IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Pleasant Creek State Recreation Area | Date: 10/21/2021 | Project No. |
South Well Repair | County: | LINN | Time: 3:00 p.m. | 22-06-57-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $15,000.00 | Contractor: | The Northway Corporation | |||||||||||
Funding Source: 100% REAP-Parks Maintenance and Operations , | 4895 8th Ave | ||||||||||||
Marion IA 52302 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 3193776339 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | South Well Repair | 1 | L.S. | $18,300.00 | $18,300.00 | $0.00 | $0.00 | ||||||
2 | South Well Pump Installation | 1 | L.S. | $4,875.00 | $4,875.00 | $0.00 | $0.00 | ||||||
3 | Mobilization | 1 | L.S. | $300.00 | $300.00 | $0.00 | $0.00 | ||||||
4 | Site Restoration | 1 | L.S. | $1,200.00 | $1,200.00 | $0.00 | $0.00 | ||||||
$24,675.00 | $0.00 | $0.00 | |||||||||||
9/27/2024