IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Macbride State Park | Date: 9/22/2022 | Project No. |
North Shore Parking Lot Extension | County: | JOHNSON | Time: 11:00 a.m. | 22-06-52-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $475,000.00 | Contractor: | Eastern Iowa Excavating & Concrete LLC | Triple B Construction | BWC, INC | |||||||||
Funding Source: 100% Federal-Boat Safety (Coast Guard), | 121 Nixon St SE | 710 Ayres Progress Dr | 1303 Hickory Hollow Rd | ||||||||||
Cascade IA 52033 | Wilton IA 52778 | Solon IA 52333 | |||||||||||
Plan Sets Requested: 6 | Quantities | 563-852-5120 | 563-732-3478 | 319-848-7513 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $4,950.00 | $4,950.00 | $5,000.00 | $5,000.00 | $2,420.00 | $2,420.00 | ||||
2 | Painted Pavement Mark, High-Build Waterborne | 15 | STA. | $155.00 | $2,325.00 | $120.00 | $1,800.00 | $119.75 | $1,796.25 | ||||
3 | Pavement, 7" PCC | 2671 | S.Y. | $43.00 | $114,853.00 | $53.50 | $142,898.50 | $56.25 | $150,243.75 | ||||
4 | Earth Shoulder | 6 | STA. | $355.00 | $2,130.00 | $550.00 | $3,300.00 | $1,006.25 | $6,037.50 | ||||
5 | Special Backfill | 470 | C.Y. | $47.50 | $22,325.00 | $47.00 | $22,090.00 | $45.50 | $21,385.00 | ||||
6 | Sidewalk, 6" PCC | 3 | S.Y. | $310.50 | $931.50 | $190.00 | $570.00 | $121.00 | $363.00 | ||||
7 | Detectable Warning Panel | 10 | S.F. | $52.00 | $520.00 | $75.00 | $750.00 | $59.50 | $595.00 | ||||
8 | Excavation, Class 10, Roadway and Borrow | 521 | C.Y. | $29.65 | $15,447.65 | $14.50 | $7,554.50 | $22.00 | $11,462.00 | ||||
9 | Embankment-In-Place, Contractor Furnish | 26 | C.Y. | $59.50 | $1,547.00 | $50.00 | $1,300.00 | $87.50 | $2,275.00 | ||||
10 | Seeding, Fertilizing, and Mulching | 0.4 | Acres | $11,250.00 | $4,500.00 | $7,700.00 | $3,080.00 | $14,700.00 | $5,880.00 | ||||
11 | Filter Sock, 8" | 645 | L.F. | $2.75 | $1,773.75 | $2.50 | $1,612.50 | $2.65 | $1,709.25 | ||||
12 | Signing | 1 | Each | $650.00 | $650.00 | $935.00 | $935.00 | $935.00 | $935.00 | ||||
13 | Precast Concrete Parking Wheel Stops | 1 | Each | $335.00 | $335.00 | $100.00 | $100.00 | $100.00 | $100.00 | ||||
14 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $825.00 | $825.00 | $6,000.00 | $6,000.00 | $1,795.00 | $1,795.00 | ||||
15 | Construction Staking | 1 | L.S. | $3,800.00 | $3,800.00 | $4,000.00 | $4,000.00 | $2,500.00 | $2,500.00 | ||||
16 | Traffic Control | 1 | L.S. | $575.00 | $575.00 | $1,000.00 | $1,000.00 | $577.50 | $577.50 | ||||
17 | Mobilization | 1 | L.S. | $21,500.00 | $21,500.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | ||||
$198,987.90 | $221,990.50 | $230,074.25 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $475,000.00 | Contractor: | Midwest Concrete Inc | Boomerang Corp of Iowa | All American Concrete, Inc | |||||||||
Funding Source: 100% Federal-Boat Safety (Coast Guard), | 9835 Midwest Lane | 13225 Circle Drive Suite A PO Box 227 | 1489 Highway 6 | ||||||||||
Peosta IA 52068 | Anamosa IA 52205 | West Liberty IA 52776 | |||||||||||
Plan Sets Requested: 6 | Quantities | 563-583-1007 | 319-462-4435 | 319-627-2226 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $6,994.00 | $6,994.00 | $20,000.00 | $20,000.00 | $11,200.00 | $11,200.00 | ||||
