IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Ahquabi State Park | Date: 3/3/2022 | Project No. |
Spillway Joint Repairs | County: | WARREN | Time: 3:00 p.m. | 22-05-91-05 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $43,000.00 | Contractor: | ![]() | National Sealant and Concrete LLC | Minturn, Inc. | ![]() | ||||||||
Funding Source: 100% Lake Restoration, | ![]() | 18989 County Rd 30 | ![]() | 144 W Front St | ![]() | ![]() | |||||||
![]() | Crosby MN 56441 | ![]() | Brooklyn IA 52211 | ![]() | ![]() | ||||||||
Plan Sets Requested: 0 | Quantities | ![]() | 9205887649 | ![]() | 6414550331 | ![]() | ![]() | ||||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Joint Cleaning | 1786 | L.F. | ![]() | $9.80 | $17,502.80 | ![]() | $6.00 | $10,716.00 | ![]() | $0.00 | ![]() | |
2 | Joint Sealant | 1786 | L.F. | ![]() | $8.35 | $14,913.10 | ![]() | $25.00 | $44,650.00 | ![]() | $0.00 | ![]() | |
3 | Joint Primer, If Needed | 1786 | L.F. | ![]() | $0.01 | $17.86 | ![]() | $1.00 | $1,786.00 | ![]() | $0.00 | ![]() | |
4 | Joint Edge Repair Grout, If Needed | 150 | L.F. | ![]() | $8.00 | $1,200.00 | ![]() | $20.00 | $3,000.00 | ![]() | $0.00 | ![]() | |
5 | Partial Depth Concrete Repair | 10 | S.F. | ![]() | $250.00 | $2,500.00 | ![]() | $450.00 | $4,500.00 | ![]() | $0.00 | ![]() | |
6 | Mobilization | 1 | L.S. | ![]() | $5,000.00 | $5,000.00 | ![]() | $7,000.00 | $7,000.00 | ![]() | $0.00 | ![]() | |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$41,133.76 | ![]() | $71,652.00 | ![]() | $0.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
7/27/2024