IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Fairport Fisheries Management Unit | Date: 2/2/2023 | Project No. |
Pavilion Pavement and Parking Area (REBID) | County: | MUSCATINE | Time: 3:00 p.m. | 23-06-70-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $23,000.00 | Contractor: | Endline Excavating LLC | Triple B Construction | Todd Hackett Construction Co | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 619 Lake St | 710 Ayres Progress Dr | 2925 Cedar St, Suite #1 PO Box 481 | ||||||||||
DeWitt IA 52742 | Wilton IA 52778 | Muscatine IA 52761 | |||||||||||
Plan Sets Requested: 0 | Quantities | 562-357-0969 | 563-732-3478 | 563-264-1539 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,800.00 | $1,800.00 | $1,500.00 | $1,500.00 | $4,500.00 | $4,500.00 | ||||
2 | Site Preparation | 1 | L.S. | $1,850.00 | $1,850.00 | $7,300.00 | $7,300.00 | $3,600.00 | $3,600.00 | ||||
3 | Granular Subbase, Class A | 48 | Tons | $51.50 | $2,472.00 | $50.00 | $2,400.00 | $60.00 | $2,880.00 | ||||
4 | Driveway and Sidewalk, PCC, 6" Depth | 42 | S.Y. | $100.00 | $4,200.00 | $65.00 | $2,730.00 | $55.00 | $2,310.00 | ||||
5 | Pavilion Pavement, Foundation and Footings | 1 | L.S. | $12,650.00 | $12,650.00 | $15,000.00 | $15,000.00 | $13,650.00 | $13,650.00 | ||||
6 | Site Restoration | 1 | L.S. | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | $4,600.00 | $4,600.00 | ||||
$24,972.00 | $29,930.00 | $31,540.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $23,000.00 | Contractor: | SulzCo LLC | Miller Trucking & Excavating Co | Heuer Construction Inc | |||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 2410 Imperial Oaks Dr | 3303 John Deere Rd | 2360 Bypass 61 | ||||||||||
Muscatine IA 52761 | Silvis IL 61282 | Muscatine IA 52761 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-272-8052 | 309-755-7644 | 563-264-8533 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $4,500.00 | $4,500.00 | $6,500.00 | $6,500.00 | ||||
2 | Site Preparation | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $2,850.00 | $2,850.00 | ||||
3 | Granular Subbase, Class A | 48 | Tons | $60.00 | $2,880.00 | $70.00 | $3,360.00 | $50.75 | $2,436.00 | ||||
4 | Driveway and Sidewalk, PCC, 6" Depth | 42 | S.Y. | $115.00 | $4,830.00 | $215.00 | $9,030.00 | $186.50 | $7,833.00 | ||||
5 | Pavilion Pavement, Foundation and Footings | 1 | L.S. | $19,500.00 | $19,500.00 | $22,500.00 | $22,500.00 | $34,186.00 | $34,186.00 | ||||
6 | Site Restoration | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $3,975.00 | $3,975.00 | ||||
$33,710.00 | $44,890.00 | $57,780.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $23,000.00 | Contractor: | VANSExcavating LLC | |||||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 1521 Taylor Ave | ||||||||||||
Belmond IA 50421 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 641-420-5052 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,070.00 | $2,070.00 | $0.00 | $0.00 | ||||||
2 | Site Preparation | 1 | L.S. | $5,129.00 | $5,129.00 | $0.00 | $0.00 | ||||||
3 | Granular Subbase, Class A | 48 | Tons | $1,495.00 | $71,760.00 | $0.00 | $0.00 | ||||||
4 | Driveway and Sidewalk, PCC, 6" Depth | 42 | S.Y. | $2,530.00 | $106,260.00 | $0.00 | $0.00 | ||||||
5 | Pavilion Pavement, Foundation and Footings | 1 | L.S. | $8,543.35 | $8,543.35 | $0.00 | $0.00 | ||||||
6 | Site Restoration | 1 | L.S. | $3,220.00 | $3,220.00 | $0.00 | $0.00 | ||||||
$196,982.35 | $0.00 | $0.00 | |||||||||||
12/22/2024