2 | Painted Pavement Mark, High-Build Waterborne | 15 | STA. | $113.00 | $1,695.00 | $120.00 | $1,800.00 | $121.00 | $1,815.00 | ||||
3 | Pavement, 7" PCC | 2671 | S.Y. | $48.00 | $128,208.00 | $60.00 | $160,260.00 | $51.00 | $136,221.00 | ||||
4 | Earth Shoulder | 6 | STA. | $859.00 | $5,154.00 | $700.00 | $4,200.00 | $300.00 | $1,800.00 | ||||
5 | Special Backfill | 470 | C.Y. | $54.00 | $25,380.00 | $50.00 | $23,500.00 | $58.00 | $27,260.00 | ||||
6 | Sidewalk, 6" PCC | 3 | S.Y. | $230.00 | $690.00 | $200.00 | $600.00 | $110.00 | $330.00 | ||||
7 | Detectable Warning Panel | 10 | S.F. | $45.00 | $450.00 | $50.00 | $500.00 | $54.00 | $540.00 | ||||
8 | Excavation, Class 10, Roadway and Borrow | 521 | C.Y. | $33.00 | $17,193.00 | $15.00 | $7,815.00 | $20.00 | $10,420.00 | ||||
9 | Embankment-In-Place, Contractor Furnish | 26 | C.Y. | $61.00 | $1,586.00 | $40.00 | $1,040.00 | $57.00 | $1,482.00 | ||||
10 | Seeding, Fertilizing, and Mulching | 0.4 | Acres | $9,270.00 | $3,708.00 | $10,000.00 | $4,000.00 | $7,800.00 | $3,120.00 | ||||
11 | Filter Sock, 8" | 645 | L.F. | $3.00 | $1,935.00 | $3.00 | $1,935.00 | $3.00 | $1,935.00 | ||||
12 | Signing | 1 | Each | $876.00 | $876.00 | $1,000.00 | $1,000.00 | $950.00 | $950.00 | ||||
13 | Precast Concrete Parking Wheel Stops | 1 | Each | $93.00 | $93.00 | $300.00 | $300.00 | $100.00 | $100.00 | ||||
14 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $4,120.00 | $4,120.00 | $3,000.00 | $3,000.00 | $6,200.00 | $6,200.00 | ||||
15 | Construction Staking | 1 | L.S. | $7,210.00 | $7,210.00 | $3,000.00 | $3,000.00 | $4,400.00 | $4,400.00 | ||||
16 | Traffic Control | 1 | L.S. | $1,545.00 | $1,545.00 | $1,500.00 | $1,500.00 | $650.00 | $650.00 | ||||
17 | Mobilization | 1 | L.S. | $30,000.00 | $30,000.00 | $13,327.00 | $13,327.00 | $40,000.00 | $40,000.00 | ||||
$236,837.00 | $247,777.00 | $248,423.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $475,000.00 | Contractor: | Rathje Construction Co | Tschiggfrie Excavating | Bockenstedt Excavating Inc | |||||||||
Funding Source: 100% Federal-Boat Safety (Coast Guard), | 305 44th St | 425 Julien Dubuque Dr | 3506 Dolphin Dr | ||||||||||
Marion IA 52302 | Dubuque IA 52003 | Iowa City IA 52240 | |||||||||||
Plan Sets Requested: 6 | Quantities | 319-377-3179 | 563-557-7450 | 319-331-1558 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $6,500.00 | $6,500.00 | $10,600.00 | $10,600.00 | $10,000.00 | $10,000.00 | ||||
2 | Painted Pavement Mark, High-Build Waterborne | 15 | STA. | $118.50 | $1,777.50 | $58.00 | $870.00 | $175.00 | $2,625.00 | ||||
3 | Pavement, 7" PCC | 2671 | S.Y. | $51.00 | $136,221.00 | $55.00 | $146,905.00 | $56.25 | $150,243.75 | ||||
4 | Earth Shoulder | 6 | STA. | $350.00 | $2,100.00 | $660.00 | $3,960.00 | $1,000.00 | $6,000.00 | ||||
5 | Special Backfill | 470 | C.Y. | $60.00 | $28,200.00 | $54.00 | $25,380.00 | $45.00 | $21,150.00 | ||||
6 | Sidewalk, 6" PCC | 3 | S.Y. | $110.00 | $330.00 | $150.00 | $450.00 | $56.00 | $168.00 | ||||
7 | Detectable Warning Panel | 10 | S.F. | $54.00 | $540.00 | $50.00 | $500.00 | $60.00 | $600.00 | ||||
8 | Excavation, Class 10, Roadway and Borrow | 521 | C.Y. | $46.00 | $23,966.00 | $18.00 | $9,378.00 | $25.00 | $13,025.00 | ||||
