IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | DLS Shooting Range | Date: 7/20/2023 | Project No. |
Range Renovation Phase I | County: | SCOTT | Time: 11:00 a.m. | 23-06-82-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $1,600,000.00 | Contractor: | H&H Construction & Delvelopment LLC | Clinton Engineering Co, Inc | Vieco Development & Construction Co Inc | |||||||||
Funding Source: 60% Federal-Other, 8% F&W Trust - Other, 32% Other, | 12475 Hwy 52 | 2101 Lincoln Way | 5180 SE 70th Rd | ||||||||||
Miles IA 52064 | Clinton IA 52732 | St Joseph MO 64507 | |||||||||||
Plan Sets Requested: 4 | Quantities | 563-357-1849 | 563-242-5732 | 816-387-1884 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Demolition | 1 | L.S. | $65,000.00 | $65,000.00 | $67,900.00 | $67,900.00 | $68,000.00 | $68,000.00 | ||||
2 | Clearing and Grubbing | 1 | L.S. | $18,000.00 | $18,000.00 | $17,500.00 | $17,500.00 | $22,000.00 | $22,000.00 | ||||
3 | Grading | 1 | L.S. | $390,000.00 | $390,000.00 | $246,100.00 | $246,100.00 | $380,640.00 | $380,640.00 | ||||
4 | 8" Filter Sock | 185 | L.F. | $5.50 | $1,017.50 | $5.40 | $999.00 | $6.00 | $1,110.00 | ||||
5 | Seeding, Fertilizing and Mulching | 5 | Acres | $4,000.00 | $20,000.00 | $2,380.00 | $11,900.00 | $5,000.00 | $25,000.00 | ||||
6 | Class A Crushed Stone | 1865.4 | Tons | $31.00 | $57,827.40 | $30.30 | $56,521.62 | $25.00 | $46,635.00 | ||||
7 | Type 1, Class A Subdrain with Perforated SDR 35 Pipe | 714 | L.F. | $51.00 | $36,414.00 | $20.00 | $14,280.00 | $40.00 | $28,560.00 | ||||
8 | 12" RCP Class III | 351 | L.F. | $85.00 | $29,835.00 | $63.00 | $22,113.00 | $92.00 | $32,292.00 | ||||
9 | SW-512 Circular Area Intake w/Type SW-604 Type 4A Casting | 7 | Each | $3,500.00 | $24,500.00 | $1,500.00 | $10,500.00 | $2,530.00 | $17,710.00 | ||||
10 | Black PVC Coated Chain Link Fencing | 1030 | L.F. | $40.00 | $41,200.00 | $35.00 | $36,050.00 | $38.00 | $39,140.00 | ||||
11 | Black PVC Coated Chain Link Fencing 12' Swing Gate | 4 | Each | $1,500.00 | $6,000.00 | $895.00 | $3,580.00 | $950.00 | $3,800.00 | ||||
12 | Black PVC Coated Chain Link Fencing 28' Double Swing Gate | 1 | Each | $3,500.00 | $3,500.00 | $2,760.00 | $2,760.00 | $2,953.00 | $2,953.00 | ||||
13 | 6" Reinforced PCC Pavement | 91.2 | S.Y. | $78.00 | $7,113.60 | $62.00 | $5,654.40 | $85.00 | $7,752.00 | ||||
14 | 5" Reinforced PCC Pavement | 944.6 | S.Y. | $69.00 | $65,177.40 | $59.50 | $56,203.70 | $80.00 | $75,568.00 | ||||
15 | Precast Concrete Parking Wheel Stops | 3 | Each | $225.00 | $675.00 | $239.00 | $717.00 | $150.00 | $450.00 | ||||
16 | Parking Space Cross Hatch Paint Striping | 1 | L.S. | $1,000.00 | $1,000.00 | $379.00 | $379.00 | $750.00 | $750.00 | ||||
17 | Handicap Signage | 1 | L.S. | $2,400.00 | $2,400.00 | $728.00 | $728.00 | $1,600.00 | $1,600.00 | ||||
18 | Existing Storage Building Siding Repair | 1 | L.S. | $8,000.00 | $8,000.00 | $4,338.00 | $4,338.00 | $9,400.00 | $9,400.00 | ||||
19 | Storage Building and Concrete | 1 | L.S. | $55,000.00 | $55,000.00 | $93,060.00 | $93,060.00 | $78,200.00 | $78,200.00 | ||||
20 | LE Range Baffles | 1 | L.S. | $55,000.00 | $55,000.00 | $142,640.00 | $142,640.00 | $81,630.00 | $81,630.00 | ||||
