IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Rathbun Wildlife Unit  Date: 6/17/2021  Project No.  
  FEMA Projects  County:   APPANOOSE  Time: 11:00 a.m.  21-05-04-02

 

 
1
2
3
Estimated Cost: $490,000.00
Contractor: 
Boyle Built Enterprises LLCKeller Excavating, Inc.Cole Construction Co Inc
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 33837 142nd St
1133 155th St
24100 Queen Ave
Selma IA  52588Boone IA  50036Keosauqua IA  52565
Plan Sets Requested: 0
Quantities
641777313351521205563195923103
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Revetment, Class E (Colyn Emergency Spillway)226.4Tons$45.95$10,403.08 $51.65$11,693.56 $68.65$15,542.36 
2Mobilization (Colyn Emergency Spillway)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
3Sediment, Removal and Disposal (Brown Slough)1286.7C.Y.$3.00$3,860.10 $10.18$13,098.606 $15.00$19,300.50 
4Revetment, Class E (Brown Slough)1823.9Tons$45.95$83,808.205 $51.65$94,204.435 $49.15$89,644.685 
5Mobilization (Brown Slough)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
6Earthwork, Fill Hauled and Placed (Brown Slough Dike)37C.Y.$45.00$1,665.00 $22.00$814.00 $60.00$2,220.00 
7Revetment, Class E (Brown Slough Dike)721.9Tons$45.95$33,171.305 $51.65$37,286.135 $52.15$37,647.085 
8Mobilization (Brown Slough Dike)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
9Revetment, Class E (North County Line Road)316.6Tons$45.45$14,389.47 $51.65$16,352.39 $53.65$16,985.59 
10Traffic Control (North County Line Road)1L.S.$300.00$300.00 $1,100.00$1,100.00 $2,000.00$2,000.00 
11Mobilization (North County Line Road)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
12Granular Surfacing on Road, 2" Roadstone (Atwells)28.6Tons$25.95$742.17 $25.25$722.15 $27.20$777.92 
13Revetment, Class E (Atwells)95.2Tons$43.45$4,136.44 $48.90$4,655.28 $52.65$5,012.28 
14Traffic Control (Atwells)1L.S.$800.00$800.00 $1,100.00$1,100.00 $1,500.00$1,500.00 
15Mobilization (Atwells)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
16Culvert, CMP Roadway, 48" (Wind n Waves)40L.F.$180.00$7,200.00 $198.00$7,920.00 $149.76$5,990.40 
17Revetment, Class E (Wind n Waves)574.4Tons$42.95$24,670.48 $48.35$27,772.24 $49.65$28,518.96 
18Granular Surfacing on Road, 1-1/4" Roadstone (Wind n Waves)378Tons$20.95$7,919.10 $24.15$9,128.70 $27.20$10,281.60 
19Traffic Control (Wind n Waves)1L.S.$800.00$800.00 $1,100.00$1,100.00 $1,500.00$1,500.00 
20Mobilization (Wind n Waves)1L.S.$300.00$300.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
21Granular Surfacing on Road, 1-1/4" Roadstone (Bridgeview)317.3Tons$20.45$6,488.785 $23.60$7,488.28 $27.20$8,630.56 
22Culvert, CMP Roadway, 24" (Bridgeview)40L.F.$90.00$3,600.00 $88.50$3,540.00 $78.76$3,150.40 
23Revetment, Class E (Bridgeview)3142.1Tons$42.95$134,953.195 $48.35$151,920.535 $45.65$143,436.865 
24Traffic Control (Bridgeview)1L.S.$800.00$800.00 $1,100.00$1,100.00 $2,500.00$2,500.00 
25Mobilization (Bridgeview)1L.S.$10,500.00$10,500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
26Sediment, Removal and Disposal (Sedan Bottoms - Site 1)517.2C.Y.$5.25$2,715.30 $11.00$5,689.20 $25.00$12,930.00 
27Mobilization (Sedan Bottoms - Site 1)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
28Culvert, CMP Roadway, 42" (Sedan Bottoms - Site 2)40L.F.$150.00$6,000.00 $183.70$7,348.00 $129.56$5,182.40 
29Earthwork, Fill Hauled and Placed (Sedan Bottoms - Site 2)118.5C.Y.$17.00$2,014.50 $13.20$1,564.20 $50.00$5,925.00 
30Revetment, Class E (Sedan Bottoms - Site 2)26.2Tons$48.45$1,269.39 $54.40$1,425.28 $65.65$1,720.03 
31Mobilization (Sedan Bottoms - Site 2)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
32Erosion Stone (Sedan Bottoms - Site 3)54Tons$48.45$2,616.30 $54.40$2,937.60 $59.65$3,221.10 
33Mobilization (Sedan Bottoms - Site 3)1L.S.$500.00$500.00 $1,650.00$1,650.00 $3,000.00$3,000.00 
      $369,122.82  $426,460.591  $453,617.735 
 
