IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Big Creek State Park | Date: 1/20/2022 | Project No. |
| Parking Lot Paving | County: | POLK | Time: 11:00 a.m. | 22-02-77-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,700,000.00 | Contractor: | Concrete Technologies Inc. | Wicks Construction Inc | Berkey Homebuilders dba Concrete Professionals | |||||||||
| Funding Source: 75% Federal-DJ, 25% Marine Fuel Tax, | 1001 SE 37th St | 2201 Hwy 9 | PO Box 7 | ||||||||||
| Grimes IA 50111 | Decorah IA 52101 | Altoona IA 50009 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 5152521650 | 5633822325 | 5159673136 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $154,250.00 | $154,250.00 | $125,000.00 | $125,000.00 | $157,600.00 | $157,600.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $3,215.00 | $3,215.00 | $6,000.00 | $6,000.00 | $4,400.00 | $4,400.00 | ||||
| 3 | Construction Survey | 1 | L.S. | $17,225.00 | $17,225.00 | $19,000.00 | $19,000.00 | $9,350.00 | $9,350.00 | ||||
| 4 | Site Restoration | 1 | L.S. | $58,220.00 | $58,220.00 | $22,500.00 | $22,500.00 | $24,750.00 | $24,750.00 | ||||
| 5 | 15" Dia. RCP | 180 | L.F. | $76.00 | $13,680.00 | $75.00 | $13,500.00 | $95.00 | $17,100.00 | ||||
| 6 | 15" Dia. RCP Apron | 1 | Each | $2,275.00 | $2,275.00 | $2,250.00 | $2,250.00 | $2,475.00 | $2,475.00 | ||||
| 7 | 18" Dia. RCP | 247 | L.F. | $81.00 | $20,007.00 | $80.00 | $19,760.00 | $99.00 | $24,453.00 | ||||
| 8 | 18" Dia. RCP Apron | 7 | Each | $2,430.00 | $17,010.00 | $2,400.00 | $16,800.00 | $2,650.00 | $18,550.00 | ||||
| 9 | 24" Dia. RCP | 81 | L.F. | $96.25 | $7,796.25 | $95.00 | $7,695.00 | $133.00 | $10,773.00 | ||||
| 10 | 24" Dia. RCP Apron | 4 | Each | $2,885.00 | $11,540.00 | $2,850.00 | $11,400.00 | $3,442.00 | $13,768.00 | ||||
| 11 | 5" PCC | 181 | S.Y. | $65.50 | $11,855.50 | $54.00 | $9,774.00 | $124.00 | $22,444.00 | ||||
| 12 | 6" Curb | 2830 | L.F. | $11.60 | $32,828.00 | $1.50 | $4,245.00 | $22.20 | $62,826.00 | ||||
| 13 | 6" PCC | 41418 | S.Y. | $35.00 | $1,449,630.00 | $41.86 | $1,733,757.48 | $39.75 | $1,646,365.50 | ||||
| 14 | Class A Crushed Stone | 45 | Tons | $45.50 | $2,047.50 | $45.00 | $2,025.00 | $38.00 | $1,710.00 | ||||
| 15 | Concrete Pipe Disposal | 1 | L.S. | $8,100.00 | $8,100.00 | $8,000.00 | $8,000.00 | $2,925.00 | $2,925.00 | ||||
| 16 | Curb Cuts | 51 | Each | $80.00 | $4,080.00 | $30.00 | $1,530.00 | $82.50 | $4,207.50 | ||||
| 17 | Demolish Kiosk and Light Pole | 1 | L.S. | $2,880.00 | $2,880.00 | $3,600.00 | $3,600.00 | $3,275.00 | $3,275.00 | ||||
| 18 | Electrical Connection - East Boat Ramp | 1 | L.S. | $445.00 | $445.00 | $12,051.00 | $12,051.00 | $11,000.00 | $11,000.00 | ||||