21 | 100 Yard Shooting Structure and Baffles | 1 | L.S. | $91,000.00 | $91,000.00 | $211,495.00 | $211,495.00 | $160,680.00 | $160,680.00 | ||||
22 | 30 Yard Shooting Structure and Baffles | 1 | L.S. | $138,000.00 | $138,000.00 | $185,947.00 | $185,947.00 | $242,397.00 | $242,397.00 | ||||
23 | Concrete Range Sidewalls | 875 | L.F. | $115.00 | $100,625.00 | $322.00 | $281,750.00 | $175.00 | $153,125.00 | ||||
24 | Backstops Eyebrows | 280 | L.F. | $88.00 | $24,640.00 | $131.00 | $36,680.00 | $185.00 | $51,800.00 | ||||
25 | LE Range Pole and Flood Lights | 1 | L.S. | $32,000.00 | $32,000.00 | $22,775.00 | $22,775.00 | $9,660.00 | $9,660.00 | ||||
26 | Electrical Service and Distribution | 1 | L.S. | $115,000.00 | $115,000.00 | $41,280.00 | $41,280.00 | $102,000.00 | $102,000.00 | ||||
27 | NPDES General Permit #2 | 1 | L.S. | $4,000.00 | $4,000.00 | $5,955.00 | $5,955.00 | $7,600.00 | $7,600.00 | ||||
28 | Construction Staking | 1 | L.S. | $5,000.00 | $5,000.00 | $5,955.00 | $5,955.00 | $10,800.00 | $10,800.00 | ||||
29 | Mobilization | 1 | L.S. | $59,500.00 | $59,500.00 | $66,380.00 | $66,380.00 | $85,000.00 | $85,000.00 | ||||
$1,457,424.90 | $1,652,140.72 | $1,746,252.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $1,600,000.00 | Contractor: | Bill Bruce Builders Inc | Tricon General Construction Inc | Sheets Design Build LLC | |||||||||
Funding Source: 60% Federal-Other, 8% F&W Trust - Other, 32% Other, | 900 East Franklin St | 1230 East 12th St | 18284 Hwy 64 | ||||||||||
Eldridge IA 52748 | Dubuque IA 52001 | Maquoketa IA 52060 | |||||||||||
Plan Sets Requested: 4 | Quantities | 563-285-9341 | 563-588-9516 | 563-652-8399 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Demolition | 1 | L.S. | $63,265.07 | $63,265.07 | $110,000.00 | $110,000.00 | $111,619.05 | $111,619.05 | ||||
2 | Clearing and Grubbing | 1 | L.S. | $20,202.05 | $20,202.05 | $77,000.00 | $77,000.00 | $58,201.06 | $58,201.06 | ||||
3 | Grading | 1 | L.S. | $429,281.82 | $429,281.82 | $489,000.00 | $489,000.00 | $316,931.22 | $316,931.22 | ||||
4 | 8" Filter Sock | 185 | L.F. | $3.03 | $560.55 | $5.00 | $925.00 | $5.29 | $978.65 | ||||
5 | Seeding, Fertilizing and Mulching | 5 | Acres | $8,195.00 | $40,975.00 | $2,200.00 | $11,000.00 | $2,328.04 | $11,640.20 | ||||
6 | Class A Crushed Stone | 1865.4 | Tons | $27.28 | $50,888.112 | $25.00 | $46,635.00 | $26.08 | $48,649.632 | ||||
7 | Type 1, Class A Subdrain with Perforated SDR 35 Pipe | 714 | L.F. | $29.15 | $20,813.10 | $31.00 | $22,134.00 | $32.80 | $23,419.20 | ||||
8 | 12" RCP Class III | 351 | L.F. | $53.68 | $18,841.68 | $50.00 | $17,550.00 | $52.91 | $18,571.41 | ||||
9 | SW-512 Circular Area Intake w/Type SW-604 Type 4A Casting | 7 | Each | $1,912.35 | $13,386.45 | $2,200.00 | $15,400.00 | $2,328.04 | $16,296.28 | ||||
10 | Black PVC Coated Chain Link Fencing | 1030 | L.F. | $35.95 | $37,028.50 | $36.00 | $37,080.00 | $34.58 | $35,617.40 | ||||
11 | Black PVC Coated Chain Link Fencing 12' Swing Gate | 4 | Each | $909.70 | $3,638.80 | $1,200.00 | $4,800.00 | $874.97 | $3,499.88 | ||||
12 | Black PVC Coated Chain Link Fencing 28' Double Swing Gate | 1 | Each | $2,808.30 | $2,808.30 | $2,700.00 | $2,700.00 | $2,701.59 | $2,701.59 | ||||
