - SPECIALTIES1L.S.$4,665.15$4,665.15 $6,353.00$6,353.00 $6,547.00$6,547.00 
11DIVISION 12 - FURNISHINGS1L.S.$7,673.19$7,673.19 $7,724.00$7,724.00 $381.00$381.00 
12DIVISION 22 - PLUMBING1L.S.$55,148.60$55,148.60 $56,199.00$56,199.00 $61,932.00$61,932.00 
13DIVISION 23 - HEATING, VENTILATION, AND COOLING1L.S.$80,104.50$80,104.50 $82,511.00$82,511.00 $82,055.00$82,055.00 
14DIVISION 26 - ELECTRICAL1L.S.$84,516.60$84,516.60 $85,840.00$85,840.00 $79,846.00$79,846.00 
15DIVISION 27 - COMMUNICATIONS1L.S.$3,150.00$3,150.00 $7,500.00$7,500.00 $5,000.00$5,000.00 
16DIVISION 28 - ELECTRONIC SAFETY AND SECURITY1L.S.$0.00$0.00 $3,500.00$3,500.00 $5,000.00$5,000.00 
17DIVISION 31 - EARTHWORK1L.S.$69,742.05$69,742.05 $76,500.00$76,500.00 $30,549.00$30,549.00 
18DIVISION 32 - EXTERIOR IMPROVEMENTS1L.S.$29,642.03$29,642.03 $34,800.00$34,800.00 $167,393.00$167,393.00 
19DIVISION 33 - SITE UTILITIES1L.S.$31,573.50$31,573.50 $22,300.00$22,300.00 $40,000.00$40,000.00 
      $948,313.87  $959,583.00  $997,887.00 
 
4
5
6
Estimated Cost: $1,430,677.00
Contractor: 
Cardinal ConstructionRice Companies, IncHuff Contracting, Inc
Funding Source: 85% Infrastructure, 15% Federal-Boat Safety (Coast Guard), 1246 Martin Road
6815 Innovative Dr Ste 100
1310 Grandview Ave
Waterloo IA  50701Cedar Falls IA  50613Waterloo IA  50703
Plan Sets Requested: 9
Quantities
319-232-5400319-243-1000319-233-9000
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$0.00$0.00 $13,683.00$13,683.00 $21,515.44$21,515.44 
2DIVISION 1 - GENERAL AND ADMINISTRATIVE1L.S.$106,856.00$106,856.00 $91,726.00$91,726.00 $120,677.24$120,677.24 
3DIVISION 2 - EXISTING CONDITIONS1L.S.$60,848.00$60,848.00 $0.00$0.00 $0.00$0.00 
4DIVISION 3 - CONCRETE1L.S.$74,338.00$74,338.00 $96,974.00$96,974.00 $76,766.04$76,766.04 
5DIVISION 5 - METALS1L.S.$10,754.00$10,754.00 $3,158.00$3,158.00 $0.00$0.00 
6DIVISION 6 - WOOD1L.S.$81,088.00$81,088.00 $99,855.00$99,855.00 $93,719.83$93,719.83 
7DIVISION 7 - THERMAL AND MOISTURE1L.S.$178,029.00$178,029.00 $169,095.00$169,095.00 $221,346.18$221,346.18 
8DIVISION 8 - OPENINGS1L.S.$59,873.00$59,873.00 $61,269.00$61,269.00 $55,668.34$55,668.34 
9DIVISION 9 - FINISHES1L.S.$20,862.00$20,862.00 $19,686.00$19,686.00 $34,653.40$34,653.40 
10DIVISION 10 - SPECIALTIES1L.S.$6,942.00$6,942.00 $7,010.00$7,010.00 $2,110.71$2,110.71 
11DIVISION 12 - FURNISHINGS1L.S.$0.00$0.00 $0.00$0.00 $0.00$0.00 
12DIVISION 22 - PLUMBING1L.S.$62,827.00$62,827.00 $78,938.00$78,938.00 $60,966.36$60,966.36 
13DIVISION 23 - HEATING, VENTILATION, AND COOLING1L.S.$83,243.00$83,243.00 $78,938.00$78,938.00 $80,775.43$80,775.43 
14DIVISION 26 - ELECTRICAL1L.S.$90,129.00$90,129.00 $92,594.00$92,594.00 $84,457.87$84,457.87 
15DIVISION 27 - COMMUNICATIONS1L.S.$0.00$0.00 $0.00$0.00 $3,000.00$3,000.00 
16DIVISION 28 - ELECTRONIC SAFETY AND SECURITY1L.S.$0.00$0.00 $0.00$0.00 $0.00$0.00 
17DIVISION 31 - EARTHWORK1L.S.$74,449.00$74,449.00 $226,481.00$226,481.00 $296,001.61$296,001.61 
18DIVISION 32 - EXTERIOR IMPROVEMENTS1L.S.$118,734.00$118,734.00 $108,810.00$108,810.00 $0.00$0.00 
19DIVISION 33 - SITE UTILITIES1L.S.$25,321.00$25,321.00 $0.00$0.00 $0.00$0.00 
      $1,054,293.00  $1,148,217.00  $1,151,658.45 
 
