IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Honey Creek State Park | Date: 2/18/2021 | Project No. |
Wastewater Conveyance System | County: | APPANOOSE | Time: 11:00 a.m. | 20-05-04-06 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $220,000.00 | Contractor: | Hartland Bobcat Services LLC | Vicker Drilling, LLC | Joiner Construction Co. Inc. | |||||||||
Funding Source: 100% Infrastructure, | 19561 205th Ave | 2151 Cherry St Rd | 11996 490th St PO Box 27 | ||||||||||
Centerville IA 52544 | Creston IA 50801 | Plano IA 52581 | |||||||||||
Plan Sets Requested: 2 | Quantities | 6418952127 | 6412022728 | 6416492646 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $8,500.00 | $8,500.00 | $5,500.00 | $5,500.00 | $10,000.00 | $10,000.00 | ||||
2 | 4-INCH SANITARY SEWER SERVICE (PVC SCH 40) WITH CONNECTIONS | 20 | L.F. | $42.50 | $850.00 | $28.50 | $570.00 | $50.00 | $1,000.00 | ||||
3 | REMOVE & PLUG 8" SEWER AT MH 11 | 1 | L.S. | $415.00 | $415.00 | $500.00 | $500.00 | $500.00 | $500.00 | ||||
4 | INSTALL NEW DUPLEX LIFT STATION COMPLETE WITH CONTROLS & VALVE PIT | 1 | L.S. | $35,301.00 | $35,301.00 | $37,258.00 | $37,258.00 | $35,000.00 | $35,000.00 | ||||
5 | ELECTRICAL CONNECTION FROM TRANSFORMER (APROX. 50 FT.) | 1 | L.S. | $2,761.35 | $2,761.35 | $500.00 | $500.00 | $5,500.00 | $5,500.00 | ||||
6 | 3 INCH HDPE DR 11 FORCEMAIN WITH #12 TRACER WIRE | 3289 | L.F. | $16.09 | $52,920.01 | $17.00 | $55,913.00 | $19.00 | $62,491.00 | ||||
7 | AIR RELIEF VALVE COMPLETE WITH MANHOLE | 1 | L.S. | $14,513.88 | $14,513.88 | $12,176.00 | $12,176.00 | $8,500.00 | $8,500.00 | ||||
8 | CONNECT FORCEMAIN WITH MH No. 2 | 2 | Each | $430.00 | $860.00 | $500.00 | $1,000.00 | $1,500.00 | $3,000.00 | ||||
9 | DISCONNECT AND PLUG 8" SEWER AT MH No. 2 | 1 | L.S. | $415.00 | $415.00 | $500.00 | $500.00 | $500.00 | $500.00 | ||||
10 | REPLACE CONE SECTION OF MH No.2, 48" DIA | 1 | L.S. | $2,518.00 | $2,518.00 | $1,500.00 | $1,500.00 | $2,250.00 | $2,250.00 | ||||
11 | REPLACE EXISTING SEWER BETWEEN MH 16 TO MH 15 & MH 15 TO PROPOSED LIFT STATION (INCLUDING CONNECTIONS) WITH 4"PVC SCH 40. | 307 | L.F. | $17.70 | $5,433.90 | $19.88 | $6,103.16 | $35.00 | $10,745.00 | ||||
12 | REMOVE MH 14 & DISPOSE OFF SITE | 1 | L.S. | $1,300.00 | $1,300.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | ||||
13 | INSTALL NEW E-ONE SIMPLEX LIFT STATION WITH CONTROLLER (OR APPROVED EQUIVALENT) | 1 | L.S. | $8,794.44 | $8,794.44 | $17,000.00 | $17,000.00 | $12,000.00 | $12,000.00 | ||||
14 | ELECTRICAL CONNECTION FROM TRANSFORMER (APROX. 100 FT.) | 1 | L.S. | $2,950.17 | $2,950.17 | $900.00 | $900.00 | $4,500.00 | $4,500.00 | ||||
15 | 2 INCH HDPE DR 11 FORCEMAIN WITH #12 TRACER WIRE | 1094 | L.F. | $13.47 | $14,736.18 | $16.00 | $17,504.00 | $16.00 | $17,504.00 | ||||
16 | AIR RELIEF VALVE COMPLETE WITH MANHOLE | 1 | L.S. | $14,513.88 | $14,513.88 | $12,176.00 | $12,176.00 | $8,500.00 | $8,500.00 | ||||
17 | SITE RESTORATION FOR COMPLETE SITE | 1 | L.S. | $4,800.00 | $4,800.00 | $4,500.00 | $4,500.00 | $10,000.00 | $10,000.00 | ||||
$171,582.81 | $175,600.16 | $193,990.00 | |||||||||||
Hartland Bobcat Services LLC, Centerville, IA
4/25/2024