IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ledges State Park and BWRS | Date: 3/19/2026 | Project No. |
| Road Maintenance | County: | BOONE | Time: 11:00 a.m. | 23-02-08-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,578,000.00 | Contractor: | InRoads LLC | Manatts, Inc | Grimes Asphalt and Paving Corporation | |||||||||
| Funding Source: 92% Park & Institutional Road Fund, 8% Infrastructure, | 4761 NE 20th Lane | 2120 E 13th Street | 5550 NE 22nd St | ||||||||||
| Des Moines IA 50313 | Ames IA 50010 | Des Moines IA 50313 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 515-348-8148 | 515-233-2005 | 515-262-8096 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Binder Bitumen, MC-3000 | 10534 | GAL. | $14.82 | $156,113.88 | $8.00 | $84,272.00 | $7.75 | $81,638.50 | ||||
| 2 | Aggregate, Roadway Cover, 3/8" | 460 | Tons | $58.71 | $27,006.60 | $242.00 | $111,320.00 | $92.25 | $42,435.00 | ||||
| 3 | Preparation of Surface - Microsurfacing | 3.23 | MI. | $11,820.21 | $38,179.278 | $1,831.50 | $5,915.745 | $14,775.00 | $47,723.25 | ||||
| 4 | Emulsified Asphalt - Microsurfacing | 11704 | GAL. | $8.78 | $102,761.12 | $6.50 | $76,076.00 | $11.00 | $128,744.00 | ||||
| 5 | Aggregate - Microsurfacing, L-2 | 313 | Tons | $409.16 | $128,067.08 | $566.50 | $177,314.50 | $511.50 | $160,099.50 | ||||
| 6 | Clean and Fill Crack (HMA Surfaces) | 4.64 | MI. | $12,000.00 | $55,680.00 | $13,200.00 | $61,248.00 | $15,000.00 | $69,600.00 | ||||
| 7 | Sealer Material (HMA Surfaces) | 4640 | LB. | $1.20 | $5,568.00 | $1.35 | $6,264.00 | $1.50 | $6,960.00 | ||||
| 8 | Patch, Full-Depth Finish, 6-inch, by Area, HMA | 301.7 | S.Y. | $62.00 | $18,705.40 | $102.85 | $31,029.845 | $101.00 | $30,471.70 | ||||
| 9 | Patch, Full-Depth Finish, by Area (Greater than 50 ft in length) | 295.2 | S.Y. | $62.00 | $18,302.40 | $103.15 | $30,449.88 | $106.25 | $31,365.00 | ||||
| 10 | Patch, Full-Depth Finish, 6-inch, by Count, HMA | 31 | Each | $400.00 | $12,400.00 | $93.50 | $2,898.50 | $125.00 | $3,875.00 | ||||
| 11 | Patch, Full-Depth Repair, by Area, HMA | 104.2 | S.Y. | $74.00 | $7,710.80 | $187.50 | $19,537.50 | $142.00 | $14,796.40 | ||||
| 12 | Patch, Full-Depth Repair, by Area (Greater than 50 ft in length) | 95.6 | S.Y. | $67.00 | $6,405.20 | $206.30 | $19,722.28 | $163.00 | $15,582.80 | ||||
| 13 | Patch By Count (Repair) HMA | 8 | Each | $515.00 | $4,120.00 | $135.75 | $1,086.00 | $125.00 | $1,000.00 | ||||
| 14 | Subbase (Patch) | 784.6 | S.Y. | $27.00 | $21,184.20 | $31.50 | $24,714.90 | $61.50 | $48,252.90 | ||||