7
8
9
Estimated Cost: $1,430,677.00
Contractor: 
N.B. Koch General Contractors
Funding Source: 85% Infrastructure, 15% Federal-Boat Safety (Coast Guard), 1521 W 7th St
PO Box 829


Cedar Falls IA  50613    
Plan Sets Requested: 9
Quantities
319-269-0889
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$33,800.00$33,800.00 $0.00 $0.00 
2DIVISION 1 - GENERAL AND ADMINISTRATIVE1L.S.$38,000.00$38,000.00 $0.00 $0.00 
3DIVISION 2 - EXISTING CONDITIONS1L.S.$68,500.00$68,500.00 $0.00 $0.00 
4DIVISION 3 - CONCRETE1L.S.$119,200.00$119,200.00 $0.00 $0.00 
5DIVISION 5 - METALS1L.S.$10,100.00$10,100.00 $0.00 $0.00 
6DIVISION 6 - WOOD1L.S.$130,100.00$130,100.00 $0.00 $0.00 
7DIVISION 7 - THERMAL AND MOISTURE1L.S.$177,000.00$177,000.00 $0.00 $0.00 
8DIVISION 8 - OPENINGS1L.S.$61,700.00$61,700.00 $0.00 $0.00 
9DIVISION 9 - FINISHES1L.S.$22,000.00$22,000.00 $0.00 $0.00 
10DIVISION 10 - SPECIALTIES1L.S.$9,000.00$9,000.00 $0.00 $0.00 
11DIVISION 12 - FURNISHINGS1L.S.$0.00$0.00 $0.00 $0.00 
12DIVISION 22 - PLUMBING1L.S.$52,500.00$52,500.00 $0.00 $0.00 
13DIVISION 23 - HEATING, VENTILATION, AND COOLING1L.S.$77,100.00$77,100.00 $0.00 $0.00 
14DIVISION 26 - ELECTRICAL1L.S.$88,000.00$88,000.00 $0.00 $0.00 
15DIVISION 27 - COMMUNICATIONS1L.S.$0.00$0.00 $0.00 $0.00 
16DIVISION 28 - ELECTRONIC SAFETY AND SECURITY1L.S.$0.00$0.00 $0.00 $0.00 
17DIVISION 31 - EARTHWORK1L.S.$226,800.00$226,800.00 $0.00 $0.00 
18DIVISION 32 - EXTERIOR IMPROVEMENTS1L.S.$36,000.00$36,000.00 $0.00 $0.00 
19DIVISION 33 - SITE UTILITIES1L.S.$37,300.00$37,300.00 $0.00 $0.00 
      $1,187,100.00  $0.00  $0.00 
 



 

6/6/2026