| 19 | Excavation, Class 10, Waste | 8331 | C.Y. | $12.75 | $106,220.25 | $12.50 | $104,137.50 | $14.65 | $122,049.15 | ||||
| 20 | Light Pole with Base | 3 | Each | $5,955.00 | $17,865.00 | $3,219.00 | $9,657.00 | $4,730.00 | $14,190.00 | ||||
| 21 | Parking Bumper | 4 | Each | $155.00 | $620.00 | $135.00 | $540.00 | $150.00 | $600.00 | ||||
| 22 | Pavement Markings - ADA Parking | 13 | Each | $61.00 | $793.00 | $60.00 | $780.00 | $66.00 | $858.00 | ||||
| 23 | Pavement Removal | 33886 | S.Y. | $1.60 | $54,217.60 | $7.00 | $237,202.00 | $3.85 | $130,461.10 | ||||
| 24 | Pavement Striping | 16659 | L.F. | $0.60 | $9,995.40 | $0.70 | $11,661.30 | $0.77 | $12,827.43 | ||||
| 25 | Raise Stormwater Intakes | 3 | Each | $1,670.00 | $5,010.00 | $1,650.00 | $4,950.00 | $2,225.00 | $6,675.00 | ||||
| 26 | Removable Bollard | 1 | Each | $1,220.00 | $1,220.00 | $1,200.00 | $1,200.00 | $1,325.00 | $1,325.00 | ||||
| 27 | Remove and Dispose of Chain Link Fence | 621 | L.F. | $3.50 | $2,173.50 | $8.00 | $4,968.00 | $9.70 | $6,023.70 | ||||
| 28 | Remove and Dispose of Light Pole | 4 | Each | $2,110.00 | $8,440.00 | $850.00 | $3,400.00 | $825.00 | $3,300.00 | ||||
| 29 | Remove and Replace Stairs | 1 | L.S. | $41,730.00 | $41,730.00 | $45,000.00 | $45,000.00 | $62,900.00 | $62,900.00 | ||||
| 30 | Seeding, Native Prairie | 1.1 | Acres | $4,050.00 | $4,455.00 | $4,000.00 | $4,400.00 | $4,400.00 | $4,840.00 | ||||
| 31 | Sign - ADA Parking | 10 | Each | $150.00 | $1,500.00 | $195.00 | $1,950.00 | $215.00 | $2,150.00 | ||||
| 32 | Sign - Authorized Vehicles | 2 | Each | $150.00 | $300.00 | $175.00 | $350.00 | $195.00 | $390.00 | ||||
| 33 | Sign - Begin One Way | 2 | Each | $150.00 | $300.00 | $180.00 | $360.00 | $200.00 | $400.00 | ||||
| 34 | Sign - Employee Parking | 3 | Each | $150.00 | $450.00 | $180.00 | $540.00 | $200.00 | $600.00 | ||||
| 35 | Sign - Loading Zone | 3 | Each | $150.00 | $450.00 | $180.00 | $540.00 | $200.00 | $600.00 | ||||
| 36 | Sign - No Parking | 10 | Each | $150.00 | $1,500.00 | $180.00 | $1,800.00 | $200.00 | $2,000.00 | ||||
| 37 | Sign - One Way | 1 | Each | $150.00 | $150.00 | $180.00 | $180.00 | $200.00 | $200.00 | ||||
| 38 | Sign - Rigging Lane | 21 | Each | $150.00 | $3,150.00 | $180.00 | $3,780.00 | $200.00 | $4,200.00 | ||||
| 39 | Solar Light Pole with Base | 1 | Each | $10,880.00 | $10,880.00 | $10,106.00 | $10,106.00 | $10,900.00 | $10,900.00 | ||||
| 40 | Special Backfill | 14104 | Tons | $22.00 | $310,288.00 | $21.75 | $306,762.00 | $25.25 | $356,126.00 | ||||