| 15 | Pavement Scarification | 24347.9 | S.Y. | $4.15 | $101,043.785 | $6.05 | $147,304.795 | $8.00 | $194,783.20 | ||||
| 16 | Hot Mix Asphalt, Thin Lift Surface, 3/8 In. Mix | 1446 | Tons | $99.00 | $143,154.00 | $94.25 | $136,285.50 | $98.00 | $141,708.00 | ||||
| 17 | Hot Mix Asphalt, Standard Traffic, Intermediate Course, 1/2" | 2851 | Tons | $89.00 | $253,739.00 | $83.75 | $238,771.25 | $94.00 | $267,994.00 | ||||
| 18 | Asphalt Binder, PG 64-34E+ | 114 | Tons | $791.00 | $90,174.00 | $840.00 | $95,760.00 | $900.00 | $102,600.00 | ||||
| 19 | Asphalt Binder, PG 58-28S | 146 | Tons | $596.00 | $87,016.00 | $530.00 | $77,380.00 | $662.00 | $96,652.00 | ||||
| 20 | Blade and Shape Shoulder Material | 2 | STA. | $450.00 | $900.00 | $908.50 | $1,817.00 | $1,650.00 | $3,300.00 | ||||
| 21 | Reconstruction of Roadbed, Blade and Shape | 1.14 | STA. | $100.00 | $114.00 | $3,750.00 | $4,275.00 | $3,750.00 | $4,275.00 | ||||
| 22 | Granular Surface On Road, 1 1/2" | 28 | Tons | $40.00 | $1,120.00 | $93.75 | $2,625.00 | $81.25 | $2,275.00 | ||||
| 23 | Granular Shoulder, Type A | 42 | Tons | $76.72 | $3,222.24 | $100.35 | $4,214.70 | $128.00 | $5,376.00 | ||||
| 24 | Granular Shoulder, Type B | 1106 | Tons | $40.35 | $44,627.10 | $52.00 | $57,512.00 | $69.00 | $76,314.00 | ||||
| 25 | Revetment, Class E | 42 | Tons | $66.50 | $2,793.00 | $151.25 | $6,352.50 | $132.50 | $5,565.00 | ||||
| 26 | Storm Sewer Pipe, PVC SDR35, 8" | 100 | L.F. | $30.00 | $3,000.00 | $59.00 | $5,900.00 | $67.00 | $6,700.00 | ||||
| 27 | Culvert, Concrete Roadway Pipe, 12" | 40 | L.F. | $140.00 | $5,600.00 | $116.25 | $4,650.00 | $132.00 | $5,280.00 | ||||
| 28 | Culvert, Concrete Roadway Pipe, 18" | 60 | L.F. | $150.00 | $9,000.00 | $127.50 | $7,650.00 | $145.00 | $8,700.00 | ||||
| 29 | Hickenbottom Intake With Standard Bar Guard, 8" | 1 | Each | $350.00 | $350.00 | $715.00 | $715.00 | $813.00 | $813.00 | ||||
| 30 | Apron, Concrete, 12" | 2 | Each | $1,800.00 | $3,600.00 | $2,425.00 | $4,850.00 | $2,750.00 | $5,500.00 | ||||
| 31 | Apron, Concrete, 18" | 2 | Each | $2,200.00 | $4,400.00 | $2,730.00 | $5,460.00 | $3,100.00 | $6,200.00 | ||||
| 32 | Painted Pavement Marking, High-Build Waterborne | 180 | STA. | $172.00 | $30,960.00 | $204.00 | $36,720.00 | $232.00 | $41,760.00 | ||||
| 33 | Reshaping Ditch | 29.46 | STA. | $300.00 | $8,838.00 | $1,182.50 | $34,836.45 | $1,350.00 | $39,771.00 | ||||
| 34 | Swale Ditch Grading | 149 | L.F. | $10.00 | $1,490.00 | $75.00 | $11,175.00 | $75.00 | $11,175.00 | ||||
| 35 | Grid Tied Concrete Block Mat | 8250 | S.F. | $5.75 | $47,437.50 | $11.15 | $91,987.50 | $12.50 | $103,125.00 | ||||