13 | 6" Reinforced PCC Pavement | 91.2 | S.Y. | $88.00 | $8,025.60 | $60.00 | $5,472.00 | $95.26 | $8,687.712 | ||||
14 | 5" Reinforced PCC Pavement | 944.6 | S.Y. | $70.40 | $66,499.84 | $52.00 | $49,119.20 | $80.95 | $76,465.37 | ||||
15 | Precast Concrete Parking Wheel Stops | 3 | Each | $275.00 | $825.00 | $120.00 | $360.00 | $121.69 | $365.07 | ||||
16 | Parking Space Cross Hatch Paint Striping | 1 | L.S. | $1,650.00 | $1,650.00 | $500.00 | $500.00 | $507.94 | $507.94 | ||||
17 | Handicap Signage | 1 | L.S. | $1,650.00 | $1,650.00 | $1,500.00 | $1,500.00 | $1,317.46 | $1,317.46 | ||||
18 | Existing Storage Building Siding Repair | 1 | L.S. | $12,650.00 | $12,650.00 | $7,500.00 | $7,500.00 | $15,132.28 | $15,132.28 | ||||
19 | Storage Building and Concrete | 1 | L.S. | $110,905.70 | $110,905.70 | $49,000.00 | $49,000.00 | $99,422.96 | $99,422.96 | ||||
20 | LE Range Baffles | 1 | L.S. | $85,800.00 | $85,800.00 | $100,000.00 | $100,000.00 | $122,179.89 | $122,179.89 | ||||
21 | 100 Yard Shooting Structure and Baffles | 1 | L.S. | $319,819.06 | $319,819.06 | $225,000.00 | $225,000.00 | $258,190.05 | $258,190.05 | ||||
22 | 30 Yard Shooting Structure and Baffles | 1 | L.S. | $214,978.39 | $214,978.39 | $219,000.00 | $219,000.00 | $247,394.13 | $247,394.13 | ||||
23 | Concrete Range Sidewalls | 875 | L.F. | $189.40 | $165,725.00 | $268.00 | $234,500.00 | $354.10 | $309,837.50 | ||||
24 | Backstops Eyebrows | 280 | L.F. | $205.46 | $57,528.80 | $175.00 | $49,000.00 | $283.77 | $79,455.60 | ||||
25 | LE Range Pole and Flood Lights | 1 | L.S. | $23,137.40 | $23,137.40 | $30,000.00 | $30,000.00 | $22,258.20 | $22,258.20 | ||||
26 | Electrical Service and Distribution | 1 | L.S. | $41,940.80 | $41,940.80 | $40,000.00 | $40,000.00 | $40,347.09 | $40,347.09 | ||||
27 | NPDES General Permit #2 | 1 | L.S. | $6,050.00 | $6,050.00 | $3,500.00 | $3,500.00 | $1,772.49 | $1,772.49 | ||||
28 | Construction Staking | 1 | L.S. | $8,300.00 | $8,300.00 | $7,100.00 | $7,100.00 | $10,052.91 | $10,052.91 | ||||
29 | Mobilization | 1 | L.S. | $70,400.00 | $70,400.00 | $88,224.80 | $88,224.80 | $151,449.74 | $151,449.74 | ||||
$1,897,575.022 | $1,944,000.00 | $2,092,961.964 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $1,600,000.00 | Contractor: | Valley Construction Co | Miller Trucking & Excavating Co | Woodruff Construction Inc | |||||||||
Funding Source: 60% Federal-Other, 8% F&W Trust - Other, 32% Other, | 3610 78th Ave West | 3303 John Deere Rd | 501 Greenfield Dr | ||||||||||
Rock Island IL 61201 | Silvis IL 61282 | Tiffin IA 52340 | |||||||||||
Plan Sets Requested: 4 | Quantities | 309-787-0292 | 309-755-7644 | 319-545-2410 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Demolition | 1 | L.S. | $125,000.00 | $125,000.00 | $109,482.50 | $109,482.50 | $90,870.46 | $90,870.46 | ||||
2 | Clearing and Grubbing | 1 | L.S. | $115,000.00 | $115,000.00 | $10,000.00 | $10,000.00 | $58,830.00 | $58,830.00 | ||||
3 | Grading | 1 | L.S. | $500,000.00 | $500,000.00 | $511,500.00 | $511,500.00 | $320,356.00 | $320,356.00 | ||||
4 | 8" Filter Sock | 185 | L.F. | $5.00 | $925.00 | $3.00 | $555.00 | $5.35 | $989.75 | ||||
5 | Seeding, Fertilizing and Mulching | 5 | Acres | $2,200.00 | $11,000.00 | $2,500.00 | $12,500.00 | $2,353.20 | $11,766.00 | ||||