| 41 | SW-501 Single Grate Intake | 2 | Each | $3,550.00 | $7,100.00 | $3,500.00 | $7,000.00 | $4,450.00 | $8,900.00 | ||||
| 42 | SW-512 Circular Area Intake | 1 | Each | $3,040.00 | $3,040.00 | $3,000.00 | $3,000.00 | $2,600.00 | $2,600.00 | ||||
| 43 | SW-513 Open Sided Area Intake | 1 | Each | $5,365.00 | $5,365.00 | $5,300.00 | $5,300.00 | $5,580.00 | $5,580.00 | ||||
| 44 | Trench Drain | 44 | L.F. | $425.00 | $18,700.00 | $150.00 | $6,600.00 | $278.00 | $12,232.00 | ||||
| 45 | Truncated Dome Panel | 2 | Each | $365.00 | $730.00 | $450.00 | $900.00 | $250.00 | $500.00 | ||||
| $2,433,727.00 | $2,795,951.28 | $2,811,399.38 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $2,700,000.00 | Contractor: | Jensen Builders Ltd | Nehring Construction, Inc. | All Star Concrete LLC | |||||||||
| Funding Source: 75% Federal-DJ, 25% Marine Fuel Tax, | 1175 South 32nd St | 4300 NE 14th St | 4989 NW Johnston Dr | ||||||||||
| Fort Dodge IA 50501 | Des Moines IA 50313 | Johnston IA 50131 | |||||||||||
| Plan Sets Requested: 5 | Quantities | 5155733292 | 5152651440 | 5152246394 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $105,000.00 | $105,000.00 | $164,400.00 | $164,400.00 | $76,432.50 | $76,432.50 | ||||
| 2 | Traffic Control | 1 | L.S. | $4,300.00 | $4,300.00 | $4,000.00 | $4,000.00 | $3,762.50 | $3,762.50 | ||||
| 3 | Construction Survey | 1 | L.S. | $33,400.00 | $33,400.00 | $23,000.00 | $23,000.00 | $18,275.00 | $18,275.00 | ||||
| 4 | Site Restoration | 1 | L.S. | $24,300.00 | $24,300.00 | $15,000.00 | $15,000.00 | $32,250.00 | $32,250.00 | ||||
| 5 | 15" Dia. RCP | 180 | L.F. | $90.00 | $16,200.00 | $87.15 | $15,687.00 | $53.75 | $9,675.00 | ||||
| 6 | 15" Dia. RCP Apron | 1 | Each | $4,100.00 | $4,100.00 | $3,995.00 | $3,995.00 | $2,365.00 | $2,365.00 | ||||
| 7 | 18" Dia. RCP | 247 | L.F. | $96.00 | $23,712.00 | $93.45 | $23,082.15 | $59.13 | $14,605.11 | ||||
| 8 | 18" Dia. RCP Apron | 7 | Each | $4,300.00 | $30,100.00 | $4,200.00 | $29,400.00 | $2,687.50 | $18,812.50 | ||||
| 9 | 24" Dia. RCP | 81 | L.F. | $132.00 | $10,692.00 | $128.10 | $10,376.10 | $77.40 | $6,269.40 | ||||
| 10 | 24" Dia. RCP Apron | 4 | Each | $5,225.00 | $20,900.00 | $5,092.00 | $20,368.00 | $2,902.50 | $11,610.00 | ||||
| 11 | 5" PCC | 181 | S.Y. | $56.00 | $10,136.00 | $55.00 | $9,955.00 | $60.90 | $11,022.90 | ||||
| 12 | 6" Curb | 2830 | L.F. | $3.90 | $11,037.00 | $1.20 | $3,396.00 | $36.54 | $103,408.20 | ||||
| 13 | 6" PCC | 41418 | S.Y. | $43.25 | $1,791,328.50 | $42.30 | $1,751,981.40 | $46.69 | $1,933,806.42 | ||||
| 14 | Class A Crushed Stone | 45 | Tons | $43.00 | $1,935.00 | $40.00 | $1,800.00 | $27.95 | $1,257.75 | ||||