| 36 | Clean Out Pipe Culvert | 144 | L.F. | $25.00 | $3,600.00 | $22.00 | $3,168.00 | $25.00 | $3,600.00 | ||||
| 37 | Remove Culvert Less Than or Equal To 36" | 150 | L.F. | $12.00 | $1,800.00 | $33.00 | $4,950.00 | $37.50 | $5,625.00 | ||||
| 38 | Removal of Pavement | 877.6 | S.Y. | $15.00 | $13,164.00 | $11.00 | $9,653.60 | $26.50 | $23,256.40 | ||||
| 39 | Excavation, Class 13, Widen | 243.5 | C.Y. | $62.00 | $15,097.00 | $64.50 | $15,705.75 | $30.00 | $7,305.00 | ||||
| 40 | Base Widening, 6" HMA | 673 | S.Y. | $42.00 | $28,266.00 | $57.25 | $38,529.25 | $56.25 | $37,856.25 | ||||
| 41 | Modified Subbase | 1249.4 | C.Y. | $103.77 | $129,650.238 | $99.15 | $123,878.01 | $116.50 | $145,555.10 | ||||
| 42 | Shoulder Construction, Earth | 1.65 | STA. | $650.00 | $1,072.50 | $1,187.50 | $1,959.375 | $1,200.00 | $1,980.00 | ||||
| 43 | Macadam Stone Base | 196 | Tons | $48.50 | $9,506.00 | $137.50 | $26,950.00 | $144.00 | $28,224.00 | ||||
| 44 | Granular Surface on Road, Class A Crushed Stone | 14 | Tons | $40.00 | $560.00 | $141.00 | $1,974.00 | $140.00 | $1,960.00 | ||||
| 45 | Subgrade Stabilization Material, Woven Geotextile | 763.2 | S.Y. | $3.00 | $2,289.60 | $3.75 | $2,862.00 | $3.75 | $2,862.00 | ||||
| 46 | Seedbed Preparation | 0.3 | Acres | $3,700.00 | $1,110.00 | $3,300.00 | $990.00 | $2,500.00 | $750.00 | ||||
| 47 | Perimeter and Slope Sediment Control Device, 9" | 692 | L.F. | $3.00 | $2,076.00 | $4.50 | $3,114.00 | $3.75 | $2,595.00 | ||||
| 48 | Granular Surfacing Hauled and Placed, Class A Crushed Stone | 602 | Tons | $40.00 | $24,080.00 | $71.50 | $43,043.00 | $68.75 | $41,387.50 | ||||
| 49 | Clearing and Grubbing | 3 | Units | $250.00 | $750.00 | $937.50 | $2,812.50 | $938.00 | $2,814.00 | ||||
| 50 | Seed and Fertilize (Urban) | 0.9 | Acres | $3,100.00 | $2,790.00 | $7,255.00 | $6,529.50 | $12,500.00 | $11,250.00 | ||||
| 51 | Excavation, Class 10, Roadway and Borrow | 43 | C.Y. | $38.00 | $1,634.00 | $62.50 | $2,687.50 | $62.50 | $2,687.50 | ||||
| 52 | Embankment-In-Place | 368 | C.Y. | $18.00 | $6,624.00 | $75.00 | $27,600.00 | $81.25 | $29,900.00 | ||||
| 53 | Signs | 18 | Each | $295.00 | $5,310.00 | $302.50 | $5,445.00 | $368.75 | $6,637.50 | ||||
| 54 | Construction Survey | 1 | L.S. | $18,000.00 | $18,000.00 | $20,000.00 | $20,000.00 | $4,750.00 | $4,750.00 | ||||
| 55 | Traffic Control | 1 | L.S. | $14,850.00 | $14,850.00 | $11,500.00 | $11,500.00 | $25,000.00 | $25,000.00 | ||||
| 56 | Mobilization | 1 | L.S. | $90,000.00 | $90,000.00 | $165,000.00 | $165,000.00 | $105,650.00 | $105,650.00 | ||||
| $1,817,011.921 | $2,146,442.33 | $2,304,055.50 | |||||||||||
4/1/2026