IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Big Creek State Park | Date: 5/18/2023 | Project No. |
| Fishing Pier & Path REBID | County: | POLK | Time: 11:00 AM | 21-02-77-12 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $400,000.00 | Contractor: | Dixon Construction Co | United Contractors, Inc | Herberger Construction Company Inc | |||||||||
| Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | 409 Driftwood St | 6678 NW 62 Ave PO Box 347 | 2508 West 2nd Ave | ||||||||||
| Correctionville IA 51016 | Johnston IA 50131 | Indianola IA 50125 | |||||||||||
| Plan Sets Requested: 1 | Quantities | 712-372-4224 | 515-276-6162 | 515-961-5564 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $70,000.00 | $70,000.00 | $50,000.00 | $50,000.00 | $68,000.00 | $68,000.00 | ||||
| 2 | Excavation, Class 10, Waste | 992 | C.Y. | $15.00 | $14,880.00 | $32.00 | $31,744.00 | $25.00 | $24,800.00 | ||||
| 3 | Excavation, Class 10, Embankment | 26 | C.Y. | $30.00 | $780.00 | $52.00 | $1,352.00 | $30.00 | $780.00 | ||||
| 4 | Demolition of Existing Pier | 1 | L.S. | $40,000.00 | $40,000.00 | $46,000.00 | $46,000.00 | $60,000.00 | $60,000.00 | ||||
| 5 | Sediment Log, 8" | 300 | L.F. | $5.00 | $1,500.00 | $4.00 | $1,200.00 | $5.50 | $1,650.00 | ||||
| 6 | PCC Sidewalk Removal | 10 | S.F. | $30.00 | $300.00 | $65.00 | $650.00 | $45.00 | $450.00 | ||||
| 7 | 5" Reinforced PCC Sidewalk | 239 | S.Y. | $100.00 | $23,900.00 | $90.00 | $21,510.00 | $178.00 | $42,542.00 | ||||
| 8 | Class A Crushed Stone | 75 | Tons | $57.00 | $4,275.00 | $50.00 | $3,750.00 | $60.00 | $4,500.00 | ||||
| 9 | Revetment, Class D | 385 | Tons | $77.00 | $29,645.00 | $70.00 | $26,950.00 | $80.00 | $30,800.00 | ||||
| 10 | Seeding, Fertilizing, and Mulching | 1 | L.S. | $5,000.00 | $5,000.00 | $4,000.00 | $4,000.00 | $2,100.00 | $2,100.00 | ||||
| 11 | Fishing Pier, Complete | 1 | L.S. | $282,500.00 | $282,500.00 | $300,000.00 | $300,000.00 | $260,000.00 | $260,000.00 | ||||
| 12 | 6" PCC Patch | 193 | S.Y. | $100.00 | $19,300.00 | $120.00 | $23,160.00 | $145.00 | $27,985.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,500.00 | $5,500.00 | ||||
| $497,080.00 | $515,316.00 | $529,107.00 | |||||||||||