| 15 | Concrete Pipe Disposal | 1 | L.S. | $24,000.00 | $24,000.00 | $23,625.00 | $23,625.00 | $3,225.00 | $3,225.00 | ||||
| 16 | Curb Cuts | 51 | Each | $215.00 | $10,965.00 | $50.00 | $2,550.00 | $215.00 | $10,965.00 | ||||
| 17 | Demolish Kiosk and Light Pole | 1 | L.S. | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,332.50 | $3,332.50 | ||||
| 18 | Electrical Connection - East Boat Ramp | 1 | L.S. | $2,600.00 | $2,600.00 | $10,500.00 | $10,500.00 | $5,375.00 | $5,375.00 | ||||
| 19 | Excavation, Class 10, Waste | 8331 | C.Y. | $17.00 | $141,627.00 | $15.75 | $131,213.25 | $16.13 | $134,379.03 | ||||
| 20 | Light Pole with Base | 3 | Each | $6,340.00 | $19,020.00 | $4,515.00 | $13,545.00 | $6,450.00 | $19,350.00 | ||||
| 21 | Parking Bumper | 4 | Each | $145.00 | $580.00 | $200.00 | $800.00 | $161.25 | $645.00 | ||||
| 22 | Pavement Markings - ADA Parking | 13 | Each | $64.00 | $832.00 | $66.00 | $858.00 | $69.88 | $908.44 | ||||
| 23 | Pavement Removal | 33886 | S.Y. | $5.00 | $169,430.00 | $4.90 | $166,041.40 | $4.84 | $164,008.24 | ||||
| 24 | Pavement Striping | 16659 | L.F. | $0.76 | $12,660.84 | $0.60 | $9,995.40 | $0.76 | $12,660.84 | ||||
| 25 | Raise Stormwater Intakes | 3 | Each | $2,425.00 | $7,275.00 | $2,365.00 | $7,095.00 | $1,612.50 | $4,837.50 | ||||
| 26 | Removable Bollard | 1 | Each | $1,380.00 | $1,380.00 | $3,000.00 | $3,000.00 | $1,290.00 | $1,290.00 | ||||
| 27 | Remove and Dispose of Chain Link Fence | 621 | L.F. | $5.50 | $3,415.50 | $2.50 | $1,552.50 | $8.60 | $5,340.60 | ||||
| 28 | Remove and Dispose of Light Pole | 4 | Each | $2,250.00 | $9,000.00 | $800.00 | $3,200.00 | $2,687.50 | $10,750.00 | ||||
| 29 | Remove and Replace Stairs | 1 | L.S. | $32,250.00 | $32,250.00 | $48,320.00 | $48,320.00 | $40,600.00 | $40,600.00 | ||||
| 30 | Seeding, Native Prairie | 1.1 | Acres | $4,850.00 | $5,335.00 | $4,840.00 | $5,324.00 | $5,375.00 | $5,912.50 | ||||
| 31 | Sign - ADA Parking | 10 | Each | $195.00 | $1,950.00 | $175.00 | $1,750.00 | $161.25 | $1,612.50 | ||||
| 32 | Sign - Authorized Vehicles | 2 | Each | $195.00 | $390.00 | $175.00 | $350.00 | $161.25 | $322.50 | ||||
| 33 | Sign - Begin One Way | 2 | Each | $195.00 | $390.00 | $175.00 | $350.00 | $161.25 | $322.50 | ||||
| 34 | Sign - Employee Parking | 3 | Each | $195.00 | $585.00 | $175.00 | $525.00 | $161.25 | $483.75 | ||||
| 35 | Sign - Loading Zone | 3 | Each | $195.00 | $585.00 | $175.00 | $525.00 | $161.25 | $483.75 | ||||
| 36 | Sign - No Parking | 10 | Each | $195.00 | $1,950.00 | $175.00 | $1,750.00 | $161.25 | $1,612.50 | ||||
| 37 | Sign - One Way | 1 | Each | $195.00 | $195.00 | $175.00 | $175.00 | $161.25 | $161.25 | ||||
