 Bids For:  Location:   Twin Lakes  Date: 3/9/2023  Project No.  
  Boat Ramp Replacement  County:   CALHOUN  Time: 3:00 p.m.  22-01-13-01

 

 
1
2
3
Estimated Cost: $38,000.00
Contractor: 
Richards Construction Co IncJensen Builders Ltd
Funding Source: 100% Marine Fuel Tax, 2721 Sierra Ave
1175 South 32nd St

Sac City IA  50583Fort Dodge IA  50501  
Plan Sets Requested: 0
Quantities
712-662-4421515-573-3292
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,000.00$2,000.00 $3,000.00$3,000.00 $0.00 
2Pavement Removal134S.Y.$30.00$4,020.00 $50.00$6,700.00 $0.00 
3Macadam Stone69Tons$75.00$5,175.00 $110.00$7,590.00 $0.00 
4Crushed Stone, Class A, Base, 6" Depth29.4Tons$80.00$2,352.00 $100.00$2,940.00 $0.00 
5Crushed Stone, Class A, Temporary Ramp87Tons$40.00$3,480.00 $100.00$8,700.00 $0.00 
6Field Stone, Class E, Revetment42Tons$65.00$2,730.00 $210.00$8,820.00 $0.00 
7P.C.C., Reinforced, Class C, 6" Depth93.3S.Y.$205.00$19,126.50 $200.00$18,660.00 $0.00 
8P.C.C., Class C, Sidewalk, 6" Depth17.5S.Y.$200.00$3,500.00 $320.00$5,600.00 $0.00 
9Site Restoration1L.S.$1,500.00$1,500.00 $3,000.00$3,000.00 $0.00 
      $43,883.50  $65,010.00  $0.00 
 



 

12/22/2024