IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Odessa Wildlife Unit | Date: 2/17/2022 | Project No. |
| Flood Damage Repairs REBID | County: | LOUISA | Time: 11:00 a.m. | 21-06-58-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | Triple B Construction | Miller Trucking & Excavating | ||||||||||
| Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | 710 Aryes Progress Drive | 3303 John Deere Road | |||||||||||
| Wilton IA 52778 | Silvis IL 61282 | ||||||||||||
| Plan Sets Requested: 3 | Quantities | 563-732-3478 | 309-755-7644 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Earthwork, Fill Hauled and Placed, Clean Sand (Site 1) | 297 | C.Y. | $30.00 | $8,910.00 | $27.00 | $8,019.00 | $0.00 | |||||
| 2 | Erosion Control Mat, RECP Type 2.A (Site 1) | 112 | S.Y. | $2.00 | $224.00 | $15.00 | $1,680.00 | $0.00 | |||||
| 3 | Seeding and Fertilizing (Site 1) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 4 | Earthwork, Fill Hauled and Placed, Clay (Site 2) | 3260 | C.Y. | $22.00 | $71,720.00 | $27.00 | $88,020.00 | $0.00 | |||||
| 5 | Erosion Control Mat, RECP Type 2.C (Site 2) | 4889 | S.Y. | $2.00 | $9,778.00 | $3.50 | $17,111.50 | $0.00 | |||||
| 6 | Seeding and Fertilizing(Site 2) | 1.5 | Acres | $4,500.00 | $6,750.00 | $1,500.00 | $2,250.00 | $0.00 | |||||
| 7 | Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 3) | 5 | C.Y. | $100.00 | $500.00 | $200.00 | $1,000.00 | $0.00 | |||||
| 8 | Erosion Control Mat, RECP Type 2.C (Site 3) | 14 | S.Y. | $2.00 | $28.00 | $25.00 | $350.00 | $0.00 | |||||
| 9 | Seeding and Fertilizing (Site 3) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 10 | Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 4) | 3 | C.Y. | $100.00 | $300.00 | $200.00 | $600.00 | $0.00 | |||||
| 11 | Erosion Control Mat, RECP Type 2.C (Site 4) | 9 | S.Y. | $2.00 | $18.00 | $25.00 | $225.00 | $0.00 | |||||
| 12 | Seeding and Fertilizing (Site 4) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 13 | Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 5) | 3 | C.Y. | $100.00 | $300.00 | $200.00 | $600.00 | $0.00 | |||||
| 14 | Erosion Control Mat, RECP Type 2.C (Site 5) | 9 | S.Y. | $2.00 | $18.00 | $25.00 | $225.00 | $0.00 | |||||
| 15 | Seeding and Fertilizing (Site 5) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 16 | Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 6) | 1 | C.Y. | $500.00 | $500.00 | $200.00 | $200.00 | $0.00 | |||||
| 17 | Erosion Control Mat, RECP Type 2.C (Site 6) | 3 | S.Y. | $2.00 | $6.00 | $25.00 | $75.00 | $0.00 | |||||
| 18 | Seeding and Fertilizing (Site 6) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 19 | Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 7) | 17 | C.Y. | $100.00 | $1,700.00 | $100.00 | $1,700.00 | $0.00 | |||||
| 20 | Erosion Control Mat, RECP Type 2.C (Site 7) | 51 | S.Y. | $2.00 | $102.00 | $25.00 | $1,275.00 | $0.00 | |||||
| 21 | Seeding and Fertilizing (Site 7) | 0.1 | Acres | $4,500.00 | $450.00 | $25,000.00 | $2,500.00 | $0.00 | |||||
| 22 | Seeding and Fertilizing (Construction Road) | 3.1 | Acres | $3,300.00 | $10,230.00 | $1,500.00 | $4,650.00 | $0.00 | |||||
| 23 | Mobilization | 1 | L.S. | $40,000.00 | $40,000.00 | $25,000.00 | $25,000.00 | $0.00 | |||||
| $153,784.00 | $167,980.50 | $0.00 | |||||||||||