IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Maquoketa Caves State Park | Date: 2/25/2021 | Project No. |
Residence Leach Field | County: | JACKSON | Time: 3:00 p.m. | 21-06-49-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $17,000.00 | Contractor: | Connolly Concrete & Excavating Inc. | Dan Oberbreckling Concrete & Excavating | Triple B Construction | |||||||||
Funding Source: 100% REAP Land Management, | PO Box 942 | 2780 Coggon Rd | 710 Ayres Progress Dr | ||||||||||
Cascade IA 52033 | Coggon IA 52218 | Wilton IA 52778 | |||||||||||
Plan Sets Requested: 0 | Quantities | 5635439772 | 5639200970 | 5637323478 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $750.00 | $750.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | ||||
2 | Clearing and Grubbing | 1 | L.S. | $500.00 | $500.00 | $800.00 | $800.00 | $250.00 | $250.00 | ||||
3 | Install Quick4 Plus (Or Approved Equivalent) Standard Low Profile Chambers | 85 | Each | $47.00 | $3,995.00 | $60.00 | $5,100.00 | $65.00 | $5,525.00 | ||||
4 | Connection Between Septic Tank & Chambers | 1 | L.S. | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 | ||||
5 | Connection Between House Basement & Existing Pipe | 1 | L.S. | $1,000.00 | $1,000.00 | $1,500.15 | $1,500.15 | $1,150.00 | $1,150.00 | ||||
6 | Remove & Replace Sidewalk 6" PCC | 17 | S.Y. | $70.00 | $1,190.00 | $117.50 | $1,997.50 | $80.00 | $1,360.00 | ||||
7 | Site Restoration | 1 | L.S. | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $2,250.00 | $2,250.00 | ||||
$9,435.00 | $11,897.65 | $12,035.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $17,000.00 | Contractor: | Connolly Construction Inc. | Kraus Plumbing & Heating, LLC | F.L. Krapfl, Inc. | |||||||||
Funding Source: 100% REAP Land Management, | 18409 N Cascade Rd | 317 S Locust St | PO Box 303 | ||||||||||
Peosta IA 52068 | Monticello IA 52310 | Dyersville IA 52040 | |||||||||||
Plan Sets Requested: 0 | Quantities | 5638763225 | 3194655129 | 5638758938 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,676.00 | $2,676.00 | $500.00 | $500.00 | $1,200.00 | $1,200.00 | ||||
2 | Clearing and Grubbing | 1 | L.S. | $1,272.00 | $1,272.00 | $540.00 | $540.00 | $300.00 | $300.00 | ||||
3 | Install Quick4 Plus (Or Approved Equivalent) Standard Low Profile Chambers | 85 | Each | $59.70 | $5,074.50 | $78.00 | $6,630.00 | $114.00 | $9,690.00 | ||||
4 | Connection Between Septic Tank & Chambers | 1 | L.S. | $555.00 | $555.00 | $1,040.00 | $1,040.00 | $1,496.00 | $1,496.00 | ||||
5 | Connection Between House Basement & Existing Pipe | 1 | L.S. | $755.00 | $755.00 | $960.00 | $960.00 | $1,516.00 | $1,516.00 | ||||
6 | Remove & Replace Sidewalk 6" PCC | 17 | S.Y. | $63.70 | $1,082.90 | $214.00 | $3,638.00 | $73.00 | $1,241.00 | ||||
7 | Site Restoration | 1 | L.S. | $1,803.00 | $1,803.00 | $1,260.00 | $1,260.00 | $1,522.00 | $1,522.00 | ||||
$13,218.40 | $14,568.00 | $16,965.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $17,000.00 | Contractor: | Mainline Excavating Co. Inc. | |||||||||||
Funding Source: 100% REAP Land Management, | 8180 Seippel Ct | ||||||||||||
Dubuque IA 52002 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 5635831888 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,700.00 | $2,700.00 | $0.00 | $0.00 | ||||||
2 | Clearing and Grubbing | 1 | L.S. | $3,500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
3 | Install Quick4 Plus (Or Approved Equivalent) Standard Low Profile Chambers | 85 | Each | $115.00 | $9,775.00 | $0.00 | $0.00 | ||||||
4 | Connection Between Septic Tank & Chambers | 1 | L.S. | $1,600.00 | $1,600.00 | $0.00 | $0.00 | ||||||
5 | Connection Between House Basement & Existing Pipe | 1 | L.S. | $2,020.00 | $2,020.00 | $0.00 | $0.00 | ||||||
6 | Remove & Replace Sidewalk 6" PCC | 17 | S.Y. | $78.00 | $1,326.00 | $0.00 | $0.00 | ||||||
7 | Site Restoration | 1 | L.S. | $4,075.00 | $4,075.00 | $0.00 | $0.00 | ||||||
$24,996.00 | $0.00 | $0.00 | |||||||||||
4/18/2024