IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Dolliver Memorial | Date: 6/11/2020 | Project No. |
2019 Boat Ramp Flood Repairs Rebid | County: | WEBSTER | Time: 3:00 p.m. | 20-02-94-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $60,000.00 | Contractor: | Central Iowa Dirt & Demo LLC | Richards Construction Co., Inc. | Boulder Contracting LLC | |||||||||
Funding Source: 75% Federal-FEMA 1, 25% Executive Council, | 3075 Hancock Ave | 2721 Sierra Ave | 606 E 1st St | ||||||||||
Woolstock IA 50599 | Sac City IA 50583 | Grundy Center IA 50638 | |||||||||||
Plan Sets Requested: 0 | Quantities | 3192907479 | 7126624421 | 3192433285 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 | $4,000.00 | $4,000.00 | ||||
2 | Class "E" Revetment | 435 | Tons | $40.00 | $17,400.00 | $31.00 | $13,485.00 | $43.00 | $18,705.00 | ||||
3 | 3"-6" Erosion Stone | 651 | Tons | $40.00 | $26,040.00 | $35.00 | $22,785.00 | $35.80 | $23,305.80 | ||||
4 | Class "A" Rock Surfacing | 395 | Tons | $22.00 | $8,690.00 | $39.00 | $15,405.00 | $28.00 | $11,060.00 | ||||
5 | Silt Removal and Disposal | 111 | C.Y. | $10.00 | $1,110.00 | $11.00 | $1,221.00 | $24.60 | $2,730.60 | ||||
$55,240.00 | $55,896.00 | $59,801.40 | |||||||||||