IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Clear Lake Wildlife Unit | Date: 2/19/2026 | Project No. |
| Myre Slough Water Control Structure Replacement | County: | WINNEBAGO | Time: 11:00 a.m. | 23-02-95-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $190,000.00 | Contractor: | Adam Laubenthal DBA Laubenthal Excavation | Ludovissy Enterprises | Larson Contracting Central, LLC | |||||||||
| Funding Source: 50% Lake Restoration, 50% Federal-NAWCA, | 1245 180th St | 702 S 2nd St | 508 W Main St | ||||||||||
| Bradgate IA 50520 | Guttenberg IA 52052 | Lake Mills IA 50450 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 515-368-1112 | 563-880-4866 | 641-592-5800 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,000.00 | $9,000.00 | $25,000.00 | $25,000.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $2,000.00 | $2,000.00 | $10,000.00 | $10,000.00 | $2,676.00 | $2,676.00 | ||||
| 3 | Runoff Diversion and Dewatering | 1 | L.S. | $7,000.00 | $7,000.00 | $10,000.00 | $10,000.00 | $6,567.00 | $6,567.00 | ||||
| 4 | Structure Removal | 1 | L.S. | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | $5,580.00 | $5,580.00 | ||||
| 5 | Water Control Structure | 1 | L.S. | $79,270.00 | $79,270.00 | $78,000.00 | $78,000.00 | $113,499.00 | $113,499.00 | ||||
| 6 | Sheet Piling | 61 | L.F. | $265.65 | $16,204.65 | $983.00 | $59,963.00 | $1,062.41 | $64,807.01 | ||||
| 7 | Road Stone, Class A | 60 | Tons | $45.00 | $2,700.00 | $60.00 | $3,600.00 | $35.00 | $2,100.00 | ||||
| 8 | Revetment, Class E | 78 | Tons | $60.00 | $4,680.00 | $60.00 | $4,680.00 | $46.24 | $3,606.72 | ||||
| 9 | Stoplogs | 12 | Each | $541.66 | $6,499.92 | $800.00 | $9,600.00 | $456.92 | $5,483.04 | ||||
| 10 | Storage Box | 1 | Each | $4,000.00 | $4,000.00 | $5,000.00 | $5,000.00 | $3,345.00 | $3,345.00 | ||||
| 11 | Site Restoration | 1 | L.S. | $3,500.00 | $3,500.00 | $5,000.00 | $5,000.00 | $6,404.00 | $6,404.00 | ||||
| $137,354.57 | $215,843.00 | $219,067.77 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $190,000.00 | Contractor: | Gus Const Co, Inc | Landwehr Construction, Inc | Nagel Construction LLC | |||||||||
| Funding Source: 50% Lake Restoration, 50% Federal-NAWCA, | 606 McPherson St PO Box 77 | 851 60th St S | 2601 140th St | ||||||||||
| Casey IA 50048 | St Cloud MN 56301 | Allerton IA 50008 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 641-746-2229 | 320-252-1494 | 641-203-2756 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $20,000.00 | $20,000.00 | $44,000.00 | $44,000.00 | $25,000.00 | $25,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | ||||
| 3 | Runoff Diversion and Dewatering | 1 | L.S. | $5,500.00 | $5,500.00 | $4,500.00 | $4,500.00 | $9,000.00 | $9,000.00 | ||||
| 4 | Structure Removal | 1 | L.S. | $7,500.00 | $7,500.00 | $10,000.00 | $10,000.00 | $10,000.00 | $10,000.00 | ||||
| 5 | Water Control Structure | 1 | L.S. | $146,000.00 | $146,000.00 | $135,000.00 | $135,000.00 | $158,505.00 | $158,505.00 | ||||
| 6 | Sheet Piling | 61 | L.F. | $410.00 | $25,010.00 | $475.00 | $28,975.00 | $375.00 | $22,875.00 | ||||
| 7 | Road Stone, Class A | 60 | Tons | $38.00 | $2,280.00 | $36.00 | $2,160.00 | $50.00 | $3,000.00 | ||||
| 8 | Revetment, Class E | 78 | Tons | $54.00 | $4,212.00 | $78.00 | $6,084.00 | $90.00 | $7,020.00 | ||||
| 9 | Stoplogs | 12 | Each | $651.08 | $7,812.96 | $418.00 | $5,016.00 | $300.00 | $3,600.00 | ||||
| 10 | Storage Box | 1 | Each | $2,874.00 | $2,874.00 | $3,250.00 | $3,250.00 | $3,000.00 | $3,000.00 | ||||
| 11 | Site Restoration | 1 | L.S. | $7,500.00 | $7,500.00 | $3,500.00 | $3,500.00 | $5,000.00 | $5,000.00 | ||||
| $230,688.96 | $243,485.00 | $250,000.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $190,000.00 | Contractor: | Kingland Construction Services | Henkel Construction Company | ||||||||||
| Funding Source: 50% Lake Restoration, 50% Federal-NAWCA, | 3216 Hwy 69 | 208 East State Street | |||||||||||
| Forest City IA 50436 | Mason City IA 50401 | ||||||||||||
| Plan Sets Requested: 8 | Quantities | 641-585-0101 | 641-423-5674 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $25,449.78 | $25,449.78 | $59,422.00 | $59,422.00 | $0.00 | |||||
| 2 | Traffic Control | 1 | L.S. | $2,429.57 | $2,429.57 | $3,062.00 | $3,062.00 | $0.00 | |||||
| 3 | Runoff Diversion and Dewatering | 1 | L.S. | $10,325.39 | $10,325.39 | $15,575.00 | $15,575.00 | $0.00 | |||||
| 4 | Structure Removal | 1 | L.S. | $9,110.90 | $9,110.90 | $10,977.00 | $10,977.00 | $0.00 | |||||
| 5 | Water Control Structure | 1 | L.S. | $150,129.21 | $150,129.21 | $190,696.00 | $190,696.00 | $0.00 | |||||
| 6 | Sheet Piling | 61 | L.F. | $990.05 | $60,393.05 | $257.00 | $15,677.00 | $0.00 | |||||
| 7 | Road Stone, Class A | 60 | Tons | $364.44 | $21,866.40 | $68.15 | $4,089.00 | $0.00 | |||||
| 8 | Revetment, Class E | 78 | Tons | $78.96 | $6,158.88 | $92.80 | $7,238.40 | $0.00 | |||||
| 9 | Stoplogs | 12 | Each | $5,279.67 | $63,356.04 | $5,246.33 | $62,955.96 | $0.00 | |||||
| 10 | Storage Box | 1 | Each | $6,073.93 | $6,073.93 | $11,787.00 | $11,787.00 | $0.00 | |||||
| 11 | Site Restoration | 1 | L.S. | $7,227.98 | $7,227.98 | $7,152.00 | $7,152.00 | $0.00 | |||||
| $362,521.13 | $388,631.36 | $0.00 | |||||||||||
4/7/2026