IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Red Rock Wildlife Unit | Date: 4/21/2022 | Project No. |
West Dunreath Access Road | County: | MARION | Time: 3:00 p.m. | 22-05-63-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $37,000.00 | Contractor: | Sterk Excavating Inc | Krichau Land Improvement, LLC | IA Builders | |||||||||
Funding Source: 100% REAP Land Management, | 1087 200th St | 11936 245th Ave | 219 | ||||||||||
Pella IA 50219 | Pleasantville IA 50225 | Albia IA 52531 | |||||||||||
Plan Sets Requested: 0 | Quantities | 6414160110 | 5159792511 | 6417808694 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2125 - Reshaping/Cleaning Ditches | 12 | STA. | $360.00 | $4,320.00 | $583.33 | $6,999.96 | $400.00 | $4,800.00 | ||||
2 | 2127 - Reconstruction of Roadbed, Blading/Shaping | 12 | STA. | $200.00 | $2,400.00 | $666.66 | $7,999.92 | $430.00 | $5,160.00 | ||||
3 | 2312 - Macadam Stone | 364 | Tons | $33.82 | $12,310.48 | $32.25 | $11,739.00 | $28.00 | $10,192.00 | ||||
4 | 2417 - Culvert, CMP Rdwy, 18" | 40 | L.F. | $70.00 | $2,800.00 | $38.75 | $1,550.00 | $75.00 | $3,000.00 | ||||
5 | 2507 - Erosion Stone | 35 | Tons | $54.70 | $1,914.50 | $32.50 | $1,137.50 | $30.00 | $1,050.00 | ||||
6 | 2533 - Mobilization | 1 | L.S. | $3,250.00 | $3,250.00 | $3,000.00 | $3,000.00 | $8,250.00 | $8,250.00 | ||||
$26,994.98 | $32,426.38 | $32,452.00 | |||||||||||
Alternate | |||||||||||||
7 | Excavation - Widen Corner | 1 | L.S. | $5,200.00 | $5,200.00 | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | ||||
$32,194.98 | $34,926.38 | $37,452.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $37,000.00 | Contractor: | Leffler Dirtworks LLC | Boyle Built Enterprises, LLC | RW Excavating Solutions, LLC | |||||||||
Funding Source: 100% REAP Land Management, | 2272 320th St | 33837 142nd St | 13293 S 88th Ave W | ||||||||||
Oskaloosa IA 52577 | Selma IA 52588 | Prairie City IA 50228 | |||||||||||
Plan Sets Requested: 0 | Quantities | 6412262231 | 6417773133 | 5159942648 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2125 - Reshaping/Cleaning Ditches | 12 | STA. | $300.00 | $3,600.00 | $708.33 | $8,499.96 | $2,000.00 | $24,000.00 | ||||
2 | 2127 - Reconstruction of Roadbed, Blading/Shaping | 12 | STA. | $300.00 | $3,600.00 | $583.50 | $7,002.00 | $1,000.00 | $12,000.00 | ||||
3 | 2312 - Macadam Stone | 364 | Tons | $35.85 | $13,049.40 | $45.00 | $16,380.00 | $52.00 | $18,928.00 | ||||
4 | 2417 - Culvert, CMP Rdwy, 18" | 40 | L.F. | $95.00 | $3,800.00 | $75.00 | $3,000.00 | $60.00 | $2,400.00 | ||||
5 | 2507 - Erosion Stone | 35 | Tons | $75.00 | $2,625.00 | $102.86 | $3,600.10 | $52.00 | $1,820.00 | ||||
6 | 2533 - Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | ||||
Alternate | |||||||||||||
7 | Excavation - Widen Corner | 1 | L.S. | $4,800.00 | $4,800.00 | $500.00 | $500.00 | $5,000.00 | $5,000.00 | ||||
$41,474.40 | $43,982.06 | $69,148.00 | |||||||||||
1/16/2025