IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Ahquabi State Park and Hooper Lake  Date: 2/17/2022  Project No.  
  Boat Docks  County:   WARREN  Time: 3:00 p.m.  22-05-91-06

 

 
1
2
3
Estimated Cost: $95,000.00
Contractor: 
Haworth Land ConstructionTWR Dock and MarineMcGee Concrete, LLC
Funding Source: 100% Marine Fuel Tax, 12981 Quaker Street
610 Warner Street
PO Box 211
219 N Fryer St.
Indianola IA  50125Lamont IA  50650Russell IA  50238
Plan Sets Requested: 0
Quantities
5152494747563-924-2222641-203-0721
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,000.00$3,000.00 $12,000.00$12,000.00 $6,200.00$6,200.00 
2Hooper Core-Out15C.Y.$37.00$555.00 $175.00$2,625.00 $41.67$625.05 
3Hooper Concrete Work87.1S.Y.$76.522$6,665.066 $135.00$11,758.50 $65.50$5,705.05 
4Hooper Wedge Dock1L.S.$12,650.00$12,650.00 $12,300.00$12,300.00 $38,500.00$38,500.00 
5Ahquabi Campground Core-Out12C.Y.$37.00$444.00 $175.00$2,100.00 $129.17$1,550.04 
6Ahquabi Campground Concrete Work68.5S.Y.$78.949$5,408.007 $42.00$2,877.00 $67.45$4,620.325 
7Ahquabi Campground Wedge Dock1L.S.$12,650.00$12,650.00 $12,300.00$12,300.00 $38,500.00$38,500.00 
8Ahquabi Main Ramp Core-Out12C.Y.$100.00$1,200.00 $175.00$2,100.00 $95.84$1,150.08 
9Ahquabi Main Ramp Concrete43.2C.Y.$226.852$9,800.006 $509.26$22,000.032 $451.39$19,500.048 
10Ahquabi Main Ramp Wood, Bumpers, and Hardware1L.S.$2,000.00$2,000.00 $2,400.00$2,400.00 $1,650.00$1,650.00 
11Class E Riprap, If Needed16Tons$55.00$880.00 $72.00$1,152.00 $71.25$1,140.00 
12Fish Cleaning Table1Each$1,500.00$1,500.00 $550.00$550.00 $850.00$850.00 
      $56,752.079  $84,162.532  $119,990.593 
Alternate        
13Ahquabi Campground Second Dock Core-Out12C.Y.$37.00$444.00 $175.00$2,100.00 $129.17$1,550.04 
Alternate        
14Ahquabi Campground Second Dock Concrete68.5S.Y.$78.949$5,408.007 $135.00$9,247.50 $67.45$4,620.325 
Alternate        
15Ahquabi Campground Second Wedge Dock1L.S.$12,650.00$12,650.00 $12,300.00$12,300.00 $38,500.00$38,500.00 
      $75,254.086  $107,810.032  $164,660.958 
 



 