6 | Class A Crushed Stone | 1865.4 | Tons | $34.50 | $64,356.30 | $25.00 | $46,635.00 | $26.37 | $49,190.598 | ||||
7 | Type 1, Class A Subdrain with Perforated SDR 35 Pipe | 714 | L.F. | $28.50 | $20,349.00 | $45.00 | $32,130.00 | $33.16 | $23,676.24 | ||||
8 | 12" RCP Class III | 351 | L.F. | $68.50 | $24,043.50 | $75.00 | $26,325.00 | $53.48 | $18,771.48 | ||||
9 | SW-512 Circular Area Intake w/Type SW-604 Type 4A Casting | 7 | Each | $2,600.00 | $18,200.00 | $3,250.00 | $22,750.00 | $2,353.14 | $16,471.98 | ||||
10 | Black PVC Coated Chain Link Fencing | 1030 | L.F. | $31.50 | $32,445.00 | $34.00 | $35,020.00 | $38.87 | $40,036.10 | ||||
11 | Black PVC Coated Chain Link Fencing 12' Swing Gate | 4 | Each | $2,050.00 | $8,200.00 | $2,250.00 | $9,000.00 | $1,198.00 | $4,792.00 | ||||
12 | Black PVC Coated Chain Link Fencing 28' Double Swing Gate | 1 | Each | $4,150.00 | $4,150.00 | $4,500.00 | $4,500.00 | $2,877.00 | $2,877.00 | ||||
13 | 6" Reinforced PCC Pavement | 91.2 | S.Y. | $95.00 | $8,664.00 | $95.00 | $8,664.00 | $431.94 | $39,392.928 | ||||
14 | 5" Reinforced PCC Pavement | 944.6 | S.Y. | $105.00 | $99,183.00 | $90.00 | $85,014.00 | $125.68 | $118,717.328 | ||||
15 | Precast Concrete Parking Wheel Stops | 3 | Each | $125.00 | $375.00 | $500.00 | $1,500.00 | $198.33 | $594.99 | ||||
16 | Parking Space Cross Hatch Paint Striping | 1 | L.S. | $450.00 | $450.00 | $200.00 | $200.00 | $1,604.00 | $1,604.00 | ||||
17 | Handicap Signage | 1 | L.S. | $225.00 | $225.00 | $1,050.00 | $1,050.00 | $363.00 | $363.00 | ||||
18 | Existing Storage Building Siding Repair | 1 | L.S. | $22,500.00 | $22,500.00 | $25,000.00 | $25,000.00 | $4,595.00 | $4,595.00 | ||||
19 | Storage Building and Concrete | 1 | L.S. | $125,000.00 | $125,000.00 | $90,000.00 | $90,000.00 | $102,011.00 | $102,011.00 | ||||
20 | LE Range Baffles | 1 | L.S. | $100,000.00 | $100,000.00 | $76,500.00 | $76,500.00 | $69,531.00 | $69,531.00 | ||||
21 | 100 Yard Shooting Structure and Baffles | 1 | L.S. | $300,000.00 | $300,000.00 | $294,060.00 | $294,060.00 | $229,810.00 | $229,810.00 | ||||
22 | 30 Yard Shooting Structure and Baffles | 1 | L.S. | $200,000.00 | $200,000.00 | $435,595.00 | $435,595.00 | $366,402.00 | $366,402.00 | ||||
23 | Concrete Range Sidewalls | 875 | L.F. | $350.00 | $306,250.00 | $225.00 | $196,875.00 | $367.13 | $321,238.75 | ||||
24 | Backstops Eyebrows | 280 | L.F. | $245.00 | $68,600.00 | $521.00 | $145,880.00 | $148.53 | $41,588.40 | ||||
25 | LE Range Pole and Flood Lights | 1 | L.S. | $21,050.00 | $21,050.00 | $27,500.00 | $27,500.00 | $22,499.00 | $22,499.00 | ||||
26 | Electrical Service and Distribution | 1 | L.S. | $38,250.00 | $38,250.00 | $70,000.00 | $70,000.00 | $40,783.00 | $40,783.00 | ||||
27 | NPDES General Permit #2 | 1 | L.S. | $7,000.00 | $7,000.00 | $2,000.00 | $2,000.00 | $1,604.00 | $1,604.00 | ||||
28 | Construction Staking | 1 | L.S. | $12,500.00 | $12,500.00 | $10,000.00 | $10,000.00 | $14,890.00 | $14,890.00 | ||||
29 | Mobilization | 1 | L.S. | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $352,853.00 | $352,853.00 | ||||
$2,283,715.80 | $2,340,235.50 | $2,367,105.004 | |||||||||||
1/29/2025