IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Ahquabi State Park  Date: 3/3/2022  Project No.  
  Spillway Joint Repairs  County:   WARREN  Time: 3:00 p.m.  22-05-91-05

 

 
1
2
3
Estimated Cost: $43,000.00
Contractor: 
National Sealant and Concrete LLCMinturn, Inc.
Funding Source: 100% Lake Restoration, 18989 County Rd 30
144 W Front St

Crosby MN  56441Brooklyn IA  52211  
Plan Sets Requested: 0
Quantities
92058876496414550331
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Joint Cleaning1786L.F.$9.80$17,502.80 $6.00$10,716.00 $0.00 
2Joint Sealant1786L.F.$8.35$14,913.10 $25.00$44,650.00 $0.00 
3Joint Primer, If Needed1786L.F.$0.01$17.86 $1.00$1,786.00 $0.00 
4Joint Edge Repair Grout, If Needed150L.F.$8.00$1,200.00 $20.00$3,000.00 $0.00 
5Partial Depth Concrete Repair10S.F.$250.00$2,500.00 $450.00$4,500.00 $0.00 
6Mobilization1L.S.$5,000.00$5,000.00 $7,000.00$7,000.00 $0.00 
      $41,133.76  $71,652.00  $0.00 
 



 

3/29/2024