IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Ahquabi | Date: 7/21/2022 | Project No. |
| Road Reconstruction Project | County: | WARREN | Time: 11:00 a.m. | 21-05-91-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,900,000.00 | Contractor: | Iowa Civil Contracting Inc | C J Moyna & Sons LLC | Concrete Technologies Inc | |||||||||
| Funding Source: 85% Park & Institutional Road Fund, 15% Infrastructure, | 1106 3rd St | 34412 Hwy 13 | 1001 SE 37th St | ||||||||||
| Victor IA 52347 | Elkader IA 52043 | Grimes IA 50111 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 319-647-3561 | 563-245-1442 | 515-252-1650 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Demolition | 1 | L.S. | $16,500.00 | $16,500.00 | $26,000.00 | $26,000.00 | $28,600.00 | $28,600.00 | ||||
| 2 | Clearing and Grubbing | 1 | L.S. | $23,100.00 | $23,100.00 | $58,000.00 | $58,000.00 | $63,800.00 | $63,800.00 | ||||
| 3 | Tree Clearing | 1 | L.S. | $7,920.00 | $7,920.00 | $72,000.00 | $72,000.00 | $79,200.00 | $79,200.00 | ||||
| 4 | Full Depth Saw Cut | 89 | L.F. | $5.00 | $445.00 | $20.00 | $1,780.00 | $6.60 | $587.40 | ||||
| 5 | HMA Pavement Removal | 23046 | S.Y. | $5.00 | $115,230.00 | $11.90 | $274,247.40 | $13.25 | $305,359.50 | ||||
| 6 | PCC Removal | 214 | S.Y. | $11.02 | $2,358.28 | $36.00 | $7,704.00 | $39.75 | $8,506.50 | ||||
| 7 | Grading | 1 | L.S. | $100,000.00 | $100,000.00 | $300,000.00 | $300,000.00 | $330,000.00 | $330,000.00 | ||||
| 8 | 12-inch Filter Sock | 2225 | L.F. | $3.30 | $7,342.50 | $3.00 | $6,675.00 | $3.50 | $7,787.50 | ||||
| 9 | Type SW-401 Circular Storm MH W/SW-602 Type E Casting | 1 | Each | $8,515.10 | $8,515.10 | $10,500.00 | $10,500.00 | $11,550.00 | $11,550.00 | ||||
| 10 | Type SW-503 Single Grate Intake W/MH & SW-603 Type 'R & E' Castings | 1 | Each | $5,882.80 | $5,882.80 | $8,000.00 | $8,000.00 | $8,800.00 | $8,800.00 | ||||
| 11 | Type SW-506 Double Grate Intake W/MH & SW-603 Type 'R & E' Castings | 4 | Each | $9,991.30 | $39,965.20 | $10,500.00 | $42,000.00 | $11,550.00 | $46,200.00 | ||||
| 12 | Type SW-512 Circular Area Intake W/SW-604 Type 3A Casting | 1 | Each | $2,310.00 | $2,310.00 | $3,500.00 | $3,500.00 | $5,600.00 | $5,600.00 | ||||
| 13 | Type SW-512 Circular Area Intake W/SW-604 Type 3B Casting | 1 | Each | $2,904.00 | $2,904.00 | $3,500.00 | $3,500.00 | $3,850.00 | $3,850.00 | ||||
| 14 | Type SW-512 Circular Area Intake W/SW-604 Type 5 Casting | 1 | Each | $4,505.60 | $4,505.60 | $3,500.00 | $3,500.00 | $3,850.00 | $3,850.00 | ||||
| 15 | Type SW-513 Open Sided Area Intake W/SW-602 Type G Casting | 4 | Each | $14,520.00 | $58,080.00 | $10,500.00 | $42,000.00 | $11,550.00 | $46,200.00 | ||||
| 16 | 6-inch Slotted PVC Subdrain | 323 | L.F. | $38.50 | $12,435.50 | $36.00 | $11,628.00 | $39.75 | $12,839.25 | ||||
| 17 | Subdrain Cleanout Type A-2 | 6 | Each | $385.00 | $2,310.00 | $500.00 | $3,000.00 | $550.00 | $3,300.00 | ||||
| 18 | 12-inch RCP Class III | 436 | L.F. | $63.80 | $27,816.80 | $64.00 | $27,904.00 | $70.50 | $30,738.00 | ||||
| 19 | 15-inch RCP Class III | 185 | L.F. | $72.60 | $13,431.00 | $70.00 | $12,950.00 | $77.00 | $14,245.00 | ||||
| 20 | 18-inch RCP Class III | 122 | L.F. | $82.50 | $10,065.00 | $84.00 | $10,248.00 | $92.50 | $11,285.00 | ||||
| 21 | 24-inch RCP Class III | 344 | L.F. | $118.80 | $40,867.20 | $123.00 | $42,312.00 | $135.50 | $46,612.00 | ||||
| 22 | 30-inch RCP Class III | 91 | L.F. | $181.50 | $16,516.50 | $192.00 | $17,472.00 | $211.25 | $19,223.75 | ||||
| 23 | 36-inch RCP Class III | 339 | L.F. | $223.30 | $75,698.70 | $578.00 | $195,942.00 | $636.00 | $215,604.00 | ||||
