IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Ahquabi State Park | Date: 3/3/2022 | Project No. |
Spillway Joint Repairs | County: | WARREN | Time: 3:00 p.m. | 22-05-91-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $43,000.00 | Contractor: | National Sealant and Concrete LLC | Minturn, Inc. | ||||||||||
Funding Source: 100% Lake Restoration, | 18989 County Rd 30 | 144 W Front St | |||||||||||
Crosby MN 56441 | Brooklyn IA 52211 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 9205887649 | 6414550331 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Joint Cleaning | 1786 | L.F. | $9.80 | $17,502.80 | $6.00 | $10,716.00 | $0.00 | |||||
2 | Joint Sealant | 1786 | L.F. | $8.35 | $14,913.10 | $25.00 | $44,650.00 | $0.00 | |||||
3 | Joint Primer, If Needed | 1786 | L.F. | $0.01 | $17.86 | $1.00 | $1,786.00 | $0.00 | |||||
4 | Joint Edge Repair Grout, If Needed | 150 | L.F. | $8.00 | $1,200.00 | $20.00 | $3,000.00 | $0.00 | |||||
5 | Partial Depth Concrete Repair | 10 | S.F. | $250.00 | $2,500.00 | $450.00 | $4,500.00 | $0.00 | |||||
6 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $7,000.00 | $7,000.00 | $0.00 | |||||
$41,133.76 | $71,652.00 | $0.00 | |||||||||||
3/29/2024