IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Mines of Spain Recreation Area | Date: 8/1/2024 | Project No. |
Pavement Preservation | County: | DUBUQUE | Time: 3:00 p.m. | 22-03-31-01 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $86,000.00 | Contractor: | ![]() | River City Paving, Div of Mathy | Sulam Corp dba Tri State Paving | ![]() | ||||||||
Funding Source: 100% Park & Institutional Road Fund, | ![]() | PO Box 1430 | ![]() | 305 Cedar Cross Rd | ![]() | ![]() | |||||||
![]() | Dubuque IA 52004 | ![]() | Dubuque IA 52003 | ![]() | ![]() | ||||||||
Plan Sets Requested: 0 | Quantities | ![]() | 563-587-9522 | ![]() | 563-583-0854 | ![]() | ![]() | ||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $650.00 | $650.00 | ![]() | $10,000.00 | $10,000.00 | ![]() | $0.00 | ![]() | |
2 | Traffic Control | 1 | L.S. | ![]() | $550.00 | $550.00 | ![]() | $12,500.00 | $12,500.00 | ![]() | $0.00 | ![]() | |
3 | Patches, Full Depth Finish | 590 | S.Y. | ![]() | $10.00 | $5,900.00 | ![]() | $38.95 | $22,980.50 | ![]() | $0.00 | ![]() | |
4 | Patches by Count | 3 | Each | ![]() | $125.00 | $375.00 | ![]() | $1,500.00 | $4,500.00 | ![]() | $0.00 | ![]() | |
5 | Hot Mix Asphalt Mixture, Interlayer Base Course, 3/8in. Mix | 31.7 | Tons | ![]() | $70.00 | $2,219.00 | ![]() | $80.00 | $2,536.00 | ![]() | $0.00 | ![]() | |
6 | Hot Mix Asphalt High Traffic, Intermediate Course, 1/2in. Mix | 47.6 | Tons | ![]() | $65.00 | $3,094.00 | ![]() | $70.00 | $3,332.00 | ![]() | $0.00 | ![]() | |
7 | Hot Mix Asphalt High Traffic, Surface Course, 1/2in. Mix | 47.6 | Tons | ![]() | $65.00 | $3,094.00 | ![]() | $70.00 | $3,332.00 | ![]() | $0.00 | ![]() | |
8 | Asphalt Binder, PG 58-28S | 5.1 | Tons | ![]() | $500.00 | $2,550.00 | ![]() | $600.00 | $3,060.00 | ![]() | $0.00 | ![]() | |
9 | Asphalt Binder, PG 58-28S | 1.6 | Tons | ![]() | $500.00 | $800.00 | ![]() | $600.00 | $960.00 | ![]() | $0.00 | ![]() | |
10 | Subbase (Patch) | 98.2 | C.Y. | ![]() | $12.00 | $1,178.40 | ![]() | $53.54 | $5,257.628 | ![]() | $0.00 | ![]() | |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$20,410.40 | ![]() | $68,458.128 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
3/31/2025