 Bids For:  Location:   Green Valley State Park  Date: 7/22/2021  Project No.  
  Campground Sewer Main  County:   UNION  Time: 11:00 a.m.  22-04-88-02

 

 
1
2
3
Estimated Cost: $600,000.00
Contractor: 
Vicker Drilling, LLCEllingson Drainage, Inc.Jackson Creek Enterprises, LC
Funding Source: 67% Infrastructure, 33% Federal-Land and Water Conservation Fund, 2151 Cherry St Rd
56113 State Hwy 56
2232 120th St
Creston IA  50801West Concord MN  55985Allerton IA  50008
Plan Sets Requested: 3
Quantities
641202272850752722946418706500
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$7,500.00$7,500.00 $11,000.00$11,000.00 $8,000.00$8,000.00 
2LIFT STATION PUMPS, ELECTRICAL, ACCESSORIES, ELECTRICAL WIRING AND CONTROLS1L.S.$25,000.00$25,000.00 $33,000.00$33,000.00 $35,000.00$35,000.00 
3DISCONNECT AND PLUG OLD FORCEMAIN AND CONNECT NEW FM AT LIFT STATION1L.S.$1,200.00$1,200.00 $3,200.00$3,200.00 $3,675.00$3,675.00 
43" HDPE SDR 17 FORCEMAIN BORED BELOW LAKE BED WITH #12 TRACER WIRE1400L.F.$26.00$36,400.00 $22.00$30,800.00 $125.00$175,000.00 
53" HDPE SDR 17 FORCEMAIN BORED WITH #12 TRACER WIRE, INCLUDES ROAD CROSSINGS15100L.F.$16.00$241,600.00 $16.50$249,150.00 $16.00$241,600.00 
6AIR RELIEF VALVE COMPLETE WITH MANHOLE6Each$11,482.00$68,892.00 $16,250.00$97,500.00 $10,300.00$61,800.00 
7CONNECT FORCEMAIN TO CITY MANHOLE1L.S.$1,000.00$1,000.00 $2,100.00$2,100.00 $4,500.00$4,500.00 
8SITE RESTORATION1L.S.$2,500.00$2,500.00 $38,750.00$38,750.00 $4,500.00$4,500.00 
9LAGOON CONTENTS, PUMPING, DISPOSAL AND LAGOON DEMOLITION1L.S.$35,000.00$35,000.00 $81,000.00$81,000.00 $50,000.00$50,000.00 
      $419,092.00  $546,500.00  $584,075.00 
 



 

5/1/2024