IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Rathbun WMA | Date: 8/18/2022 | Project No. |
Road Maintenance | County: | APPANOOSE | Time: 11:00 a.m. | 22-05-04-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $130,000.00 | Contractor: | IA Builders LLC | Nagel Construction | Miller Trucking & Excavating Co | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 219 N 10th St | 2601 140th St | 3303 John Deere Rd | ||||||||||
Albia IA 52531 | Allerton IA 50008 | Silvis IL 61282 | |||||||||||
Plan Sets Requested: 0 | Quantities | 641-780-8694 | 641-203-2756 | 309-755-7644 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2101 - CLEARING | 3.7 | Acres | $2,200.00 | $8,140.00 | $1,700.00 | $6,290.00 | $7,500.00 | $27,750.00 | ||||
2 | 2125 - DITCH CLEANING/RESHAPING | 29.5 | STA. | $315.00 | $9,292.50 | $235.00 | $6,932.50 | $450.00 | $13,275.00 | ||||
3 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 57.6 | STA. | $270.00 | $15,552.00 | $325.00 | $18,720.00 | $165.00 | $9,504.00 | ||||
4 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1216 | Tons | $24.00 | $29,184.00 | $26.20 | $31,859.20 | $35.50 | $43,168.00 | ||||
5 | 2312 - GRANULAR SURFACING ON ROAD, CRUSHED STONE - 2-INCH | 125 | Tons | $25.00 | $3,125.00 | $27.25 | $3,406.25 | $33.50 | $4,187.50 | ||||
6 | 2416 - APRON, CONC, 18" | 4 | Each | $1,003.00 | $4,012.00 | $1,000.00 | $4,000.00 | $2,450.00 | $9,800.00 | ||||
7 | 2416 - CULV, CONC RDWY PIPE, 18" | 32 | L.F. | $76.00 | $2,432.00 | $148.25 | $4,744.00 | $195.00 | $6,240.00 | ||||
8 | 2507 - ENGINEERING FABRIC | 250 | S.Y. | $1.80 | $450.00 | $3.00 | $750.00 | $3.00 | $750.00 | ||||
9 | 2507 - REVETMENT, CLASS E | 80 | Tons | $33.95 | $2,716.00 | $42.45 | $3,396.00 | $65.00 | $5,200.00 | ||||
10 | 2507 - EROSION STONE | 64 | Tons | $33.95 | $2,172.80 | $38.50 | $2,464.00 | $50.00 | $3,200.00 | ||||
11 | 2518 - SAFETY CLOSURE | 4 | Each | $375.00 | $1,500.00 | $250.00 | $1,000.00 | $285.00 | $1,140.00 | ||||
12 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $1,500.00 | $1,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | ||||
13 | 2533 - MOBILIZATION | 1 | L.S. | $3,250.00 | $3,250.00 | $6,500.00 | $6,500.00 | $20,000.00 | $20,000.00 | ||||
14 | 2601 - SEED+FERTILIZE (RURAL) | 1 | Acres | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | $5,000.00 | $5,000.00 | ||||
$85,826.30 | $98,061.95 | $155,714.50 | |||||||||||
1/2/2025