IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Little Sioux Delta Access | Date: 7/20/2023 | Project No. |
Parking Lot Expansion | County: | HARRISON | Time: 11:00 a.m. | 23-04-43-01 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $115,000.00 | Contractor: | ![]() | IA Builders Dirt Work LLC | Carley Construction LLC | Johnston Excavating LLC | ![]() | |||||||
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | ![]() | 219 N 10th St | ![]() | 18148 Bungee Ave | ![]() | 10032 Buckeye Ave | ![]() | ||||||
![]() | Albia IA 52531 | ![]() | Council Bluffs IA 51503 | ![]() | Sloan IA 51055 | ![]() | |||||||
Plan Sets Requested: 4 | Quantities | ![]() | 6418955447 | ![]() | 712-256-5818 | ![]() | 712-490-8241 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Grading | 1 | L.S. | ![]() | $10,250.00 | $10,250.00 | ![]() | $7,500.00 | $7,500.00 | ![]() | $10,500.00 | $10,500.00 | ![]() |
2 | Macadam | 963 | Tons | ![]() | $42.00 | $40,446.00 | ![]() | $50.25 | $48,390.75 | ![]() | $47.00 | $45,261.00 | ![]() |
3 | 1" Crushed Road Stone | 652 | Tons | ![]() | $40.00 | $26,080.00 | ![]() | $42.90 | $27,970.80 | ![]() | $47.00 | $30,644.00 | ![]() |
4 | CMP, 24" | 73 | L.F. | ![]() | $20.00 | $1,460.00 | ![]() | $105.00 | $7,665.00 | ![]() | $95.00 | $6,935.00 | ![]() |
5 | Site Restoration | 1 | L.S. | ![]() | $1,850.00 | $1,850.00 | ![]() | $1,750.00 | $1,750.00 | ![]() | $3,500.00 | $3,500.00 | ![]() |
6 | 6" PCC, Reinforced | 159 | S.Y. | ![]() | $90.00 | $14,310.00 | ![]() | $85.25 | $13,554.75 | ![]() | $169.86 | $27,007.74 | ![]() |
7 | Special Backfill | 63 | Tons | ![]() | $40.00 | $2,520.00 | ![]() | $42.90 | $2,702.70 | ![]() | $75.00 | $4,725.00 | ![]() |
8 | Pavement Striping | 156 | L.F. | ![]() | $5.00 | $780.00 | ![]() | $5.00 | $780.00 | ![]() | $20.00 | $3,120.00 | ![]() |
9 | Signs, ADA Parking | 2 | Each | ![]() | $500.00 | $1,000.00 | ![]() | $400.00 | $800.00 | ![]() | $575.00 | $1,150.00 | ![]() |
10 | Clearing and Grubbing | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $4,500.00 | $4,500.00 | ![]() | $4,500.00 | $4,500.00 | ![]() |
11 | Traffic Control | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $500.00 | $500.00 | ![]() | $750.00 | $750.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$102,696.00 | ![]() | $116,114.00 | ![]() | $138,092.74 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
![]() | 4 | 5 | 6 | ![]() | |||||||||
Estimated Cost: $115,000.00 | Contractor: | ![]() | Armodus LLC | L.A. Carlson Contracting Inc | Pruett Grading LLC | ![]() | |||||||
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | ![]() | PO Box 1 | ![]() | 25164 Hillside Drive | ![]() | 3252 Quimby Ave | ![]() | ||||||
![]() | Mondamin IA 51557 | ![]() | Hinton IA 51024 | ![]() | Logan IA 51546 | ![]() | |||||||
Plan Sets Requested: 4 | Quantities | ![]() | 402-669-1898 | ![]() | 712-947-0002 | ![]() | 712-420-0490 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Grading | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $15,000.00 | $15,000.00 | ![]() | $15,000.00 | $15,000.00 | ![]() |
2 | Macadam | 963 | Tons | ![]() | $62.00 | $59,706.00 | ![]() | $48.00 | $46,224.00 | ![]() | $43.00 | $41,409.00 | ![]() |
3 | 1" Crushed Road Stone | 652 | Tons | ![]() | $58.00 | $37,816.00 | ![]() | $43.00 | $28,036.00 | ![]() | $40.00 | $26,080.00 | ![]() |
4 | CMP, 24" | 73 | L.F. | ![]() | $85.00 | $6,205.00 | ![]() | $45.00 | $3,285.00 | ![]() | $47.00 | $3,431.00 | ![]() |
5 | Site Restoration | 1 | L.S. | ![]() | $2,000.00 | $2,000.00 | ![]() | $4,000.00 | $4,000.00 | ![]() | $10,000.00 | $10,000.00 | ![]() |
6 | 6" PCC, Reinforced | 159 | S.Y. | ![]() | $110.00 | $17,490.00 | ![]() | $210.00 | $33,390.00 | ![]() | $350.00 | $55,650.00 | ![]() |
7 | Special Backfill | 63 | Tons | ![]() | $58.00 | $3,654.00 | ![]() | $53.00 | $3,339.00 | ![]() | $40.00 | $2,520.00 | ![]() |
8 | Pavement Striping | 156 | L.F. | ![]() | $15.00 | $2,340.00 | ![]() | $7.15 | $1,115.40 | ![]() | $28.00 | $4,368.00 | ![]() |
9 | Signs, ADA Parking | 2 | Each | ![]() | $750.00 | $1,500.00 | ![]() | $550.00 | $1,100.00 | ![]() | $1,200.00 | $2,400.00 | ![]() |
10 | Clearing and Grubbing | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $13,000.00 | $13,000.00 | ![]() | $10,000.00 | $10,000.00 | ![]() |
11 | Traffic Control | 1 | L.S. | ![]() | $3,000.00 | $3,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() | $1,000.00 | $1,000.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$143,711.00 | ![]() | $149,489.40 | ![]() | $171,858.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
7/27/2024