9 | Embankment-In-Place, Contractor Furnish | 26 | C.Y. | $35.00 | $910.00 | $18.00 | $468.00 | $45.00 | $1,170.00 | ||||
10 | Seeding, Fertilizing, and Mulching | 0.4 | Acres | $9,000.00 | $3,600.00 | $6,900.00 | $2,760.00 | $6,000.00 | $2,400.00 | ||||
11 | Filter Sock, 8" | 645 | L.F. | $2.10 | $1,354.50 | $3.50 | $2,257.50 | $2.50 | $1,612.50 | ||||
12 | Signing | 1 | Each | $2,200.00 | $2,200.00 | $870.00 | $870.00 | $2,000.00 | $2,000.00 | ||||
13 | Precast Concrete Parking Wheel Stops | 1 | Each | $175.00 | $175.00 | $220.00 | $220.00 | $1,000.00 | $1,000.00 | ||||
14 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $4,000.00 | $4,000.00 | $2,900.00 | $2,900.00 | $5,500.00 | $5,500.00 | ||||
15 | Construction Staking | 1 | L.S. | $2,500.00 | $2,500.00 | $4,000.00 | $4,000.00 | $25,000.00 | $25,000.00 | ||||
16 | Traffic Control | 1 | L.S. | $1,000.00 | $1,000.00 | $1,700.00 | $1,700.00 | $3,000.00 | $3,000.00 | ||||
17 | Mobilization | 1 | L.S. | $34,000.00 | $34,000.00 | $44,600.00 | $44,600.00 | $19,500.00 | $19,500.00 | ||||
$249,374.00 | $257,818.50 | $264,994.25 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $475,000.00 | Contractor: | Jasper Construction Services Inc | OEL Construction Services, INC | ||||||||||
Funding Source: 100% Federal-Boat Safety (Coast Guard), | 928 N 19th Ave E | 1306 River Road S | |||||||||||
Newton IA 50208 | Steamboat Rock IA 50672 | ||||||||||||
Plan Sets Requested: 6 | Quantities | 641-792-8650 | 641-868-2222 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $5,000.00 | $5,000.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
2 | Painted Pavement Mark, High-Build Waterborne | 15 | STA. | $120.00 | $1,800.00 | $100.00 | $1,500.00 | $0.00 | |||||
3 | Pavement, 7" PCC | 2671 | S.Y. | $72.00 | $192,312.00 | $65.00 | $173,615.00 | $0.00 | |||||
4 | Earth Shoulder | 6 | STA. | $600.00 | $3,600.00 | $1,500.00 | $9,000.00 | $0.00 | |||||
5 | Special Backfill | 470 | C.Y. | $62.00 | $29,140.00 | $52.50 | $24,675.00 | $0.00 | |||||
6 | Sidewalk, 6" PCC | 3 | S.Y. | $150.00 | $450.00 | $550.00 | $1,650.00 | $0.00 | |||||
7 | Detectable Warning Panel | 10 | S.F. | $75.00 | $750.00 | $200.00 | $2,000.00 | $0.00 | |||||
8 | Excavation, Class 10, Roadway and Borrow | 521 | C.Y. | $32.00 | $16,672.00 | $37.75 | $19,667.75 | $0.00 | |||||
9 | Embankment-In-Place, Contractor Furnish | 26 | C.Y. | $75.00 | $1,950.00 | $400.00 | $10,400.00 | $0.00 | |||||
10 | Seeding, Fertilizing, and Mulching | 0.4 | Acres | $6,000.00 | $2,400.00 | $10,000.00 | $4,000.00 | $0.00 | |||||
11 | Filter Sock, 8" | 645 | L.F. | $1.50 | $967.50 | $2.50 | $1,612.50 | $0.00 | |||||
12 | Signing | 1 | Each | $1,000.00 | $1,000.00 | $1,225.00 | $1,225.00 | $0.00 | |||||
13 | Precast Concrete Parking Wheel Stops | 1 | Each | $150.00 | $150.00 | $210.00 | $210.00 | $0.00 | |||||
14 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $3,200.00 | $3,200.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
15 | Construction Staking | 1 | L.S. | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
16 | Traffic Control | 1 | L.S. | $2,000.00 | $2,000.00 | $800.00 | $800.00 | $0.00 | |||||
17 | Mobilization | 1 | L.S. | $20,000.00 | $20,000.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
$285,391.50 | $294,355.25 | $0.00 | |||||||||||
12/21/2024