IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Rock Creek State Park | Date: 10/20/2022 | Project No. |
Sanitary Sewer Liner | County: | JASPER | Time: 11:00 a.m. | 21-05-50-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $230,000.00 | Contractor: | Municipal Pipe Tool Co LLC | Insituform Technologies USA LLC | Visu-Sewer, Inc | |||||||||
Funding Source: 100% Infrastructure, | 515 5th St | 580 Goddard Ave | W230 N4855 Betker Dr | ||||||||||
Hudson IA 50643 | Chesterfield MO 63005 | Pewaukee WI 53072 | |||||||||||
Plan Sets Requested: 1 | Quantities | 319-988-4205 | 636-530-8000 | 262-695-2340 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $35,473.00 | $35,473.00 | $18,500.00 | $18,500.00 | $49,650.00 | $49,650.00 | ||||
2 | CIPP Sewer lining | 2549 | L.F. | $38.00 | $96,862.00 | $49.20 | $125,410.80 | $49.00 | $124,901.00 | ||||
3 | Point Repairs | 10 | Each | $3,323.00 | $33,230.00 | $8,050.00 | $80,500.00 | $15,750.00 | $157,500.00 | ||||
4 | Replace pipe with 6 inch PVC SDR 35 | 38 | L.F. | $158.00 | $6,004.00 | $240.00 | $9,120.00 | $475.00 | $18,050.00 | ||||
5 | Site Restoration & Seeding | 1 | L.S. | $8,925.00 | $8,925.00 | $2,800.00 | $2,800.00 | $18,100.00 | $18,100.00 | ||||
$180,494.00 | $236,330.80 | $368,201.00 | |||||||||||
12/22/2024