IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Blue Lake | Date: 6/17/2021 | Project No. |
| Dredging | County: | MONONA | Time: 11:00 a.m. | 22-01-67-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,500,000.00 | Contractor: | Dredge America, Inc. | J.F. Brennan Company, Inc. | Dubuque Barge & Fleeting Service Company dba Newt | |||||||||
| Funding Source: 100% Lake Restoration, | 9555 NW Highway | 818 Bainbridge St | 5 Jones St | ||||||||||
| North Kansas City MO 64153 | La Crosse WI 54603 | Dubuque IA 52001 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 8163303100 | 6087847173 | 5635571855 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION/DEMOBILIZATION | 1 | L.S. | $285,500.00 | $285,500.00 | $660,000.00 | $660,000.00 | $450,000.00 | $450,000.00 | ||||
| 2 | SAFETY PLAN | 1 | L.S. | $15,000.00 | $15,000.00 | $6,500.00 | $6,500.00 | $22,000.00 | $22,000.00 | ||||
| 3 | DREDGING | 383700 | C.Y. | $3.20 | $1,227,840.00 | $4.00 | $1,534,800.00 | $5.30 | $2,033,610.00 | ||||
| 4 | SWPPP PREPARATION AND MANAGEMENT | 1 | L.S. | $45,000.00 | $45,000.00 | $4,500.00 | $4,500.00 | $15,000.00 | $15,000.00 | ||||
| 5 | GRANULAR SURFACING | 130 | Tons | $50.00 | $6,500.00 | $50.00 | $6,500.00 | $80.00 | $10,400.00 | ||||
| 6 | REMOVAL/REPLACEMENT OF PAVEMENT | 100 | S.Y. | $80.00 | $8,000.00 | $50.00 | $5,000.00 | $225.00 | $22,500.00 | ||||
| $1,587,840.00 | $2,217,300.00 | $2,553,510.00 | |||||||||||
| Alternate | |||||||||||||
| 7 | BID ALTERNATE 1 - DREDGING | 50000 | C.Y. | $3.20 | $160,000.00 | $4.00 | $200,000.00 | $4.80 | $240,000.00 | ||||
| $1,747,840.00 | $2,417,300.00 | $2,793,510.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $2,500,000.00 | Contractor: | Magellan Dredging, Inc. | Veit & Company, Inc. | Southwind Construction Corporation | |||||||||
| Funding Source: 100% Lake Restoration, | 1723 Ryon Falls Dr | 14000 Veit Place | 14649 Hwy 41 N, Ste 100 | ||||||||||
| Richmond TX 77469 | Rogers MN 55374 | Evansville IN 47725 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 8324539891 | 7634282242 | 8128677720 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION/DEMOBILIZATION | 1 | L.S. | $544,286.00 | $544,286.00 | $510,000.00 | $510,000.00 | $714,636.56 | $714,636.56 | ||||
| 2 | SAFETY PLAN | 1 | L.S. | $2,000.00 | $2,000.00 | $40,000.00 | $40,000.00 | $278.20 | $278.20 | ||||
| 3 | DREDGING | 383700 | C.Y. | $5.09 | $1,953,033.00 | $6.00 | $2,302,200.00 | $7.18 | $2,754,966.00 | ||||
| 4 | SWPPP PREPARATION AND MANAGEMENT | 1 | L.S. | $10,000.00 | $10,000.00 | $30,000.00 | $30,000.00 | $347.75 | $347.75 | ||||
| 5 | GRANULAR SURFACING | 130 | Tons | $86.12 | $11,195.60 | $30.00 | $3,900.00 | $42.08 | $5,470.40 | ||||
| 6 | REMOVAL/REPLACEMENT OF PAVEMENT | 100 | S.Y. | $428.00 | $42,800.00 | $225.00 | $22,500.00 | $507.25 | $50,725.00 | ||||
| Alternate | |||||||||||||
| 7 | BID ALTERNATE 1 - DREDGING | 50000 | C.Y. | $5.25 | $262,500.00 | $6.00 | $300,000.00 | $7.39 | $369,500.00 | ||||
| $2,825,814.60 | $3,208,600.00 | $3,895,923.91 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $2,500,000.00 | Contractor: | Michels Corporation | |||||||||||
| Funding Source: 100% Lake Restoration, | 817 West Main St | ||||||||||||
| Brownsville WI 53006 | |||||||||||||
| Plan Sets Requested: 2 | Quantities | 9209244300 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION/DEMOBILIZATION | 1 | L.S. | $839,555.12 | $839,555.12 | $0.00 | $0.00 | ||||||
| 2 | SAFETY PLAN | 1 | L.S. | $20,127.77 | $20,127.77 | $0.00 | $0.00 | ||||||
| 3 | DREDGING | 383700 | C.Y. | $10.50 | $4,028,850.00 | $0.00 | $0.00 | ||||||
| 4 | SWPPP PREPARATION AND MANAGEMENT | 1 | L.S. | $37,499.13 | $37,499.13 | $0.00 | $0.00 | ||||||
| 5 | GRANULAR SURFACING | 130 | Tons | $52.88 | $6,874.40 | $0.00 | $0.00 | ||||||
| 6 | REMOVAL/REPLACEMENT OF PAVEMENT | 100 | S.Y. | $187.50 | $18,750.00 | $0.00 | $0.00 | ||||||
| Alternate | |||||||||||||
| 7 | BID ALTERNATE 1 - DREDGING | 50000 | C.Y. | $10.50 | $525,000.00 | $0.00 | $0.00 | ||||||
| $5,476,656.42 | $0.00 | $0.00 | |||||||||||
12/18/2025