IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Gypsum City OHV Park | Date: 3/19/2026 | Project No. |
| ATV Bridge | County: | WEBSTER | Time: 11:00 a.m. | 23-02-94-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $220,000.00 | Contractor: | High Plains Structural Group | Dixon Construction | Peterson Contractors, Inc | |||||||||
| Funding Source: 100% ATV Fund, | 7701 Cornhusker Hwy | 1319 Hackberry St | 104 Blackhawk St | ||||||||||
| Lincoln NE 68507 | Correctionville IA 51016 | Reinbeck IA 50669 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 402-833-3842 | 712-372-4224 | 319-575-0796 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $28,410.00 | $28,410.00 | $40,000.00 | $40,000.00 | $51,000.00 | $51,000.00 | ||||
| 2 | Class 10 Excavation | 104 | C.Y. | $18.00 | $1,872.00 | $21.00 | $2,184.00 | $40.25 | $4,186.00 | ||||
| 3 | 100' x 8' Pratt-Truss Bridge | 1 | Each | $175,770.00 | $175,770.00 | $157,000.00 | $157,000.00 | $195,000.00 | $195,000.00 | ||||
| 4 | Bridge Headwall and Foundation | 2 | Each | $35,000.00 | $70,000.00 | $70,000.00 | $140,000.00 | $80,000.00 | $160,000.00 | ||||
| 5 | Construction Staking | 1 | L.S. | $2,500.00 | $2,500.00 | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | ||||
| 6 | Site Restoration | 1 | L.S. | $5,575.00 | $5,575.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | ||||
| $284,127.00 | $347,184.00 | $425,186.00 | |||||||||||
4/1/2026