| 24 | 12-inch RCP Class III FES | 7 | Each | $2,640.00 | $18,480.00 | $1,600.00 | $11,200.00 | $1,760.00 | $12,320.00 | ||||
| 25 | 18-inch RCP Class III FES W/Footing & Apron Guard | 2 | Each | $5,082.00 | $10,164.00 | $4,100.00 | $8,200.00 | $4,510.00 | $9,020.00 | ||||
| 26 | 24-inch RCP Class III FES W/Footing & Apron Guard | 2 | Each | $6,296.40 | $12,592.80 | $5,100.00 | $10,200.00 | $5,610.00 | $11,220.00 | ||||
| 27 | 36-inch RCP Class III FES W/Footing & Apron Guard | 7 | Each | $9,350.00 | $65,450.00 | $7,700.00 | $53,900.00 | $8,470.00 | $59,290.00 | ||||
| 28 | Flexstorm #62LCBFX Inlet Filter (Or Approved Equal) | 18 | Each | $220.00 | $3,960.00 | $200.00 | $3,600.00 | $220.00 | $3,960.00 | ||||
| 29 | Flexstorm #62MRDFX Inlet Filter (Or Approved Equal) | 4 | Each | $330.00 | $1,320.00 | $300.00 | $1,200.00 | $330.00 | $1,320.00 | ||||
| 30 | Flexstorm #62LRDFX Inlet Filter (Or Approved Equal) | 2 | Each | $385.00 | $770.00 | $350.00 | $700.00 | $385.00 | $770.00 | ||||
| 31 | 3/8" Minus Pea Gravel | 40 | Tons | $74.80 | $2,992.00 | $90.00 | $3,600.00 | $99.00 | $3,960.00 | ||||
| 32 | Class 'D' Riprap | 125 | Tons | $82.50 | $10,312.50 | $110.00 | $13,750.00 | $121.00 | $15,125.00 | ||||
| 33 | Special Backfill/Granular Base | 8718 | Tons | $37.94 | $330,760.92 | $23.10 | $201,385.80 | $25.50 | $222,309.00 | ||||
| 34 | 6-inch Non-Reinforced PCC | 4930 | S.Y. | $80.23 | $395,533.90 | $50.00 | $246,500.00 | $50.00 | $246,500.00 | ||||
| 35 | 7-inch Non-Reinforced PCC | 22002 | S.Y. | $57.20 | $1,258,514.40 | $54.00 | $1,188,108.00 | $54.00 | $1,188,108.00 | ||||
| 36 | 6-Inch Standard Curb and 2-Inch Drop Curb | 701 | L.F. | $32.90 | $23,062.90 | $17.00 | $11,917.00 | $17.00 | $11,917.00 | ||||
| 37 | Granular Base-Sidewalks | 53.1 | Tons | $67.00 | $3,557.70 | $90.00 | $4,779.00 | $99.25 | $5,270.175 | ||||
| 38 | 5-inch Non-Reinforced PCC Sidewalks | 262.6 | S.Y. | $114.00 | $29,936.40 | $76.00 | $19,957.60 | $76.00 | $19,957.60 | ||||
| 39 | Class 'A' Crushed Stone | 25 | Tons | $82.50 | $2,062.50 | $70.00 | $1,750.00 | $77.00 | $1,925.00 | ||||
| 40 | Traffic Control | 1 | L.S. | $7,700.00 | $7,700.00 | $38,000.00 | $38,000.00 | $7,700.00 | $7,700.00 | ||||
| 41 | Seeding, Fertilizing and Mulching | 3.5 | Acres | $6,875.00 | $24,062.50 | $6,250.00 | $21,875.00 | $6,875.00 | $24,062.50 | ||||
| 42 | Street Signage | 1 | L.S. | $7,700.00 | $7,700.00 | $9,000.00 | $9,000.00 | $7,700.00 | $7,700.00 | ||||
| 43 | Handicap Parking Signage | 1 | L.S. | $5,500.00 | $5,500.00 | $6,500.00 | $6,500.00 | $5,500.00 | $5,500.00 | ||||
| 44 | Street Pavement Markings | 1 | L.S. | $3,850.00 | $3,850.00 | $4,000.00 | $4,000.00 | $3,850.00 | $3,850.00 | ||||
| 45 | Parking Space Pavement Striping, Handicap Parking Cross Hatch Markings | 1 | L.S. | $13,750.00 | $13,750.00 | $15,000.00 | $15,000.00 | $13,750.00 | $13,750.00 | ||||
| 46 | 6' Concrete Parking Wheel Stops | 4 | Each | $300.00 | $1,200.00 | $1,200.00 | $4,800.00 | $165.00 | $660.00 | ||||
| 47 | Concrete Bollards | 2 | Each | $500.00 | $1,000.00 | $450.00 | $900.00 | $266.75 | $533.50 | ||||
| 48 | Construction Survey Staking and As-Built Survey | 1 | Each | $59,400.00 | $59,400.00 | $65,000.00 | $65,000.00 | $59,400.00 | $59,400.00 | ||||
| 49 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $3,960.00 | $3,960.00 | $3,600.00 | $3,600.00 | $3,960.00 | $3,960.00 | ||||
| 50 | Mobilization | 1 | L.S. | $230,000.00 | $230,000.00 | $450,000.00 | $450,000.00 | $438,174.32 | $438,174.32 | ||||
| $3,121,791.70 | $3,580,284.80 | $3,681,999.995 | |||||||||||