IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Sugema Wildlife Management Area  Date: 11/17/2022  Project No.  
  Mercer Wetland Water Control Structure Replacement  County:   VAN BUREN  Time: 11:00 a.m.  22-06-89-01

 

 
1
2
3
Estimated Cost: $140,000.00
Contractor: 
Nagel ConstructionDrish Construction IncCole Construction Co, Inc
Funding Source: 30% Federal-EPA, 30% REAP OS Acquisition & Development, 40% Lake Restoration, 2601 140th St
1701 S Main St
24100 Queen Ave
Allerton IA  50008Fairfield IA  52556Keosauqua IA  52565
Plan Sets Requested: 4
Quantities
641-203-2756641-472-9506319-592-3103
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,000.00$5,000.00 $15,000.00$15,000.00 $30,000.00$30,000.00 
2Site Restoration1L.S.$5,000.00$5,000.00 $7,300.00$7,300.00 $8,500.00$8,500.00 
3Intake Structure1L.S.$12,000.00$12,000.00 $68,000.00$68,000.00 $25,000.00$25,000.00 
448" Smooth Metal Pipe177.5L.F.$300.00$53,250.00 $410.00$72,775.00 $510.00$90,525.00 
5Reinforced Concrete Footing And Pad1L.S.$11,000.00$11,000.00 $8,250.00$8,250.00 $4,500.00$4,500.00 
66" Smooth Metal Pipe79.5L.F.$60.00$4,770.00 $155.00$12,322.50 $65.31$5,192.145 
7Fine Drainfill130Tons$80.00$10,400.00 $80.00$10,400.00 $81.00$10,530.00 
8Aluminum Stoplogs1L.S.$13,000.00$13,000.00 $15,000.00$15,000.00 $26,010.21$26,010.21 
9Sediment Log216L.F.$6.00$1,296.00 $10.00$2,160.00 $12.00$2,592.00 
10Demolition1L.S.$5,000.00$5,000.00 $17,500.00$17,500.00 $61,545.58$61,545.58 
11Class E Revetment65Tons$55.00$3,575.00 $60.00$3,900.00 $55.00$3,575.00 
      $124,291.00  $232,607.50  $267,969.935 
 



 

12/22/2024