IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Sugema Wildlife Management Area | Date: 11/17/2022 | Project No. |
Mercer Wetland Water Control Structure Replacement | County: | VAN BUREN | Time: 11:00 a.m. | 22-06-89-01 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $140,000.00 | Contractor: | ![]() | Nagel Construction | Drish Construction Inc | Cole Construction Co, Inc | ![]() | |||||||
Funding Source: 30% Federal-EPA, 30% REAP OS Acquisition & Development, 40% Lake Restoration, | ![]() | 2601 140th St | ![]() | 1701 S Main St | ![]() | 24100 Queen Ave | ![]() | ||||||
![]() | Allerton IA 50008 | ![]() | Fairfield IA 52556 | ![]() | Keosauqua IA 52565 | ![]() | |||||||
Plan Sets Requested: 4 | Quantities | ![]() | 641-203-2756 | ![]() | 641-472-9506 | ![]() | 319-592-3103 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $15,000.00 | $15,000.00 | ![]() | $30,000.00 | $30,000.00 | ![]() |
2 | Site Restoration | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $7,300.00 | $7,300.00 | ![]() | $8,500.00 | $8,500.00 | ![]() |
3 | Intake Structure | 1 | L.S. | ![]() | $12,000.00 | $12,000.00 | ![]() | $68,000.00 | $68,000.00 | ![]() | $25,000.00 | $25,000.00 | ![]() |
4 | 48" Smooth Metal Pipe | 177.5 | L.F. | ![]() | $300.00 | $53,250.00 | ![]() | $410.00 | $72,775.00 | ![]() | $510.00 | $90,525.00 | ![]() |
5 | Reinforced Concrete Footing And Pad | 1 | L.S. | ![]() | $11,000.00 | $11,000.00 | ![]() | $8,250.00 | $8,250.00 | ![]() | $4,500.00 | $4,500.00 | ![]() |
6 | 6" Smooth Metal Pipe | 79.5 | L.F. | ![]() | $60.00 | $4,770.00 | ![]() | $155.00 | $12,322.50 | ![]() | $65.31 | $5,192.145 | ![]() |
7 | Fine Drainfill | 130 | Tons | ![]() | $80.00 | $10,400.00 | ![]() | $80.00 | $10,400.00 | ![]() | $81.00 | $10,530.00 | ![]() |
8 | Aluminum Stoplogs | 1 | L.S. | ![]() | $13,000.00 | $13,000.00 | ![]() | $15,000.00 | $15,000.00 | ![]() | $26,010.21 | $26,010.21 | ![]() |
9 | Sediment Log | 216 | L.F. | ![]() | $6.00 | $1,296.00 | ![]() | $10.00 | $2,160.00 | ![]() | $12.00 | $2,592.00 | ![]() |
10 | Demolition | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $17,500.00 | $17,500.00 | ![]() | $61,545.58 | $61,545.58 | ![]() |
11 | Class E Revetment | 65 | Tons | ![]() | $55.00 | $3,575.00 | ![]() | $60.00 | $3,900.00 | ![]() | $55.00 | $3,575.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$124,291.00 | ![]() | $232,607.50 | ![]() | $267,969.935 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
7/27/2024