IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Maquoketa Wildlife Unit | Date: 6/30/2022 | Project No. |
Building Foundation & Floor | County: | DELAWARE | Time: 3:00 PM | 22-03-28-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $25,000.00 | Contractor: | Matt Construction Inc | Browns Pump Srv & Excavating | ||||||||||
Funding Source: 100% REAP Land Management, | 203 Y Ave | 638 Upper St | |||||||||||
Sumner IA 50674 | Arlington IA 50606 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 563-578-8418 | 563-633-3365 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $3,500.00 | $3,500.00 | $0.00 | |||||
2 | Foundation & Footing | 165 | L.F. | $90.90 | $14,998.50 | $100.00 | $16,500.00 | $0.00 | |||||
3 | PC Concrete Reinforced Slab With Infloor Heating System, Complete | 1496.75 | S.F. | $10.49 | $15,700.908 | $11.00 | $16,464.25 | $0.00 | |||||
4 | Crush Stone Base | 115 | Tons | $22.00 | $2,530.00 | $22.00 | $2,530.00 | $0.00 | |||||
5 | Sewer Connection | 1 | L.S. | $1,640.00 | $1,640.00 | $1,800.00 | $1,800.00 | $0.00 | |||||
6 | Water & Electrical Stub In | 1 | L.S. | $500.00 | $500.00 | $500.00 | $500.00 | $0.00 | |||||
$40,369.408 | $41,294.25 | $0.00 | |||||||||||
4/19/2024