 Bids For:  Location:   Backbone State Park  Date: 7/28/2022  Project No.  
  Building Foundation & Floor Rebid  County:   DELAWARE  Time: 3:00 p.m.  22-03-28-03

 

 
1
2
3
Estimated Cost: $32,000.00
Contractor: 
Browns Pump Srv & ExcavatingMatt Construction IncBacon Concrete LLC
Funding Source: 100% REAP Land Management, 638 Upper St
203 Y Ave
370 N Bancroft St
Arlington IA  50606Sumner IA  50674Postville IA  52162
Plan Sets Requested: 0
Quantities
563-633-3365563-578-8418563-864-7602
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,000.00$3,000.00 $5,000.00$5,000.00 $3,000.00$3,000.00 
2Trench Footing165L.F.$80.00$13,200.00 $90.90$14,998.50 $84.25$13,901.25 
3PC Concrete Reinforced Slab With Infloor Heating System, Complete1496.75S.F.$10.25$15,341.688 $10.49$15,700.908 $12.56$18,799.18 
4Crushed Stone Base115Tons$22.00$2,530.00 $22.00$2,530.00 $22.00$2,530.00 
5Water, Sewer, & Electrical Stub In1L.S.$2,000.00$2,000.00 $2,140.00$2,140.00 $5,500.00$5,500.00 
      $36,071.688  $40,369.408  $43,730.43 
 



 

7/26/2024