| 38 | Sign - Rigging Lane | 21 | Each | $195.00 | $4,095.00 | $175.00 | $3,675.00 | $161.25 | $3,386.25 | ||||
| 39 | Solar Light Pole with Base | 1 | Each | $11,580.00 | $11,580.00 | $10,400.00 | $10,400.00 | $11,287.50 | $11,287.50 | ||||
| 40 | Special Backfill | 14104 | Tons | $28.00 | $394,912.00 | $32.00 | $451,328.00 | $22.58 | $318,468.32 | ||||
| 41 | SW-501 Single Grate Intake | 2 | Each | $4,900.00 | $9,800.00 | $4,780.00 | $9,560.00 | $2,956.25 | $5,912.50 | ||||
| 42 | SW-512 Circular Area Intake | 1 | Each | $4,473.00 | $4,473.00 | $4,360.00 | $4,360.00 | $2,902.50 | $2,902.50 | ||||
| 43 | SW-513 Open Sided Area Intake | 1 | Each | $8,245.00 | $8,245.00 | $8,035.00 | $8,035.00 | $6,127.50 | $6,127.50 | ||||
| 44 | Trench Drain | 44 | L.F. | $312.00 | $13,728.00 | $455.00 | $20,020.00 | $403.13 | $17,737.72 | ||||
| 45 | Truncated Dome Panel | 2 | Each | $370.00 | $740.00 | $700.00 | $1,400.00 | $456.75 | $913.50 | ||||
| $2,984,128.84 | $3,021,263.20 | $3,038,866.47 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $2,700,000.00 | Contractor: | Absolute Concrete Construction Inc. | |||||||||||
| Funding Source: 75% Federal-DJ, 25% Marine Fuel Tax, | 1000 W 6th Ave | ||||||||||||
| Slater IA 50244 | |||||||||||||
| Plan Sets Requested: 5 | Quantities | 5154976140 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $200,000.00 | $200,000.00 | $0.00 | $0.00 | ||||||
| 2 | Traffic Control | 1 | L.S. | $7,500.00 | $7,500.00 | $0.00 | $0.00 | ||||||
| 3 | Construction Survey | 1 | L.S. | $29,000.00 | $29,000.00 | $0.00 | $0.00 | ||||||
| 4 | Site Restoration | 1 | L.S. | $25,000.00 | $25,000.00 | $0.00 | $0.00 | ||||||
| 5 | 15" Dia. RCP | 180 | L.F. | $46.00 | $8,280.00 | $0.00 | $0.00 | ||||||
| 6 | 15" Dia. RCP Apron | 1 | Each | $2,180.00 | $2,180.00 | $0.00 | $0.00 | ||||||
| 7 | 18" Dia. RCP | 247 | L.F. | $51.00 | $12,597.00 | $0.00 | $0.00 | ||||||
| 8 | 18" Dia. RCP Apron | 7 | Each | $2,074.00 | $14,518.00 | $0.00 | $0.00 | ||||||
| 9 | 24" Dia. RCP | 81 | L.F. | $71.00 | $5,751.00 | $0.00 | $0.00 | ||||||
| 10 | 24" Dia. RCP Apron | 4 | Each | $2,654.00 | $10,616.00 | $0.00 | $0.00 | ||||||
| 11 | 5" PCC | 181 | S.Y. | $150.00 | $27,150.00 | $0.00 | $0.00 | ||||||
| 12 | 6" Curb | 2830 | L.F. | $22.00 | $62,260.00 | $0.00 | $0.00 | ||||||
| 13 | 6" PCC | 41418 | S.Y. | $46.50 | $1,925,937.00 | $0.00 | $0.00 | ||||||
| 14 | Class A Crushed Stone | 45 | Tons | $26.00 | $1,170.00 | $0.00 | $0.00 | ||||||
| 15 | Concrete Pipe Disposal | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 16 | Curb Cuts | 51 | Each | $30.00 | $1,530.00 | $0.00 | $0.00 | ||||||
