Bids For: | Location: | Ledges and Pine Lake State Park | Date: 2/16/2023 | Project No. |
Sign Installation | County: | BOONE | Time: 3:00 p.m. | 23-02-08-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $63,000.00 | Contractor: | Pillar, Inc | Vieco Development & Construction Co Inc | Voltmer, Inc | |||||||||
Funding Source: 100% Infrastructure, | 210 Freel Dr. | 5180 SE 70th Rd | 1732 Old Stage Road PO Box 200 | ||||||||||
Ames IA 50010 | St Joseph MO 64507 | Decorah IA 52101 | |||||||||||
Plan Sets Requested: 0 | Quantities | 515-321-7938 | 816-3871884 | 563-382-9214 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Demolition of Existing Signage | 1 | L.S. | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | $6,470.00 | $6,470.00 | ||||
2 | Utility Location and Flagging | 1 | L.S. | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | $3,235.00 | $3,235.00 | ||||
3 | Sign Installation at Ledges State Park | 1 | L.S. | $28,000.00 | $28,000.00 | $41,220.00 | $41,220.00 | $67,135.00 | $67,135.00 | ||||
4 | Sign Installation at Pine Lake State Park | 1 | L.S. | $28,000.00 | $28,000.00 | $44,100.00 | $44,100.00 | $71,820.00 | $71,820.00 | ||||
5 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $1,000.00 | $1,000.00 | $6,430.00 | $6,430.00 | ||||
6 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $4,000.00 | $4,000.00 | $15,040.00 | $15,040.00 | ||||
$76,000.00 | $94,320.00 | $170,130.00 | |||||||||||
12/22/2024