4
5
6
Estimated Cost: $490,000.00
Contractor: 
RW Excavating Solutions, LCBerkey Homebuilders dba Concrete ProfessionalsLegacy Corporation of IL
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 13293 S 88th Ave W
PO BOX 7
16322 Barstow Rd
Prairie City IA  50228Altoona IA  50009East Moline IL  61244
Plan Sets Requested: 0
Quantities
515994264851596731363092031094
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Revetment, Class E (Colyn Emergency Spillway)226.4Tons$56.30$12,746.32 $71.40$16,164.96 $62.60$14,172.64 
2Mobilization (Colyn Emergency Spillway)1L.S.$6,000.00$6,000.00 $3,000.00$3,000.00 $1,800.00$1,800.00 
3Sediment, Removal and Disposal (Brown Slough)1286.7C.Y.$18.00$23,160.60 $11.00$14,153.70 $19.60$25,219.32 
4Revetment, Class E (Brown Slough)1823.9Tons$56.30$102,685.57 $62.75$114,449.725 $59.80$109,069.22 
5Mobilization (Brown Slough)1L.S.$5,000.00$5,000.00 $4,500.00$4,500.00 $8,400.00$8,400.00 
6Earthwork, Fill Hauled and Placed (Brown Slough Dike)37C.Y.$40.00$1,480.00 $40.70$1,505.90 $32.00$1,184.00 
7Revetment, Class E (Brown Slough Dike)721.9Tons$56.30$40,642.97 $60.85$43,927.615 $61.30$44,252.47 
8Mobilization (Brown Slough Dike)1L.S.$3,000.00$3,000.00 $3,000.00$3,000.00 $2,100.00$2,100.00 
9Revetment, Class E (North County Line Road)316.6Tons$56.30$17,824.58 $67.70$21,433.82 $71.90$22,763.54 
10Traffic Control (North County Line Road)1L.S.$1,500.00$1,500.00 $1,200.00$1,200.00 $2,200.00$2,200.00 
11Mobilization (North County Line Road)1L.S.$1,500.00$1,500.00 $3,000.00$3,000.00 $2,100.00$2,100.00 
12Granular Surfacing on Road, 2" Roadstone (Atwells)28.6Tons$45.00$1,287.00 $52.35$1,497.21 $27.50$786.50 
13Revetment, Class E (Atwells)95.2Tons$56.30$5,359.76 $75.62$7,199.024 $92.40$8,796.48 
14Traffic Control (Atwells)1L.S.$1,000.00$1,000.00 $1,000.00$1,000.00 $1,350.00$1,350.00 
15Mobilization (Atwells)1L.S.$1,000.00$1,000.00 $3,000.00$3,000.00 $1,650.00$1,650.00 
16Culvert, CMP Roadway, 48" (Wind n Waves)40L.F.$135.00$5,400.00 $382.50$15,300.00 $276.20$11,048.00 
17Revetment, Class E (Wind n Waves)574.4Tons$56.30$32,338.72 $67.30$38,657.12 $66.50$38,197.60 
18Granular Surfacing on Road, 1-1/4" Roadstone (Wind n Waves)378Tons$31.50$11,907.00 $55.00$20,790.00 $34.60$13,078.80 
19Traffic Control (Wind n Waves)1L.S.$1,000.00$1,000.00 $1,300.00$1,300.00 $9,500.00$9,500.00 
20Mobilization (Wind n Waves)1L.S.$1,500.00$1,500.00 $3,500.00$3,500.00 $4,650.00$4,650.00 
21Granular Surfacing on Road, 1-1/4" Roadstone (Bridgeview)317.3Tons$31.50$9,994.95 $39.50$12,533.35 $36.60$11,613.18 
22Culvert, CMP Roadway, 24" (Bridgeview)40L.F.$58.50$2,340.00 $138.00$5,520.00 $214.80$8,592.00 
23Revetment, Class E (Bridgeview)3142.1Tons$56.30$176,900.23 $67.65$212,563.065 $72.80$228,744.88 
24Traffic Control (Bridgeview)1L.S.$1,000.00$1,000.00 $1,500.00$1,500.00 $9,500.00$9,500.00 
25Mobilization (Bridgeview)1L.S.$1,000.00$1,000.00 $4,500.00$4,500.00 $10,200.00$10,200.00 
26Sediment, Removal and Disposal (Sedan Bottoms - Site 1)517.2C.Y.$20.00$10,344.00 $55.00$28,446.00 $29.30$15,153.96 
27Mobilization (Sedan Bottoms - Site 1)1L.S.$2,000.00$2,000.00 $3,000.00$3,000.00 $3,000.00$3,000.00 
28Culvert, CMP Roadway, 42" (Sedan Bottoms - Site 2)40L.F.$120.00$4,800.00 $333.00$13,320.00 $429.70$17,188.00 
29Earthwork, Fill Hauled and Placed (Sedan Bottoms - Site 2)118.5C.Y.$20.00$2,370.00 $22.00$2,607.00 $32.00$3,792.00 
30Revetment, Class E (Sedan Bottoms - Site 2)26.2Tons$56.30$1,475.06 $90.00$2,358.00 $75.00$1,965.00 
31Mobilization (Sedan Bottoms - Site 2)1L.S.$2,000.00$2,000.00 $3,000.00$3,000.00 $2,500.00$2,500.00 
32Erosion Stone (Sedan Bottoms - Site 3)54Tons$48.00$2,592.00 $61.30$3,310.20 $100.00$5,400.00 
33Mobilization (Sedan Bottoms - Site 3)1L.S.$1,000.00$1,000.00 $2,000.00$2,000.00 $4,000.00$4,000.00 
      $494,148.76  $613,236.689  $643,967.59 
 



 

12/18/2025