| 17 | Demolish Kiosk and Light Pole | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 18 | Electrical Connection - East Boat Ramp | 1 | L.S. | $2,438.00 | $2,438.00 | $0.00 | $0.00 | ||||||
| 19 | Excavation, Class 10, Waste | 8331 | C.Y. | $15.50 | $129,130.50 | $0.00 | $0.00 | ||||||
| 20 | Light Pole with Base | 3 | Each | $5,882.00 | $17,646.00 | $0.00 | $0.00 | ||||||
| 21 | Parking Bumper | 4 | Each | $135.00 | $540.00 | $0.00 | $0.00 | ||||||
| 22 | Pavement Markings - ADA Parking | 13 | Each | $60.00 | $780.00 | $0.00 | $0.00 | ||||||
| 23 | Pavement Removal | 33886 | S.Y. | $6.00 | $203,316.00 | $0.00 | $0.00 | ||||||
| 24 | Pavement Striping | 16659 | L.F. | $0.70 | $11,661.30 | $0.00 | $0.00 | ||||||
| 25 | Raise Stormwater Intakes | 3 | Each | $1,500.00 | $4,500.00 | $0.00 | $0.00 | ||||||
| 26 | Removable Bollard | 1 | Each | $1,195.00 | $1,195.00 | $0.00 | $0.00 | ||||||
| 27 | Remove and Dispose of Chain Link Fence | 621 | L.F. | $9.00 | $5,589.00 | $0.00 | $0.00 | ||||||
| 28 | Remove and Dispose of Light Pole | 4 | Each | $2,084.00 | $8,336.00 | $0.00 | $0.00 | ||||||
| 29 | Remove and Replace Stairs | 1 | L.S. | $85,000.00 | $85,000.00 | $0.00 | $0.00 | ||||||
| 30 | Seeding, Native Prairie | 1.1 | Acres | $4,000.00 | $4,400.00 | $0.00 | $0.00 | ||||||
| 31 | Sign - ADA Parking | 10 | Each | $195.00 | $1,950.00 | $0.00 | $0.00 | ||||||
| 32 | Sign - Authorized Vehicles | 2 | Each | $175.00 | $350.00 | $0.00 | $0.00 | ||||||
| 33 | Sign - Begin One Way | 2 | Each | $180.00 | $360.00 | $0.00 | $0.00 | ||||||
| 34 | Sign - Employee Parking | 3 | Each | $180.00 | $540.00 | $0.00 | $0.00 | ||||||
| 35 | Sign - Loading Zone | 3 | Each | $180.00 | $540.00 | $0.00 | $0.00 | ||||||
| 36 | Sign - No Parking | 10 | Each | $180.00 | $1,800.00 | $0.00 | $0.00 | ||||||
| 37 | Sign - One Way | 1 | Each | $180.00 | $180.00 | $0.00 | $0.00 | ||||||
| 38 | Sign - Rigging Lane | 21 | Each | $180.00 | $3,780.00 | $0.00 | $0.00 | ||||||
| 39 | Solar Light Pole with Base | 1 | Each | $10,745.00 | $10,745.00 | $0.00 | $0.00 | ||||||
| 40 | Special Backfill | 14104 | Tons | $20.75 | $292,658.00 | $0.00 | $0.00 | ||||||
| 41 | SW-501 Single Grate Intake | 2 | Each | $2,750.00 | $5,500.00 | $0.00 | $0.00 | ||||||
| 42 | SW-512 Circular Area Intake | 1 | Each | $2,630.00 | $2,630.00 | $0.00 | $0.00 | ||||||
| 43 | SW-513 Open Sided Area Intake | 1 | Each | $5,700.00 | $5,700.00 | $0.00 | $0.00 | ||||||
| 44 | Trench Drain | 44 | L.F. | $600.00 | $26,400.00 | $0.00 | $0.00 | ||||||
| 45 | Truncated Dome Panel | 2 | Each | $600.00 | $1,200.00 | $0.00 | $0.00 | ||||||
| $3,169,853.80 | $0.00 | $0.00 | |||||||||||