IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Red Rock Wildlife Unit  Date: 8/27/2020  Project No.  
  Runnells Marsh outlet repair  County:   POLK  Time: 3:00 p.m.  21-05-77-02

 

 
1
2
3
Estimated Cost: $16,000.00
Contractor: 
Sterk Excavating IncHaworth Land Construction
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, 117 180th Ave
12981 Quaker St

Otley IA  50214Indianola IA  50125  
Plan Sets Requested: 0
Quantities
64141601105152494747
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Handrail Repairs1L.S.$4,800.00$4,800.00 $6,000.00$6,000.00 $0.00 
2Excavation69C.Y.$10.00$690.00 $10.00$690.00 $0.00 
3Class E Riprap16Tons$100.00$1,600.00 $80.00$1,280.00 $0.00 
4Mobilization1L.S.$5,000.00$5,000.00 $5,000.00$5,000.00 $0.00 
      $12,090.00  $12,970.00  $0.00 
 



 

4/23/2024