IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Wapsipinicon State Park | Date: 12/18/2025 | Project No. |
| Pavement Maintenance | County: | JONES | Time: 11:00 a.m. | 22-06-53-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $886,000.00 | Contractor: | River City Paving | L.L. Pelling Company Inc. | ||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | PO Box 1430 | 1425 W Penn St | |||||||||||
| Dubuque IA 52004 | North Liberty IA 52317 | ||||||||||||
| Plan Sets Requested: 4 | Quantities | 608-568-3433 | 319-626-4600 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Binder Bitumen, MC-3000 | 18809 | GAL. | $7.28 | $136,929.52 | $4.75 | $89,342.75 | $0.00 | |||||
| 2 | Aggregate, Roadway Cover, 3/8" | 807 | Tons | $72.69 | $58,660.83 | $77.85 | $62,824.95 | $0.00 | |||||
| 3 | Asphalt Emulsion - Fog Seal (HMA Pavement) | 1454 | GAL. | $21.52 | $31,290.08 | $6.45 | $9,378.30 | $0.00 | |||||
| 4 | Patches, Full-Depth Finish, 6-inch, by Area, HMA | 53.3 | S.Y. | $73.50 | $3,917.55 | $91.25 | $4,863.625 | $0.00 | |||||
| 5 | Patches, Full-Depth Finish, by Area (Greater than 50 ft in length) | 50 | S.Y. | $85.50 | $4,275.00 | $91.25 | $4,562.50 | $0.00 | |||||
| 6 | Patches, Full-Depth Finish, 6-inch, by Count, HMA | 4 | Each | $39.00 | $156.00 | $210.00 | $840.00 | $0.00 | |||||
| 7 | Subbase (Patches) | 17.3 | C.Y. | $87.85 | $1,519.805 | $137.90 | $2,385.67 | $0.00 | |||||
| 8 | Pavement Scarification | 13346.3 | S.Y. | $6.80 | $90,754.84 | $7.90 | $105,435.77 | $0.00 | |||||
| 9 | Hot Mix Asphalt, Thin Lift Surface, 3/8 In. Mix | 740 | Tons | $77.15 | $57,091.00 | $96.60 | $71,484.00 | $0.00 | |||||
| 10 | Hot Mix Asphalt Standard Traffic, Intermediate Course, 1/2" | 2947 | Tons | $70.42 | $207,527.74 | $78.00 | $229,866.00 | $0.00 | |||||
| 11 | Asphalt Binder, PG 64-34E+ | 60 | Tons | $585.00 | $35,100.00 | $744.00 | $44,640.00 | $0.00 | |||||
| 12 | Asphalt Binder, PG 58-28S | 148 | Tons | $425.00 | $62,900.00 | $538.00 | $79,624.00 | $0.00 | |||||
| 13 | Slurry Level | 0.3 | MI. | $13,680.75 | $4,104.225 | $50,000.00 | $15,000.00 | $0.00 | |||||
| 14 | Surface Preparation-Slurry | 0.3 | MI. | $17,589.59 | $5,276.877 | $35,000.00 | $10,500.00 | $0.00 | |||||
| 15 | Asphalt Emulsion-Slurry Level, Wedge, Treatment | 9 | GAL. | $260.59 | $2,345.31 | $5.00 | $45.00 | $0.00 | |||||
| 16 | Granular Surface On Road, 1 1/4" | 350 | Tons | $31.25 | $10,937.50 | $31.25 | $10,937.50 | $0.00 | |||||
| 17 | Granular Shoulder, Type B | 518 | Tons | $27.54 | $14,265.72 | $44.50 | $23,051.00 | $0.00 | |||||
| 18 | Revetment, Class E | 84 | Tons | $37.50 | $3,150.00 | $37.50 | $3,150.00 | $0.00 | |||||
| 19 | Culvert, Concrete Roadway Pipe, 18" | 40 | L.F. | $135.75 | $5,430.00 | $135.75 | $5,430.00 | $0.00 | |||||
| 20 | Apron, Concrete, 18" | 1 | Each | $1,975.00 | $1,975.00 | $1,975.00 | $1,975.00 | $0.00 | |||||
| 21 | Intake, SW-513, 3x3 | 1 | Each | $4,335.00 | $4,335.00 | $4,335.00 | $4,335.00 | $0.00 | |||||
| 22 | Traffic Control | 1 | L.S. | $2,000.00 | $2,000.00 | $4,380.00 | $4,380.00 | $0.00 | |||||
| 23 | Mobilization | 1 | L.S. | $52,968.37 | $52,968.37 | $37,000.00 | $37,000.00 | $0.00 | |||||
| $796,910.367 | $821,051.065 | $0.00 | |||||||||||
2/18/2026